Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - QUEUX LANE ( LES BEAUCAMPS to RUETTE DES EFFARDS )
Description: Work starting 09:00 AM on Mon 13 Jun 22 and finishing 04:00 PM on Fri 08 Jul 22 - Construct roadside wall
Start date: Monday, 13/06/22 End date: Friday, 08/07/22 Timing: All Day
Promoter: Vaudin Stonemasons Contractor: Vaudin Stonemasons
Bus Routes Affected: Cycle Access: No: Closure

CASTEL - ROUTE DU TERTRE
Description: Work starting 07:30 AM on Mon 20 Jun 22 and finishing 05:00 PM on Fri 15 Jul 22 - Road resurfacing
Start date: Monday, 20/06/22 End date: Friday, 15/07/22 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: States Works (Patching)
Bus Routes Affected: Cycle Access: Restricted: Dismount Signage

CASTEL - RUE DE LA HOUGUE ( LA HOUGUETTE ROAD to RUE AU FERRE )
Description: Work starting 08:00 AM on Mon 27 Jun 22 and finishing 05:00 PM on Fri 01 Jul 22 - Network Upgrade
Start date: Monday, 27/06/22 End date: Friday, 01/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

Emergency Activity - CASTEL - RUE DE LA VIEILLE MARE
Description: Repair burst 8" water main
Start date: Saturday, 25/06/22 End date: Wednesday, 29/06/22 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. ANDREW - LES VAURIOUFS
Description: CUT OFF GAS SERVICE IN THE ROAD
Start date: Monday, 27/06/22 End date: Wednesday, 29/06/22 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - RUE CHARIOT
Description: Work starting 08:00 AM on Mon 16 May 22 and finishing 05:00 PM on Mon 04 Jul 22 - Network Upgrade
Start date: Monday, 16/05/22 End date: Monday, 04/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BOUILLON LANE
Description: Work starting 07:00 AM on Mon 15 Nov 21 and finishing 05:00 PM on Fri 29 Jul 22 - Scaffold for repairs to fire damaged roof; Property: Jamaica Inn; Purpose: Roofing Works
Start date: Monday, 15/11/21 End date: Friday, 29/07/22 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - HAUTEVILLE ( PEDVIN STREET to HAVELET )
Description: Work starting 07:00 AM on Mon 27 Jun 22 and finishing 05:00 PM on Mon 04 Jul 22 - Install water service
Start date: Monday, 27/06/22 End date: Monday, 04/07/22 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Restricted: Dismount passed works

ST. PETER PORT - LA RUE MARGUERITE
Description: Work starting 08:00 AM on Mon 05 Oct 20 and finishing 05:00 PM on Sun 31 Jul 22 - Construction of 5 storey office block and site set up
Start date: Monday, 05/10/20 End date: Sunday, 31/07/22 Timing: All Day
Promoter: J W Rihoy Builders Contractor: J W Rihoy Builders
Bus Routes Affected: Cycle Access: No: road barriered off

ST. PETER PORT - ST. JAMES STREET
Description: Work starting 08:00 AM on Wed 01 Jun 22 and finishing 05:00 PM on Sat 30 Jul 22 - Crane Lift for building construction
Start date: Wednesday, 01/06/22 End date: Saturday, 30/07/22 Timing: All Day
Promoter: J W Rihoy Builders Contractor: J W Rihoy Builders
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - ROUTE DE LIHOU ( ROUTE DU LONGFRIE to RUE DU LONGFRIE )
Description: CBT installation in chamber
Start date: Monday, 27/06/22 End date: Wednesday, 29/06/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - RUE DES PRES
Description: Work starting 08:00 AM on Mon 16 May 22 and finishing 05:00 PM on Wed 29 Jun 22 - Network Upgrade
Start date: Monday, 16/05/22 End date: Wednesday, 29/06/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - RUE DU CAMP AU PRETRE ( RUE DU COUDRE to RUE DU CATILLON )
Description: tree surgery
Start date: Monday, 27/06/22 End date: Thursday, 30/06/22 Timing: All Day
Promoter: Special Branch Contractor: Special Branch
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LES CANUS ( LES ABREUVEURS ROAD to LA ROUTE DES CAPELLES )
Description: Work starting 07:00 AM on Mon 20 Jun 22 and finishing 05:00 PM on Fri 01 Jul 22 - Closure to allow for new mains to be installed and connected
Start date: Monday, 20/06/22 End date: Friday, 01/07/22 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

