Road closures and delays

Road closures
CASTEL - MONT D`AVAL; to

Start date: Monday, 12/08/19
End date: Thursday, 22/08/19
Traffic details: Road Closure     All Day
Promoter: Traffic and Highway Services (Capital Works)
Contractor: Ronez (Patching)
Description: Work starting 07:30 AM on Mon 12 Aug 19 and finishing 02:00 PM on Thu 22 Aug 19 - Road resurfacing



ST. SAMPSON - LE MURIER

Start date: Monday, 12/08/19
End date: Saturday, 31/08/19
Traffic details: Road Closure     All Day
Promoter: Traffic and Highway Services (Capital Works)
Contractor: States Works (Patching)
Description: Work starting 07:30 AM on Mon 12 Aug 19 and finishing 06:00 AM on Sat 31 Aug 19 - Road resurfacing



ST. PETER PORT - LES AMBALLES - THS; PIETTE ROAD to LES COTILS

Start date: Monday, 08/04/19
End date: Friday, 29/11/19
Traffic details: Road Closure     Between AM and PM Peaks
Promoter: Infinity Construction Ltd
Contractor: Infinity Construction Ltd
Description: Work starting Mon 08 Apr 19 and Finishing Fri 29 Nov 19 - Road closed weekdays 9am - 4pm from material deliveries / crane lifting. The road will be one-way at all other times (Piette Road to Les Cotils).



ST. SAMPSON - NOCQ ROAD; SALTPANS ROAD to ROLAND ROAD

Start date: Monday, 19/08/19
End date: Friday, 30/08/19
Traffic details: Road Closure     All Day
Promoter: Geomarine
Contractor: Geomarine
Description: Work starting 07:00 AM on Mon 19 Aug 19 and finishing 05:00 PM on Fri 30 Aug 19 - Main drain connection



ST. PETER PORT - VAUVERT; GRANGE ROAD to LA COUPERDERIE

Start date: Monday, 05/08/19
End date: Friday, 23/08/19
Traffic details: Road Closure     All Day
Promoter: Sure Guernsey
Contractor: Geomarine
Description: Work starting 07:00 AM on Mon 05 Aug 19 and finishing 11:00 PM on Fri 23 Aug 19 - Repairs to ducts



ST. ANDREW - LA VILLIAZE ROAD

Start date: Monday, 12/08/19
End date: Friday, 23/08/19
Traffic details: Road Closure     All Day
Promoter: Sure Guernsey
Contractor: Geomarine
Description: Work starting 07:00 AM on Mon 12 Aug 19 and finishing on Fri 23 Aug 19 - Installation of services



ST. PETER PORT - COUPEE LANE; LE GALET STEPS to

Start date: Tuesday, 13/08/19
End date: Friday, 27/09/19
Traffic details: Road Closure     All Day
Promoter: J W Rihoy Builders
Contractor: J W Rihoy Builders
Description: Work starting 08:00 AM on Tue 13 Aug 19 and finishing 04:00 PM on Fri 27 Sep 19 - Demolishing and rebuilding the wall



ST. PETER PORT - VAUVERT

Start date: Monday, 05/08/19
End date: Friday, 23/08/19
Traffic details: Road Closure     All Day
Promoter: JT Guernsey
Contractor: Geomarine
Description: Work starting 07:00 AM on Mon 05 Aug 19 and finishing 11:00 PM on Fri 23 Aug 19 - Network extension



ST. PETER PORT - LA COUTURE

Start date: Monday, 05/08/19
End date: Saturday, 31/08/19
Traffic details: Road Closure     All Day
Promoter: Guernsey Electricity
Contractor: Trant
Description: Work starting 08:00 AM on Mon 05 Aug 19 and finishing on Sat 31 Aug 19 - LV new pillar installation



