Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - RUE DU FRIE PLAIDY
Description: Scaffolding; Property: Le Frie Plaidy; Purpose: Other (see Details)
Start date: Saturday, 15/03/25 End date: Saturday, 10/05/25 Timing: Between AM and PM Peaks
Promoter: Island Scaffolding Contractor: Island Scaffolding
Bus Routes Affected: Cycle Access: Yes

CASTEL - RUE DU PRESBYTERE
Description: Work starting 08:30 AM on Mon 03 Mar 25 and finishing 05:00 PM on Mon 02 Jun 25 - Install new water transfer pipework
Start date: Monday, 03/03/25 End date: Monday, 02/06/25 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Castel 1A; St Martin 1B; 51;52 Cycle Access: Dismount past works

CASTEL - RUETTE DE TOUILLETS ( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
Description: Work starting 08:00 AM on Sat 19 Aug 23 and finishing 11:59 PM on Wed 30 Apr 25 - Investigation and repairs to roadside wall
Start date: Saturday, 19/08/23 End date: Wednesday, 30/04/25 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

CASTEL - RUETTE DU VILLOCQ; RUETTE DU COURTIL SIMON to ROUTE DE SAUMAREZ ( RUETTE DU COURTIL SIMON to ROUTE DE SAUMAREZ )
Description: Repair leaking service
Start date: Monday, 17/03/25 End date: Tuesday, 18/03/25 Timing: All Day
Promoter: Guernsey Water Contractor: Guernsey Water
Bus Routes Affected: LMDC HS 5A;LMDC HS 5B;LMDC HS 6B;LMDC HS 7A;SS HS 4A NEW;SS HS 4B NEW Cycle Access: Dismount past works

Emergency Activity - CASTEL - KING'S MILLS ROAD
Description: Work starting 09:52 AM on Sun 16 Mar 25 and finishing 05:00 PM on Tue 18 Mar 25 - Excavations required to repair an LV cable fault
Start date: Sunday, 16/03/25 End date: Tuesday, 18/03/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Castel 1B; LB 5A; LB 5B; LB 9B; LV 3B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; LMDC 3B / LB 8B; 61;N2 Cycle Access: Dismount past works

Emergency Activity - CASTEL - RUE DE LA PORTE
Description: Emergency Work - LV Fault
Start date: Friday, 14/03/25 End date: Friday, 21/03/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Castel 1B; LB 4A; LB 4B; LB 4A Overflow; LB 5A; LB 5B; LB 9B; LV 3B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; LMDC 3B / LB 8B; 61;N2 Cycle Access: Dismount past works

FOREST - RUE DES AUBERTS ( LE BOURG to )
Description: Work starting 08:00 AM on Mon 10 Mar 25 and finishing 05:00 PM on Fri 18 Apr 25 - Trenching for high voltage cable upgrade, cable installation and high voltage jointing
Start date: Monday, 10/03/25 End date: Friday, 18/04/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Cycle Access: Dismount past works

FOREST - RUE DES GLAGEULS ( LA RUE DES CROISEE to RUE DES LES HOUARDS )
Description: Chamber and duct installation
Start date: Monday, 10/03/25 End date: Tuesday, 18/03/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LES PAGES
Description: Work starting 07:30 AM on Mon 17 Mar 25 and finishing 04:00 PM on Fri 04 Apr 25 - Road resurfacing
Start date: Monday, 17/03/25 End date: Friday, 04/04/25 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: States Works (Patching)
Bus Routes Affected: Cycle Access: No: dismount

ST. PETER PORT - BERTHELOT STREET
Description: Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
Start date: Monday, 17/03/25 End date: Monday, 04/05/26 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - FOUNTAIN STREET; LE BORDAGE to CHURCH SQUARE
Description: To repair an electrical fault
Start date: Monday, 17/03/25 End date: Thursday, 20/03/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 3B; LB 9B; LMDC 6A / LV 6A; LMDC 6B / LV 6B; LV 4A; P2;51;52;91;92;93;94;95;N3 Cycle Access: Yes

ST. PETER PORT - HIGH STREET ( LEFEBVRE STREET to BERTHELOT STREET )
Description: Stripping scaffolding.
Start date: Monday, 10/03/25 End date: Saturday, 19/04/25 Timing: Between AM and PM Peaks
Promoter: Formula Scaffolding Contractor: Formula Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LA BUTTE ( L'HYVREUSE AVENUE to BROCK ROAD )
Description: Chamber and duct installation
Start date: Monday, 17/03/25 End date: Friday, 21/03/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 31;32 Cycle Access: Dismount past works