VALE - HOUMET LANE
Description: Work starting 12:00 AM on Mon 13 Jun 22 and finishing 05:00 PM on Sun 03 Jul 22 - Network upgrade
Start date: Monday, 13/06/22 End date: Sunday, 03/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Restricted: Dismount signage

VALE - LA HOUGUE ( CROUTE BECREL to RUE DES LANDES )
Description: Work starting 08:00 AM on Mon 27 Jun 22 and finishing 05:00 PM on Fri 01 Jul 22 - Network Upgrade
Start date: Monday, 27/06/22 End date: Friday, 01/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

VALE - ROUTE DE VAUGRAT ( RUE D'AVAL to )
Description: Work starting 07:30 AM on Wed 15 Jun 22 and finishing 04:00 PM on Fri 01 Jul 22 - Road resurfacing
Start date: Wednesday, 15/06/22 End date: Friday, 01/07/22 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: No: Will have to dismount and walk through

One Ways
ST. SAMPSON - RUE DES COTTES ( PLEINHEAUME ROAD to ROUTE DE LA PASSEE )
Description: Obstruction of eastbound lane at junction with Grand Maison Road due to scaffolding in carriageway.
Start date: Monday, 27/06/22 End date: Saturday, 02/07/22 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: 31, 32 Cycle Access: Restricted: 1-way - eastbound will need to dismount.

Signals
ST. PETER PORT - COLBORNE ROAD ( RUETTES BRAYES to HAVILLAND ROAD )
Description: Work starting 07:00 AM on Mon 13 Jun 22 and finishing 05:00 PM on Wed 13 Jul 22 - demolish property lean-to and build rear extension
Start date: Monday, 13/06/22 End date: Wednesday, 13/07/22 Timing: All Day
Promoter: Just Build It Ltd Contractor: Just Build It Ltd
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
CASTEL - Le Viaer Marchi
Description: Work starting 03:00 PM on Mon 04 Jul 22 and finishing 10:00 PM on Mon 04 Jul 22 - The National Trust of Guerney Annual Viaer Marchi
Start date: Monday, 04/07/22 End date: Monday, 04/07/22 Timing: All Day
Promoter: The National Trust of Guernsey Contractor: N/A
Bus Routes Affected: Cycle Access: Yes

CASTEL - RUE DE BOUVERIE ( RUETTE DE LA TOUR to ROUTE DE CARTERET )
Description: Work starting 07:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Fri 15 Jul 22 - Install new foul water connection to site
Start date: Monday, 04/07/22 End date: Friday, 15/07/22 Timing: All Day
Promoter: Geomarine Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

CASTEL - RUETTE DU COURTIL SIMON
Description: Work starting 07:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Mon 11 Jul 22 - Replace existing water main
Start date: Monday, 04/07/22 End date: Monday, 11/07/22 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: No: No access past works

FOOTES LANE - ST. ANDREW - Mini`s Soccer Festival
Description: GFCs Mini`s Tournament
Start date: Saturday, 02/07/22 End date: Sunday, 03/07/22 Timing: All Day
Promoter: Guernsey Football Association Contractor: N/A
Bus Routes Affected: 51, 52 Cycle Access: Yes

FOREST - RUE DES GLAGEULS ( LA RUE DES CROISEE to RUE DES LES HOUARDS )
Description: Work starting 07:00 AM on Wed 29 Jun 22 and finishing 04:00 PM on Fri 01 Jul 22 - new electricity supply
Start date: Wednesday, 29/06/22 End date: Friday, 01/07/22 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

ST. ANDREW - RUE DES BAILLEULS ( RUE DE LA BOULLERIE to RUE DES LANDES )
Description: Work starting 09:00 AM and finishing 03:00 PM daily between Mon 04 Jul 22 and Tue 05 Jul 22 - CCTV Camera Clean
Start date: Monday, 04/07/22 End date: Tuesday, 05/07/22 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - LES MERRIENNES
Description: Work starting 07:30 AM on Mon 04 Jul 22 and finishing 04:00 PM on Fri 15 Jul 22 - Footway resurfacing and road patching
Start date: Monday, 04/07/22 End date: Friday, 15/07/22 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: 81 Cycle Access: Yes