ST. PETER PORT - LE POLLET; FOREST LANE to LA PLAIDERIE

Start date: Sunday, 18/08/19
End date: Friday, 23/08/19
Traffic details: Road Closure     All Day
Promoter: Guernsey Electricity
Contractor: Trant
Description: Work starting 09:00 AM on Sun 18 Aug 19 and finishing 11:00 PM on Fri 23 Aug 19 - LV service fault to Cancer Research Le Pollet



ST. PETER PORT - LOWER CANICHERS - THS

Start date: Thursday, 20/06/19
End date: Friday, 27/03/20
Traffic details: Road Closure     All Day
Promoter: RG Falla
Contractor: RG Falla
Description: Work starting on Thu 20 Jun 19 and finishing in March 20 - Demolish and rebuild of property



ST. PIERRE DU BOIS - RUE DU CAMP AU PRETRE

Start date: Monday, 19/08/19
End date: Tuesday, 20/08/19
Traffic details: Road Closure     All Day
Promoter: Traffic and Highway Services (Highways Inspector)
Contractor: States Works (Patching)
Description: Work starting 07:00 AM on Mon 19 Aug 19 and finishing 11:00 PM on Tue 20 Aug 19 - Road Improvements



ST. SAMPSON - NOCQ ROAD; SALTPANS ROAD to ROLAND ROAD

Start date: Monday, 19/08/19
End date: Friday, 30/08/19
Traffic details: Road Closure     All Day
Promoter: Geomarine
Contractor: Geomarine
Description: Work starting 07:00 AM on Mon 19 Aug 19 and finishing 05:00 PM on Fri 30 Aug 19 - New drain connection



Delays
ST. PETER PORT - UPLAND ROAD; MONUMENT GARDENS to MONUMENT ROAD

Start date: Monday, 12/08/19
End date: Wednesday, 21/08/19
Traffic details: Lanes Reduced     All Day
Promoter: Guernsey Electricity
Contractor: Trant
Description: Work starting 08:00 AM on Mon 12 Aug 19 and finishing on Fri 16 Aug 19 - New low voltage electricity cable installation at above location, both roads closure (we will try to arrange obstruction only for Upland Road). Rue Des Freres to be excavated from the Monday (12th), Upland road to be excavated from the Wednesday (14th)



FOREST - LA ROUTE DE FARRAS

Start date: Monday, 01/07/19
End date: Friday, 30/08/19
Traffic details: Portable Signals     All Day
Promoter: Sure Guernsey
Contractor: Geomarine
Description: Work starting 07:00 AM on Mon 01 Jul 19 and finishing 11:00 PM on Fri 30 Aug 19 - Network upgrade



ST. PETER PORT - COLBORNE ROAD; to HAVILLAND ROAD

Start date: Monday, 19/08/19
End date: Sunday, 25/08/19
Traffic details: Portable Signals     All Day
Promoter: Private Individual
Contractor: Private Individual
Description: Work starting 07:00 AM on Mon 19 Aug 19 and finishing 11:00 PM on Sun 25 Aug 19 - Repairs to roadside wall



ST. PETER PORT - VAUVERT; NEW PLACE to GEORGE STREET

Start date: Monday, 22/07/19
End date: Friday, 13/09/19
Traffic details: One Way (All Vehicles)     All Day
Promoter: Guernsey Electricity
Contractor: Trant
Description: Work starting 08:00 AM on Mon 22 Jul 19 and finishing 11:59 PM on Fri 13 Sep 19 - Substation rebuild in Burnt Lane - Section of Vauvert from George Street to Victoria Road is One-Way (Down) - Section of Burnt Lane between Vauvert and Port Vase closed to pedestrians.