ST. PETER PORT - LE POLLET
Description: Work starting 07:00 AM on Sun 26 Jan 25 and finishing 05:00 PM on Sun 27 Apr 25 - Property: CAFE EMILIA; Purpose: External Decoration
Start date: Sunday, 26/01/25 End date: Sunday, 27/04/25 Timing: All Day
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - LES PETITES FONTAINES ( MOUNT HERMON to VALNORD ROAD )
Description: Work starting 11:30 AM on Fri 22 Nov 24 and finishing 05:00 PM on Mon 31 Mar 25 - wall repairs
Start date: Friday, 22/11/24 End date: Monday, 31/03/25 Timing: All Day
Promoter: TNT Stonemasons Contractor: TNT Stonemasons
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LES VAUXLAURENS
Description: Work starting 07:30 AM and finishing 07:30 AM daily between Fri 29 Nov 24 and Sun 30 Mar 25 - Scaffold to access for emergency works from storm damage; Property: Apartments 4 and 29 St Julians Avenue; Purpose: Roofing Works
Start date: Friday, 29/11/24 End date: Sunday, 30/03/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LES VAUXLAURENS
Description: Work starting 07:30 AM and finishing 07:30 AM daily between Fri 29 Nov 24 and Sun 30 Mar 25 - Scaffolding; Property: No 1 St Julians Avenue; Purpose: Roofing Works
Start date: Friday, 29/11/24 End date: Sunday, 30/03/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LOWER CANICHERS ( LE TRUCHOT to DOYLE STREET )
Description: Work starting 08:00 AM on Mon 30 Sep 24 and finishing 07:00 AM on Mon 28 Apr 25 - building repair and refit
Start date: Monday, 30/09/24 End date: Monday, 28/04/25 Timing: All Day
Promoter: Ravenscroft Construction Ltd Contractor: Ravenscroft Construction Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - PRINCE ALBERT ROAD
Description: Work starting 07:00 AM on Mon 17 Mar 25 and finishing 05:00 PM on Mon 31 Mar 25 - Fibre optic chamber and duct installation
Start date: Monday, 17/03/25 End date: Monday, 31/03/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - THE STRAND
Description: Scaffold for construction; Property: La Coquere; Purpose: Demolition / New Build
Start date: Wednesday, 10/07/24 End date: Saturday, 12/04/25 Timing: All Day
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - UPPER MANSELL STREET ( PARK STREET to TRINITY SQUARE )
Description: Chamber and duct installation
Start date: Monday, 17/03/25 End date: Wednesday, 19/03/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - VALNORD ROAD
Description: crane lifts 8am to 5pm daily.
Start date: Monday, 17/03/25 End date: Sunday, 23/03/25 Timing: All Day
Promoter: Ravenscroft Construction Ltd Contractor: Ravenscroft Construction Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - ROUTE DE LIHOU ( RUE DU LONGFRIE to RUE DES GRANDES RUES )
Description: Work starting 09:00 AM on Thu 29 Aug 24 and finishing 11:59 PM on Sat 31 May 25 - Road blocked due to collapsed granite wall approx 10m from the Route de Lihou and Rue du Longfrie junction, near property Longfrie House.
Start date: Thursday, 29/08/24 End date: Saturday, 31/05/25 Timing: All Day
Promoter: Traffic and Highways Contractor: Traffic and Highways
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DE L`ISSUE
Description: Installation of new distribution pillar
Start date: Monday, 10/03/25 End date: Friday, 28/03/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - RUE DES MENAGES ( ROUTE DE LA PALLOTERIE to RUE DES CORBINETS )
Description: Repairs to roadside wall.
Start date: Wednesday, 12/03/25 End date: Wednesday, 19/03/25 Timing: All Day
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: Houguette 1A Cycle Access: Yes