ST. PETER PORT - BELMONT ROAD ( QUEENS ROAD to LES CROUTES )
Description: Work starting 07:00 AM on Tue 05 Jul 22 and finishing 05:00 PM on Fri 08 Jul 22 - Closure to allow for service alteration
Start date: Tuesday, 05/07/22 End date: Friday, 08/07/22 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - GRANGE ROAD
Description: Electricity service alteration to property
Start date: Tuesday, 05/07/22 End date: Thursday, 07/07/22 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 31, 41, 42, 51, 52, 60, 61, 71, 81, N2 Cycle Access: Restricted: Trant to manage

ST. PETER PORT - LE BORDAGE
Description: 9am - 12noon crane lift
Start date: Sunday, 03/07/22 End date: Sunday, 03/07/22 Timing: All Day
Promoter: Siteweld ltd Contractor: Siteweld ltd
Bus Routes Affected: P2, 91, 92, 93, 94, 95, N3 Cycle Access: Yes

ST. PETER PORT - ROUTE DE LA RAMEE ( LA VRANGUE to LA NEUVE RUE )
Description: Work starting 08:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Thu 07 Jul 22 - Network Upgrade
Start date: Monday, 04/07/22 End date: Thursday, 07/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 31, 32 Cycle Access: Yes

ST. PIERRE DU BOIS - RUE DE LA GRANDE MAISON ( RUE DE LA GALLIE to RUE TREMEL )
Description: Work starting 09:00 AM on Tue 05 Jul 22 and finishing 04:00 PM on Wed 06 Jul 22 - Repair Roadside bank
Start date: Tuesday, 05/07/22 End date: Wednesday, 06/07/22 Timing: All Day
Promoter: Vaudin Stonemasons Contractor: Vaudin Stonemasons
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LE GRAND FORT ROAD ( LES PETITES CAPELLES ROAD to ROUTE CARRE )
Description: Work starting 07:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Wed 06 Jul 22 - service alteration
Start date: Monday, 04/07/22 End date: Wednesday, 06/07/22 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: P2 Cycle Access: Yes

ST. SAVIOUR - ROUTE DES PIQUES
Description: Work starting 08:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Fri 15 Jul 22 - Network Upgrade
Start date: Monday, 04/07/22 End date: Friday, 15/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 71 Cycle Access: Yes

VALE - CROFT LANE ( SOUS LES HOUGUES to LA ROUTE DU BRAYE )
Description: CUT OFF STEEL SERVICE IN ROAD
Start date: Wednesday, 29/06/22 End date: Friday, 01/07/22 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: Yes

VALE - HOUGUE DU MOULIN ( VILLE ES PIES to RUE DE L'ECOLE )
Description: Work starting 07:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Tue 05 Jul 22 - Install new water service
Start date: Monday, 04/07/22 End date: Tuesday, 05/07/22 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Restricted: Dismount past work

VALE - HOUMET LANE
Description: Work starting 08:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Fri 29 Jul 22 - Network Upgrade
Start date: Monday, 04/07/22 End date: Friday, 29/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Restricted: Dismount signage

VALE - LA VILLE BAUDU ( LA ROUTE MILITAIRE to RUETTE DE LA FOLIE )
Description: Work starting 08:00 AM on Wed 29 Jun 22 and finishing 05:00 PM on Fri 08 Jul 22 - Network upgrade
Start date: Wednesday, 29/06/22 End date: Friday, 08/07/22 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 13, N1 Cycle Access: Yes

One Ways
No future major delays due to one ways
Signals
ST. SAMPSON - LES BAS COURTILS ROAD ( CAMP CODE LANE to VALE ROAD )
Description: Work starting 07:00 AM on Mon 04 Jul 22 and finishing 05:00 PM on Fri 08 Jul 22 - Electricity cable fault leading to streetlight
Start date: Monday, 04/07/22 End date: Friday, 08/07/22 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes