Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - ROUTE DE LA HOUGUE DU POMMIER
Description: Work starting 08:30 AM on Tue 01 Sep 26 and finishing 05:00 PM on Mon 21 Dec 26 - Install new 400mm water ring main pipework
Start date: Tuesday, 01/09/26 End date: Monday, 21/12/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: LMDC 6A / LV 6A; 41;42;N2 Cycle Access: Dismount past works

CASTEL - RUE DE LA CACHE ( to RUE DES VARENDES )
Description: Work starting 08:00 AM on Mon 02 Nov 26 and finishing 05:00 PM on Sun 15 Nov 26 - Erect scaffold for re-roofing
Start date: Monday, 02/11/26 End date: Sunday, 15/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

CASTEL - RUE DES BELLES ( RUE DE LA PORTE to RUE DES BERGERS )
Description: Erect scaffolding in roadway to give access to build granite wall
Start date: Wednesday, 07/10/26 End date: Wednesday, 04/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

FOREST - RUE DES AUBERTS ( LE BOURG to )
Description: Primary substation replacement
Start date: Monday, 22/06/26 End date: Friday, 27/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: No

ST. ANDREW - ROUTE DE LA CROIX AU BAILIFF
Description: Work starting 07:30 AM on Tue 27 Oct 26 and finishing 04:00 PM on Fri 06 Nov 26 - Road patching
Start date: Monday, 26/10/26 End date: Friday, 06/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: St Martin 1A; St Martin 1B; LB 1A; LB 1B; LB 2A; LB 2B; LB 3A; LB 3B; LV 4B; LV 5A / LB 6A; LV 5B / LB 6B; P2;51;52;60;61 Cycle Access: Dismount past works

ST. PETER PORT - BERTHELOT STREET ( HIGH STREET to NEW STREET )
Description: ROOMS REFURBISHMENT REQUIRING X3 SKIPS TO BE PUT ON BERTHELOT STREET BEHIND THE PICKLED PIG SECTION OF THE HOTEL.
Start date: Monday, 19/10/26 End date: Monday, 16/11/26 Timing: All Day
Promoter: The Duke of Normandie Hotel Contractor: The Duke of Normandie Hotel
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - BERTHELOT STREET
Description: Work starting 07:30 AM on Mon 17 Mar 25 and finishing 11:59 PM on Thu 31 Dec 26 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
Start date: Monday, 17/03/25 End date: Thursday, 31/12/26 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - CROUTES HAVILLAND ( FORT ROAD to DAMOUETTES LANE )
Description: Concrete Pour for 2 properties
Start date: Tuesday, 03/11/26 End date: Friday, 06/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - LES OZOUETS ROAD
Description: Work starting 08:30 AM on Mon 05 Oct 26 and finishing 05:00 PM on Mon 09 Nov 26 - Foul manhole upgrade works
Start date: Monday, 05/10/26 End date: Monday, 09/11/26 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: SS 1B; 51;52 Cycle Access: Dismount past works

ST. PETER PORT - MISC
Description: Erect scaffold - road will remain closed due to width of the road; Property: 29 Victoria Road; Purpose: Roofing Works
Start date: Wednesday, 07/10/26 End date: Wednesday, 11/11/26 Timing: All Day
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - THE STRAND ( CLIFF STREET to HAVELET )
Description: works being done to 16 Hauteville in the back carpark which leads onto main road, large vehichels will need to access and will be in the way along with works to be carried out
Start date: Monday, 02/11/26 End date: Tuesday, 01/12/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - LES REINES
Description: Erect Scaffolding; Property: Les Reines; Purpose: Roofing Works
Start date: Monday, 19/10/26 End date: Friday, 11/12/26 Timing: All Day
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Forest PS 1A;Forest PS 1B;LB HS 6A;LB HS 6B;LV HS 5A;LV HS 5A Overflow;LV HS 5B;LV HS LB HS 5A;LV HS LB HS 5B Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DU BORDAGE ( RUE DU CAMP AU PRETRE to RUE DE LA FONTENELLE )
Description: building gable wall.
Start date: Friday, 28/08/26 End date: Wednesday, 23/12/26 Timing: All Day
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LES SAUVAGEES
Description: Route Militaire high and low voltage cabling connection
Start date: Monday, 26/10/26 End date: Friday, 13/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vale 1A; Vale 3B; SS 4A; SS 5A; SS 6A; SS 8A; 13;21 Cycle Access: Dismount past works