ST. SAMPSON - CAMP CODE LANE ( LES BAS COURTILS ROAD to DELANCEY LANE )
Description: Duct installation
Start date: Monday, 17/03/25 End date: Wednesday, 19/03/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAMPSON - LES BASSES CAPELLES ROAD ( LES PETITES CAPELLES ROAD to RUE SAUVAGE )
Description: Remedial works to channel kerbs
Start date: Monday, 17/03/25 End date: Wednesday, 19/03/25 Timing: All Day
Promoter: Tarmac Services Contractor: Tarmac Services
Bus Routes Affected: SS HS 1B Cycle Access: Yes

ST. SAVIOUR - VIEILLE RUE ( RUE DES CINQ VERGES to RUE DE LA GIROUETTE )
Description: Work starting 07:00 AM and finishing 05:00 PM daily between Mon 03 Feb 25 and Thu 01 May 25 - Rebuilding roadside wall.
Start date: Monday, 03/02/25 End date: Thursday, 01/05/25 Timing: Between AM and PM Peaks
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

VALE - LA ROUTE DU BRAYE
Description: Work starting 07:30 AM on Mon 17 Mar 25 and finishing 04:00 PM on Fri 04 Apr 25 - Road Resurfacing
Start date: Monday, 17/03/25 End date: Friday, 04/04/25 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Vale 2B; Vale 3B; LV 2B; SS 2B; SS 5A; SS 5B; 11;12;13;N1 Cycle Access: Dismount past works

VALE - RUE DE HAUT ( LES ROUVETS ROAD to LES ARGUILLIERS LANE )
Description: Rebuilding roadside wall.
Start date: Tuesday, 04/03/25 End date: Tuesday, 01/04/25 Timing: All Day
Promoter: Stoneworks Ltd Contractor: Stoneworks Ltd
Bus Routes Affected: Cycle Access: Yes

One Ways
ST. PETER PORT - LE BOUET
Description: Work starting 08:00 AM and finishing 05:00 PM daily between Wed 16 Oct 24 and Fri 04 Apr 25 - Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
Start date: Wednesday, 16/10/24 End date: Friday, 04/04/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

VALE - VALE AVENUE
Description: Work starting 08:00 AM and finishing 05:00 PM daily between Mon 06 Jan 25 and Tue 25 Mar 25 - Scaffolding.; Property: Northside House.; Purpose: Roofing Works
Start date: Monday, 06/01/25 End date: Tuesday, 25/03/25 Timing: Between AM and PM Peaks
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Vale 2A; Vale 2B; LV 1A; LV 1B; LV 2B; SS 2B; SS 5A; SS 5B; SS 6A; SS 6B; P2;11;12;13;91;92;N1 Cycle Access: Yes, in direction of one-way

Signals
No current major delays due to signals

Starting - next 7 days
Closures
CASTEL - CANDIE ROAD ( RUE A L'EAU to LES VALINGUETS )
Description: Node installations and splicing 8am - 4pm dialy
Start date: Tuesday, 18/03/25 End date: Wednesday, 19/03/25 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: LB 4B; LB 4A Overflow Cycle Access: Dismount past works

CASTEL - LA ROCQUETTE ( RUE DE LA VIEILLE MARE to VAZON ROAD )
Description: CCTV Camera Clean
Start date: Wednesday, 19/03/25 End date: Wednesday, 19/03/25 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Castel 2A; Castel 3B; LMDC 3B / LB 8B; 42 Cycle Access: Dismount past works

ST. MARTIN - LES CACHES ( LA GRANDE RUE to LA RUE MAZE )
Description: Work starting 07:00 AM on Sat 22 Mar 25 and finishing 06:00 PM on Mon 24 Mar 25 - Tree surgery works.
Start date: Saturday, 22/03/25 End date: Monday, 24/03/25 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: LB 1A; LB 2A; LB 2B; LB 3B; LB 9B; LV 4A Cycle Access: Dismount past works

ST. MARTIN - RUE DE LA VALLEE ( to LES CAMPS DU MOULIN )
Description: Work starting 08:00 AM on Mon 24 Mar 25 and finishing 05:00 PM on Wed 26 Mar 25 - Chamber and duct installation
Start date: Monday, 24/03/25 End date: Wednesday, 26/03/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - HIGH STREET ( BERTHELOT STREET to QUAY STREET )
Description: Work starting 08:30 AM on Mon 24 Mar 25 and finishing 05:00 PM on Fri 04 Apr 25 - Install new water service
Start date: Monday, 24/03/25 End date: Friday, 04/04/25 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: LBHS 2A;LBHS 3B;LB HS 9B;LMDC HS 5B;LMDC HS 6B;SS HS 4B Cycle Access: Yes

