Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - RUE DU PRESBYTERE
Description: Install water main
Start date: Monday, 11/11/24 End date: Friday, 20/12/24 Timing: All Day
Promoter: Guernsey Water Contractor: Guernsey Water
Bus Routes Affected: P2, 51 Cycle Access: Yes

CASTEL - RUETTE DE TOUILLETS ( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
Description: Work starting 08:00 AM on Sat 19 Aug 23 and finishing 05:00 PM on Tue 31 Dec 24 - Investigation and repairs to roadside wall
Start date: Saturday, 19/08/23 End date: Tuesday, 31/12/24 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

Emergency Activity - ST. SAVIOUR - ROUTE DE LA PERELLE
Description: Road and wall repairs
Start date: Thursday, 14/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Geomarine
Bus Routes Affected: 60, 61, 91, 92 Cycle Access: Yes

FOREST - LES REBOUQUETS
Description: Work starting 07:00 AM on Wed 09 Oct 24 and finishing 05:00 PM on Fri 20 Dec 24 - High and low voltage cable upgrade and duct lay
Start date: Wednesday, 09/10/24 End date: Friday, 20/12/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Cycle Access: No

ST. ANDREW - LA VILLIAZE ROAD
Description: Work starting 08:00 AM on Mon 18 Nov 24 and finishing 04:00 PM on Fri 22 Nov 24 - Chamber and duct installations
Start date: Monday, 18/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - BOUILLON LANE ( ST. GEORGE'S ESPLANADE to LE BOUET )
Description: Excavate blocked duct
Start date: Thursday, 21/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - HAVELET ( THE STRAND to HAUTEVILLE )
Description: Work starting 08:00 AM on Tue 01 Oct 24 and finishing 04:00 PM on Fri 17 Jan 25 - House demolition.
Start date: Tuesday, 01/10/24 End date: Friday, 17/01/25 Timing: All Day
Promoter: Bob Froome and Sons Contractor: Bob Froome and Sons
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LE BOUET
Description: Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
Start date: Wednesday, 16/10/24 End date: Thursday, 16/01/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LE BOUET
Description: Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
Start date: Wednesday, 16/10/24 End date: Thursday, 16/01/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LE BOUET
Description: Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
Start date: Wednesday, 16/10/24 End date: Thursday, 16/01/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - LES PETITES FONTAINES ( MOUNT HERMON to VALNORD ROAD )
Description: Rebuild roadside wall
Start date: Monday, 18/11/24 End date: Monday, 02/12/24 Timing: All Day
Promoter: TNT Stonemasons Contractor: TNT Stonemasons
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LOWER CANICHERS ( LE TRUCHOT to DOYLE STREET )
Description: Work starting 08:00 AM on Mon 30 Sep 24 and finishing 07:00 AM on Mon 28 Apr 25 - building repair and refit
Start date: Monday, 30/09/24 End date: Monday, 28/04/25 Timing: All Day
Promoter: Ravenscroft Construction Ltd Contractor: Ravenscroft Construction Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - THE STRAND
Description: Scaffold for construction; Property: La Coquere; Purpose: Demolition / New Build
Start date: Wednesday, 10/07/24 End date: Saturday, 12/04/25 Timing: All Day
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - UPPER MANSELL STREET ( PARK STREET to TRINITY SQUARE )
Description: Replacement supply line.
Start date: Monday, 18/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - ROUTE DE LIHOU ( RUE DU LONGFRIE to RUE DES GRANDES RUES )
Description: Work starting 09:00 AM on Thu 29 Aug 24 and finishing 05:00 PM on Sat 15 Mar 25 - Road blocked due to collapsed granite wall approx 10m from the Route de Lihou and Rue du Longfrie junction, near property Longfrie House.
Start date: Thursday, 29/08/24 End date: Saturday, 15/03/25 Timing: All Day
Promoter: Traffic and Highways Contractor: Traffic and Highways
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DES PRES ( RUE DES RAIES to RUE DES LANDES )
Description: Work starting 07:00 AM on Mon 18 Nov 24 and finishing 04:00 PM on Fri 22 Nov 24 - Tree felling
Start date: Monday, 18/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Guernsey Tree Service Ltd Contractor: Guernsey Tree Service Ltd
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - BROCK ROAD ( RONDE CHEMINEE to NEW ROAD )
Description: Repairs to roadside wall.
Start date: Monday, 18/11/24 End date: Friday, 29/11/24 Timing: Between AM and PM Peaks
Promoter: Stoneworks Ltd Contractor: Stoneworks Ltd
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LES MARTINS
Description: Low voltage cable upgrade
Start date: Monday, 04/11/24 End date: Friday, 13/12/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: 31, 32 Cycle Access: Dismount past works