FOREST - LE CHEMIN LE ROI

Start date: Monday, 19/08/19
End date: Monday, 26/08/19
Traffic details: One Way (All Vehicles)     All Day
Promoter: British Show Jumping Guernsey
Contractor: N/A
Description: Work starting 07:00 AM on Mon 19 Aug 19 and finishing 11:00 PM on Mon 26 Aug 19 - Horse riding event



ST. SAMPSON - ROUTE DE LA PASSEE; RUE DES COTTES to ROUTE DES PECQUERIES

Start date: Monday, 19/08/19
End date: Tuesday, 20/08/19
Traffic details: One Way (All Vehicles)     All Day
Promoter: Traffic and Highway Services (Highways Inspector)
Contractor: Geomarine
Description: Work starting 08:00 AM on Mon 19 Aug 19 and finishing 05:00 PM on Tue 20 Aug 19 - Footway improvement



Starting - next 5 days
Road closures
VALE - DEHUS LANE; LA MIELLETTE LANE to RUE DE L'EPINE

Start date: Tuesday, 20/08/19
End date: Wednesday, 21/08/19
Traffic details: Road Closure     All Day
Promoter: island scaffolding
Contractor: island scaffolding
Description: Work starting 07:00 AM on Tue 20 Aug 19 and finishing 04:00 PM on Wed 21 Aug 19 - Erecting scaffolding



ST. PETER PORT - ST. STEPHEN'S LANE; YORK AVENUE to LES CROUTES

Start date: Tuesday, 20/08/19
End date: Tuesday, 20/08/19
Traffic details: Road Closure     All Day
Promoter: Spruce Up
Contractor: Spruce Up
Description: Work starting 07:30 AM on Tue 20 Aug 19 and finishing 04:00 PM on Tue 20 Aug 19 - Removal of a tree by crane



CASTEL - RUETTE DES SAUMAREZ

Start date: Wednesday, 21/08/19
End date: Thursday, 22/08/19
Traffic details: Road Closure     All Day
Promoter: North Show Association
Contractor: N/A
Description: Work starting 06:00 AM on Wed 21 Aug 19 and finishing 11:00 PM on Thu 22 Aug 19 - North Show



ST. PETER PORT - HOSPITAL LANE; HIRZEL STREET to LA PLAIDERIE

Start date: Thursday, 22/08/19
End date: Thursday, 22/08/19
Traffic details: Road Closure     After PM Peak
Promoter: Channel Welders Ltd
Contractor: Channel Welders Ltd
Description: Work starting 05:00 PM and finishing 08:00 PM - Crane lift of steel into Valley House



CASTEL - VAZON ROAD; RUE DU GELE to LA ROCQUETTE

Start date: Saturday, 24/08/19
End date: Saturday, 24/08/19
Traffic details: Road Closure     All Day
Promoter: Guenrsey Kart and Motor Club
Contractor: N/A
Description: Work starting 11:00 AM on Sat 24 Aug 19 and finishing 06:00 PM on Sat 24 Aug 19 - Vazon Sprint



CASTEL - VAZON ROAD; RUE DU GELE to LA ROCQUETTE

Start date: Saturday, 24/08/19
End date: Saturday, 24/08/19
Traffic details: Road Closure     All Day
Promoter: GKMC
Contractor: N/A
Description: Work starting 01:00 PM on Sat 24 Aug 19 and finishing 06:30 PM on Sat 24 Aug 19 - Vazon Sprint August 2019



Delays
ST. SAMPSON - RUE SAUVAGE; COURTIL DE BAS LANE to LA GRANDE MAISON ROAD

Start date: Wednesday, 21/08/19
End date: Wednesday, 04/09/19
Traffic details: Portable Signals     All Day
Promoter: Another Level Ltd
Contractor: Another Level Ltd
Description: Work starting 08:00 AM on Wed 21 Aug 19 and finishing 06:00 PM on Wed 04 Sep 19 - Rebuilding roadside wall



ST. SAVIOUR - LA CROIX MARTIN; ROUTE DE LA ROCQUE to RUE DES BORDES

Start date: Wednesday, 21/08/19
End date: Friday, 20/09/19
Traffic details: Portable Signals     All Day
Promoter: Traffic and Highway Services (Roadworks Coordination)
Contractor: Traffic and Highway Services (Roadworks Coordination)
Description: Work starting 08:00 AM on Wed 21 Aug 19 and finishing 11:59 PM on Fri 20 Sep 19 - Temporary Traffic Signals for sea wall repair.