ST. SAMPSON - ROUTE MILITAIRE
Description: High voltage substation installation, high and low voltage cable upgrade and service upgrades
Start date: Monday, 28/09/26 End date: Friday, 18/12/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vale 1A; Vale 3B; SS 4A; SS 5A; SS 6A; SS 8A; 13;21 Cycle Access: Dismount past works

TORTEVAL - RUE DU PLANEL ( ROUTE DE PLEINMONT to )
Description: supply line upgrade
Start date: Monday, 02/11/26 End date: Wednesday, 04/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: LMDC 1A / LB 7A; LMDC 1B / LB 7B Cycle Access: Dismount past works

TORTEVAL - RUE DU PLANEL ( RUE DU BOUT to )
Description: Service alteration
Start date: Tuesday, 03/11/26 End date: Wednesday, 04/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

VALE - ROUTE DE LA CHARRUEE
Description: Work starting 08:30 AM on Tue 01 Sep 26 and finishing 05:00 PM on Wed 23 Dec 26 - Upsize existing water main
Start date: Tuesday, 01/09/26 End date: Wednesday, 23/12/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: LMDC 6A / LV 6A; 41;42;N2 Cycle Access: Dismount past works

VALE - RUE DES HAIZES
Description: Essential maintenance to gas Mains and Services.
Start date: Monday, 02/11/26 End date: Monday, 16/11/26 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: No

VALE - RUE DU CHARDRONNET ( LA RUE DE PARADIS to RUE DE DESSOUS )
Description: Erect Scaffold to enable roof repairs
Start date: Monday, 26/10/26 End date: Thursday, 26/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

VALE - VALE-MISC54 ( ROCQUE ES CAS to LA MOYE ROAD )
Description: Work starting 10:00 AM on Tue 14 Jul 26 and finishing 05:00 PM on Sat 14 Nov 26 - Deliveries and Barn renovations
Start date: Tuesday, 14/07/26 End date: Saturday, 14/11/26 Timing: All Day
Promoter: Omega Group Contractor: Omega Group
Bus Routes Affected: Vale PS 2B;Vale PS 3B Cycle Access: Dismount past works

One Ways
No current major delays due to one ways
Signals
CASTEL - RUE DE LA SALINE ( ROUTE DE LA MARE DE CARTERET to GRANDES ROCQUES BU )
Description: COASTAL WALL REPAIR.
Start date: Monday, 07/09/26 End date: Friday, 18/12/26 Timing: All Day
Promoter: States Property Unit Contractor: States Property Unit
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - ROUTE ST. CLAIR; RUE DES POINTUES ROCQUES to VALE ROAD ( RUE DES POINTUES ROCQUES to VALE ROAD )
Description: Temporary Traffic Signals at St Clair Hill, St Sampsons - Repairing Damaged Granite wall - Monday to Friday 7am until 17:00 - for 2 weeks 2nd November until 13th November. (house name Charmouth)
Start date: Monday, 02/11/26 End date: Monday, 09/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
ST. ANDREW - LES RUETTES ( ROUTE DE LA CROIX AU BAILIFF to FOULON ROAD )
Description: House Move
Start date: Thursday, 05/11/26 End date: Friday, 06/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. ANDREW - LES RUETTES ( ROUTE DE LA CROIX AU BAILIFF to FOULON ROAD )
Description: Works to roadside driveway
Start date: Monday, 09/11/26 End date: Monday, 16/11/26 Timing: All Day
Promoter: Tarmac Services Contractor: Tarmac Services
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - COIN COLIN
Description: Work starting 07:30 AM on Mon 09 Nov 26 and finishing 04:00 PM on Fri 20 Nov 26 - Road resurfacing
Start date: Monday, 09/11/26 End date: Friday, 20/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: No