ST. SAMPSON - ROUTE CARRE
Description: Work starting 07:00 AM on Sat 26 Oct 24 and finishing 03:00 PM on Fri 22 Nov 24 - Distribution pillar installation and low voltage cabling upgrade
Start date: Saturday, 26/10/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: P2, 13, 21, N1, Cycle Access: Dismount past works

ST. SAMPSON - ROUTE CARRE; SANDY HOOK to BRAYE DU VALLE ( SANDY HOOK to BRAYE DU VALLE )
Description: Work starting 08:30 AM on Thu 21 Nov 24 and finishing 04:30 PM on Sun 24 Nov 24 - Install new water supply
Start date: Thursday, 21/11/24 End date: Sunday, 24/11/24 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: P2, 13, 21, N1, Cycle Access: Dismount past works

ST. SAVIOUR - LA BILOTERIE ROAD ( RUE DU CAMP DU DOUIT to RUE DES HURIAUX )
Description: Chamber installation
Start date: Wednesday, 20/11/24 End date: Thursday, 21/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - ROUTE DES DOMAINES ( RUE DU DOUIT MANCHOT to LES ROBERTS )
Description: Work starting 08:00 AM on Thu 21 Nov 24 and finishing 11:00 PM on Tue 26 Nov 24 - Chamber and duct installation
Start date: Thursday, 21/11/24 End date: Tuesday, 26/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 71 Cycle Access: Dismount past works

ST. SAVIOUR - RUE DES ISSUES
Description: Work starting 08:00 AM on Mon 18 Nov 24 and finishing 11:00 PM on Thu 21 Nov 24 - Chamber installations
Start date: Monday, 18/11/24 End date: Thursday, 21/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - RUE DU LORIER ( to ROUTE DES CLOS LANDAIS )
Description: Supply line upgrade
Start date: Wednesday, 20/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

VALE - CARRIERE LANE ( to LA ROUTE DU BRAYE )
Description: Low voltage cabling upgrade and new connections
Start date: Monday, 18/11/24 End date: Wednesday, 18/12/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: No

VALE - PORT SOIF LANE ( LES GRANDES MIELLES LANE to PORT SOIF ROAD )
Description: Road reconstruction and resurfacing
Start date: Monday, 04/11/24 End date: Friday, 20/12/24 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: 41 Cycle Access: Dismount past works

One Ways
ST. PETER PORT - LE BOUET
Description: Work starting 07:00 AM on Mon 23 Sep 24 and finishing 05:00 PM on Mon 30 Dec 24 - For construction of 3 flats
Start date: Monday, 23/09/24 End date: Monday, 30/12/24 Timing: All Day
Promoter: Just Build It Ltd Contractor: Just Build It Ltd
Bus Routes Affected: 31, 32 Cycle Access: Yes, in direction of one-way

Signals
CASTEL - RUE DES ETURS; RUE DU PREEL to RUE DES DESLISLES ( RUE DU PREEL to RUE DES DESLISLES )
Description: Work starting 08:00 AM on Wed 30 Oct 24 and finishing 05:00 PM on Fri 22 Nov 24 - Duct and chamber installations
Start date: Wednesday, 30/10/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - LA GRANDE RUE; LA BELLIEUSE to LES MERRIENNES ( LA BELLIEUSE to LES MERRIENNES )
Description: Work starting 07:30 AM and finishing 05:00 PM daily between Mon 18 Nov 24 and Fri 22 Nov 24 - Skips and concrete deliveries.
Start date: Monday, 18/11/24 End date: Friday, 22/11/24 Timing: Between AM and PM Peaks
Promoter: P and J Ogier (1991) Ltd Contractor: P and J Ogier (1991) Ltd
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LE GRAND BOUET; HOUGUE A LA PERRE to RUE DE CHATEAU ( HOUGUE A LA PERRE to RUE DE CHATEAU )
Description: Cut off service in footpath
Start date: Wednesday, 20/11/24 End date: Friday, 22/11/24 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
CASTEL - RUE DES GODDARDS ( VAZON ROAD to ROUTE DE LA MARE )
Description: service alterations
Start date: Monday, 25/11/24 End date: Wednesday, 27/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

Emergency Activity - ST. PIERRE DU BOIS - ROUTE DE LA LAGUE
Description: Repairs to defective bitmac around chamber lids
Start date: Friday, 22/11/24 End date: Saturday, 23/11/24 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: 61, 71, 91, 92, 93, 94, N3 Cycle Access: No