ST. PETER PORT - LE FOULON ( ROUTE ISABELLE to ROHAIS )
Description: Crane Lift.
Start date: Monday, 24/03/25 End date: Monday, 24/03/25 Timing: Between AM and PM Peaks
Promoter: Mimosa Ltd Contractor: Mimosa Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LE TRUCHOT ( DOYLE STREET to SIR WILLIAM PLACE )
Description: Crane lift
Start date: Sunday, 23/03/25 End date: Sunday, 23/03/25 Timing: Before AM Peak
Promoter: J W Rihoy Builders Contractor: J W Rihoy Builders
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - LES BAISSIERES
Description: Replace Faulty Chambers
Start date: Tuesday, 18/03/25 End date: Friday, 21/03/25 Timing: All Day
Promoter: Guernsey Water Contractor: Guernsey Water
Bus Routes Affected: SS 1B; 51;52 Cycle Access: Dismount past works

ST. PETER PORT - LES COTILS ( LES AMBALLES to BEAUREGARD LANE )
Description: Household removal.
Start date: Monday, 24/03/25 End date: Tuesday, 25/03/25 Timing: All Day
Promoter: R and R Removals Contractor: R and R Removals
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - LES ECHELONS ( SOUTH ESPLANADE to SOUTH ESPLANADE )
Description: Work starting 08:00 AM on Thu 20 Mar 25 and finishing 05:00 PM on Fri 21 Mar 25 - Chamber installation
Start date: Thursday, 20/03/25 End date: Friday, 21/03/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - ST. JULIAN'S AVENUE
Description: crane lift to RBS (bottom section closed)
Start date: Sunday, 23/03/25 End date: Sunday, 23/03/25 Timing: All Day
Promoter: AFM Contractor: AFM
Bus Routes Affected: 31;32;41;42;60;61;71;81;N2;N4 Cycle Access: No

ST. PIERRE DU BOIS - RUE DES PRES ( RUE DES LANDES to RUE DES MARCHEZ )
Description: concrete pour
Start date: Monday, 24/03/25 End date: Monday, 24/03/25 Timing: All Day
Promoter: davy Contractor: davy
Bus Routes Affected: Houguette PS 1A Cycle Access: Dismount past works

ST. SAVIOUR - LONGUE RUE ( LA GRANDE RUE to RUE DES CRABBES )
Description: Grit blasting railings.
Start date: Monday, 24/03/25 End date: Monday, 24/03/25 Timing: Between AM and PM Peaks
Promoter: C and D Carpenters Contractor: C and D Carpenters
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - RUE DES CRABBES ( RUE DE ST. APPOLINE to RUE PERELLE )
Description: Repair damaged drainage channels and surrounding bitmac
Start date: Monday, 24/03/25 End date: Friday, 28/03/25 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Tarmac Services
Bus Routes Affected: Houguette PS 1B;Houguette PS 3B;LBHS 5A;LBHS 5B;LMDC HS 3A;LMDC HS 3B;LMDC HS 4A;LMDC HS 4B;LV HS 3B;LV HS 8A;LMDC HS LB HS 3A;LMDC HS LB HS 3B Cycle Access: Yes

VALE - SOHIER ROAD
Description: CCTV Camera clean
Start date: Friday, 21/03/25 End date: Friday, 21/03/25 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: LV 2B; SS 5A; SS 5B; P2;11;12 Cycle Access: Dismount past works

One Ways
ST. PETER PORT - GRANGE ROAD
Description: Crane lift.
Start date: Tuesday, 18/03/25 End date: Thursday, 20/03/25 Timing: Between AM and PM Peaks
Promoter: Island Scaffolding Contractor: Island Scaffolding
Bus Routes Affected: 31;41;42;60;61;71;81;N2;N4 Cycle Access: Dismount past works

Signals
ST. PETER PORT - SOUTH ESPLANADE; LES ECHELONS to LES ECHELONS FILTER ( LES ECHELONS to LES ECHELONS FILTER )
Description: Tree surgery works.
Start date: Wednesday, 19/03/25 End date: Thursday, 20/03/25 Timing: Between AM and PM Peaks
Promoter: Treevolution Contractor: Treevolution
Bus Routes Affected: Cycle Access: No