ST. MARTIN - LA FOSSE DE BAS ( LA FOSSE DE HAUT to LE ROCHER )
Description: Tree Surgery
Start date: Monday, 09/11/26 End date: Monday, 09/11/26 Timing: All Day
Promoter: Guernsey Tree Service Ltd Contractor: Guernsey Tree Service Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LES PAGES ( RUE DES PAGES to LES MARTINS )
Description: Roads Resurfacing
Start date: Wednesday, 04/11/26 End date: Friday, 06/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LONG TRAC
Description: Road resurfacing
Start date: Monday, 09/11/26 End date: Tuesday, 10/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - Remembrance Sunday Service ( LA BELLIEUSE to LES MERRIENNES )
Description: Road closed 10am to 12pm
Start date: Sunday, 08/11/26 End date: Sunday, 08/11/26 Timing: All Day
Promoter: Constables of St Martin Contractor: N/A
Bus Routes Affected: 81, 93 Cycle Access: No

ST. PETER PORT - FORT ROAD
Description: Fermain Lane Substation replacement phase 2
Start date: Monday, 09/11/26 End date: Monday, 30/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 2A; LB 3B; LV 4A; 91;92;93;94;95;N3 Cycle Access: Dismount past works

ST. PETER PORT - LOWER HAUTEVILLE ( CLIFF STREET to PEDVIN STREET )
Description: House move
Start date: Tuesday, 10/11/26 End date: Tuesday, 10/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - Remembrance Day 2026 - St Peter Port
Description: Closure of streets on Parade Route and around Cenotaph along with associated suspension of parking over period.
Start date: Sunday, 08/11/26 End date: Sunday, 08/11/26 Timing: Between AM and PM Peaks
Promoter: Bailiff`s Chambers Contractor: N/A
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - ST. JACQUES
Description: New duct to property
Start date: Thursday, 05/11/26 End date: Friday, 06/11/26 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAMPSON - Guernsey Football Association
Description: GFC match - road closure
Start date: Saturday, 07/11/26 End date: Saturday, 07/11/26 Timing: Between AM and PM Peaks
Promoter: Guernsey Football Association Contractor: N/A
Bus Routes Affected: Vale 2A Cycle Access: Yes:

ST. SAVIOUR - LES BUTTES
Description: Tree surgery
Start date: Monday, 09/11/26 End date: Friday, 13/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: 71 Cycle Access: No

ST. SAVIOUR - RUE DU BELIAL ( RUE CEVECQ to ROUTE DES DOMAINES )
Description: Replace old water meter chambers
Start date: Monday, 09/11/26 End date: Thursday, 12/11/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

One Ways
ST. PETER PORT - Guernsey Rugby Club Firework Display
Description: Road one-way 4:30pm to 9pm
Start date: Sunday, 08/11/26 End date: Sunday, 08/11/26 Timing: All Day
Promoter: Guernsey Rugby Club Contractor: N/A
Bus Routes Affected: 51, 52 Cycle Access: Yes, in direction of one-way

VALE - 2nd Guernsey Scouts - Bonfire Night event ( LES ROUVETS ROAD to LES ARGUILLIERS LANE )
Description: Work starting 05:00 PM and finishing 09:00 PM - One way working of road past Wayfarer Centre at Rue du Haut
Start date: Thursday, 05/11/26 End date: Thursday, 05/11/26 Timing: After PM Peak
Promoter: 2nd Guernsey Scout Group Contractor: N/A
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

Signals
No future major delays due to signals