FOREST - LA RUE DES CROISEE ( LES MESSURIERS to LE BOURG )
Description: Chamber and duct installation
Start date: Monday, 25/11/24 End date: Friday, 29/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LA RUETTE DU NAVET ( ICART ROAD to SAINTS BAY ROAD )
Description: Chamber installation
Start date: Tuesday, 26/11/24 End date: Wednesday, 27/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LA RUETTE DU NAVET
Description: Chamber and duct installation
Start date: Wednesday, 27/11/24 End date: Friday, 06/12/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - LES CAMPS DU MOULIN ( VILLE AMPHREY to RUETTE RABEY )
Description: Road surface patch repairs
Start date: Monday, 25/11/24 End date: Friday, 29/11/24 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - LES CAMPS DU MOULIN ( RUE JACQUES GUILLE to RUE DE LA VALLEE )
Description: Work starting 07:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Fri 06 Dec 24 - Install new water services
Start date: Monday, 25/11/24 End date: Friday, 06/12/24 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - LES CAMPS DU MOULIN
Description: Work starting 08:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Fri 06 Dec 24 - Replace access cover on Camps du Moulin
Start date: Monday, 25/11/24 End date: Friday, 06/12/24 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - LES FRIETEAUX
Description: Work starting 07:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Fri 29 Nov 24 - Replacements of streetlights
Start date: Monday, 25/11/24 End date: Friday, 29/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - RUE CHARIOT
Description: Work starting 09:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Tue 26 Nov 24 - Duct installation
Start date: Monday, 25/11/24 End date: Tuesday, 26/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - RUE POUDREUSE; RUE CAUCHEZ to LES FRIETEAUX ( RUE CAUCHEZ to LES FRIETEAUX )
Description: Work starting 08:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Mon 02 Dec 24 - Replace 2 x failing chamber covers
Start date: Monday, 25/11/24 End date: Monday, 02/12/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - RUE POUDREUSE; RUE CAUCHEZ to LES FRIETEAUX ( RUE CAUCHEZ to LES FRIETEAUX )
Description: Work starting 07:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Mon 02 Dec 24 - Repair failed reinstatements around water meters
Start date: Monday, 25/11/24 End date: Monday, 02/12/24 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Yes

ST. PETER PORT - COLBORNE ROAD
Description: CCTV Camera Clean
Start date: Friday, 22/11/24 End date: Friday, 22/11/24 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 91, 92, 93, 94, 95, N3 Cycle Access: Yes

ST. PETER PORT - NEW PLACE ( VICTORIA ROAD to VAUVERT )
Description: Erecting scaffolding.
Start date: Monday, 25/11/24 End date: Thursday, 12/12/24 Timing: Between AM and PM Peaks
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - RUE A L`OR ( RICHMOND AVENUE to KINGS ROAD )
Description: Rue a L`Or substation installation and high voltage cable upgrade (Phase 1)
Start date: Monday, 25/11/24 End date: Friday, 13/12/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - VALNORD LANE
Description: Tree Surgery Works
Start date: Tuesday, 26/11/24 End date: Wednesday, 27/11/24 Timing: Between AM and PM Peaks
Promoter: Guernsey Tree Service Ltd Contractor: Guernsey Tree Service Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - ROUTE DES SAGES
Description: Work starting 07:30 AM on Mon 25 Nov 24 and finishing 04:00 PM on Fri 13 Dec 24 - Road resurfacing
Start date: Monday, 25/11/24 End date: Friday, 13/12/24 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: 61 Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DE LA POMARE ( RUE DES SALINES to RUE DE LA CACHE )
Description: Painting gable of house.
Start date: Thursday, 28/11/24 End date: Thursday, 28/11/24 Timing: Between AM and PM Peaks
Promoter: Event Hire Guernsey Ltd Contractor: Event Hire Guernsey Ltd
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DES MARCHEZ ( RUE DES REINES to RUE DES HECHES )
Description: Tree surgery works.
Start date: Monday, 25/11/24 End date: Monday, 25/11/24 Timing: Between AM and PM Peaks
Promoter: Guernsey Tree Service Ltd Contractor: Guernsey Tree Service Ltd
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DU VIDECOCQ ( RUE DES MARES to RUE DES REINES )
Description: Tree surgery works.
Start date: Thursday, 28/11/24 End date: Thursday, 28/11/24 Timing: Between AM and PM Peaks
Promoter: Arborcraft Ltd Contractor: Arborcraft Ltd
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - RUE ST PIERRE
Description: Chamber and duct installation
Start date: Wednesday, 27/11/24 End date: Friday, 06/12/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 71 Cycle Access: Dismount past works

ST. SAMPSON - COMMERCIAL ROAD ( NOCQ ROAD to THE BRIDGE )
Description: Work starting 09:00 AM and finishing 01:00 PM - CCTV Camera Clean
Start date: Wednesday, 27/11/24 End date: Wednesday, 27/11/24 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - ROUTE CARRE ( SANDY HOOK to BRAYE DU VALLE )
Description: Upgrade existing foul sewer connection
Start date: Friday, 22/11/24 End date: Wednesday, 27/11/24 Timing: All Day
Promoter: Geomarine Contractor: Geomarine
Bus Routes Affected: P2, 13, 21, N1, Cycle Access: Dismount past works

ST. SAMPSON - ROUTE CARRE ( SANDY HOOK to BRAYE DU VALLE )
Description: Chamber and duct installation
Start date: Monday, 25/11/24 End date: Friday, 29/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: P2, 13, 21, N1, Cycle Access: Dismount past works

ST. SAVIOUR - LA GRANDE LANDE ( RUE DES LOHIERS to RUE DES RIGNEAUX )
Description: Chamber and duct installation
Start date: Monday, 25/11/24 End date: Wednesday, 27/11/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - LA GRANDE LANDE ( RUE DES LOHIERS to RUE DES RIGNEAUX )
Description: new supply line
Start date: Monday, 25/11/24 End date: Friday, 29/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - LA GRANDE LANDE ( RUE DES LOHIERS to RUE DES RIGNEAUX )
Description: Supply line upgrade
Start date: Thursday, 28/11/24 End date: Friday, 29/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - LA GRANDE RUE
Description: Work starting 09:00 AM on Mon 25 Nov 24 and finishing 05:00 PM on Mon 25 Nov 24 - tree surgery
Start date: Monday, 25/11/24 End date: Monday, 25/11/24 Timing: All Day
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: 60, 61 Cycle Access: Dismount past works

ST. SAVIOUR - RUE DES LONGS CAMPS
Description: Chamber and duct installation
Start date: Monday, 25/11/24 End date: Friday, 13/12/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

TORTEVAL - Guernsey Velo Club Cyclocross - Road Closure
Description: Guernsey Velo Club Cyclocross - Road Closure & Parking Suspended
Start date: Sunday, 24/11/24 End date: Sunday, 24/11/24 Timing: Before AM Peak
Promoter: Guernsey Velo Club LBG Contractor: N/A
Bus Routes Affected: Cycle Access: Dismount past works

VALE - COURTIL DE LA LANDE
Description: New supply line
Start date: Monday, 25/11/24 End date: Thursday, 28/11/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

VALE - LA RUE DU PASSEUR ( LES HAUTES LANDES to LES MIELLES ROAD )
Description: CCTV Camera Cleans
Start date: Monday, 25/11/24 End date: Monday, 25/11/24 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 11, 12, N1 Cycle Access: Yes

VALE - RUE DU MARAIS ( ROCQUE BALAN LANE to LES MIELLES ROAD )
Description: supply line upgrade
Start date: Wednesday, 27/11/24 End date: Tuesday, 03/12/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

One Ways
CASTEL - Funeral at Matthews Church
Description: One - Way for funeral access for a Funeral at Matthews Church
Start date: Friday, 22/11/24 End date: Friday, 22/11/24 Timing: Between AM and PM Peaks
Promoter: Beckfords Funeral Services Ltd Contractor: N/A
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

Signals
ST. PETER PORT - ST. JAMES STREET ( COLLEGE STREET to GRANGE ROAD )
Description: Erecting scaffolding.
Start date: Saturday, 23/11/24 End date: Sunday, 24/11/24 Timing: Between AM and PM Peaks
Promoter: Formula Scaffolding Contractor: Formula Scaffolding
Bus Routes Affected: Cycle Access: Yes

VALE - LA ROUTE DU BRAYE; LES MARES PELLEES to SOHIER ROAD ( LES MARES PELLEES to SOHIER ROAD )
Description: Work starting 08:00 AM and finishing 05:00 PM daily between Mon 25 Nov 24 and Wed 11 Dec 24 - Rebuilding roadside wall.
Start date: Monday, 25/11/24 End date: Wednesday, 11/12/24 Timing: Between AM and PM Peaks
Promoter: meervelds Contractor: meervelds
Bus Routes Affected: Cycle Access: Yes