Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - RUE DES BERGERS
Description: Work starting 09:00 AM on Mon 01 Nov 21 and finishing 04:00 PM on Mon 31 Jan 22 - Rebuild stone roadside wall
Start date: Monday, 01/11/21 End date: Monday, 31/01/22 Timing: All Day
Promoter: Vaudin Stonemasons Contractor: Vaudin Stonemasons
Bus Routes Affected: Cycle Routes Affected: Yes

ST. ANDREW - RUE DES HOUGUES ( RUE DES BUTTES to MOURANTS ROAD )
Description: Work starting 12:00 AM on Sat 27 Nov 21 and finishing 05:00 PM on Tue 30 Nov 21 - Installation of water transfer pipework
Start date: Saturday, 27/11/21 End date: Tuesday, 30/11/21 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Routes Affected: Yes

ST. ANDREW - VERTE RUE ( CHEMIN LE ROI to )
Description: Work starting 07:00 AM on Mon 18 Oct 21 and finishing 11:59 PM on Tue 04 Jan 22 - Install water transfer pipework and surface water drainage
Start date: Monday, 18/10/21 End date: Tuesday, 04/01/22 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Routes Affected: NoDetails: No access past works

ST. MARTIN - LES CACHES ( LA GRANDE RUE to LA RUE MAZE )
Description: Work starting 07:00 AM and finishing 04:00 PM daily between Thu 25 Nov 21 and Mon 29 Nov 21 - Cover repairs
Start date: Thursday, 25/11/21 End date: Monday, 29/11/21 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - BOUILLON LANE
Description: Work starting 07:00 AM on Mon 15 Nov 21 and finishing 05:00 PM on Sat 15 Jan 22 - Scaffold for repairs to fire damaged roof; Property: Jamaica Inn; Purpose: Roofing Works
Start date: Monday, 15/11/21 End date: Saturday, 15/01/22 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - COUPEE LANE ( LE GALET STEPS to )
Description: Crane lifts of aircon units
Start date: Saturday, 27/11/21 End date: Sunday, 28/11/21 Timing: Between AM and PM Peaks
Promoter: Refco Contractor: Refco
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - LA RUE MARGUERITE
Description: Work starting 08:00 AM on Mon 05 Oct 20 and finishing 05:00 PM on Sun 31 Jul 22 - Construction of 5 storey office block and site set up
Start date: Monday, 05/10/20 End date: Sunday, 31/07/22 Timing: All Day
Promoter: J W Rihoy Builders Contractor: J W Rihoy Builders
Bus Routes Affected: Cycle Routes Affected: NoDetails: road barriered off

ST. PETER PORT - NEW STREET ( BERTHELOT STREET to LA RUE MARGUERITE )
Description: Work starting 08:00 AM on Sat 27 Nov 21 and finishing 04:00 PM on Fri 03 Dec 21 - LV Mains Cable fault outside Claigmar House
Start date: Saturday, 27/11/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - VICTORIA PIER
Description: Work starting 07:00 AM on Mon 10 May 21 and finishing 07:00 AM on Fri 31 Dec 21 - Building of Marquis for Covid testing of visitors 28 spaces initially dropping to 20 once built.
Start date: Monday, 10/05/21 End date: Friday, 31/12/21 Timing: All Day
Promoter: Guernsey Harbours Contractor: Guernsey Harbours
Bus Routes Affected: Cycle Routes Affected: NoDetails: no access

ST. PETER PORT - WATER LANES
Description: Work starting 07:00 AM on Mon 22 Nov 21 and finishing 04:00 PM on Fri 03 Dec 21 - Installation of services
Start date: Monday, 22/11/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Routes Affected: Yes

ST. SAMPSON - RUE JACQUES ( to SALTPANS ROAD )
Description: Work starting 08:00 AM on Mon 22 Nov 21 and finishing 05:00 PM on Fri 03 Dec 21 - Rebuild roadside wall and drainage works
Start date: Monday, 22/11/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Routes Affected: Yes

ST. SAVIOUR - RUE DES ISSUES ( RUE FEVERESSE to RUE CEVECQ )
Description: Work starting 07:00 AM on Wed 24 Nov 21 and finishing 05:00 PM on Thu 23 Dec 21 - Undertake edge repairs
Start date: Wednesday, 24/11/21 End date: Thursday, 23/12/21 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Crocker Engineering
Bus Routes Affected: Cycle Routes Affected: Yes

VALE - THE BRIDGE
Description: Work starting 07:30 AM on Mon 15 Nov 21 and finishing 04:00 PM on Fri 03 Dec 21 - Road resurfacing
Start date: Monday, 15/11/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: P2, 11, 12, 13, 91, 92, N1 Cycle Routes Affected: RestrictedDetails: Dismount signage

VALE_ST. SAMPSON - RUE DES ANNEVILLES
Description: Work starting 07:30 AM on Mon 08 Nov 21 and finishing 04:00 PM on Fri 03 Dec 21 - Road resurfacing
Start date: Monday, 08/11/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: States Works (Patching)
Bus Routes Affected: Cycle Routes Affected: RestrictedDetails: Dismount signage

One Ways
No current major delays due to one ways
Signals
No current major delays due to signals

Starting - next 7 days
Closures
CASTEL - LA ROCQUETTE ( RUE DE LA VIEILLE MARE to VAZON ROAD )
Description: Work starting 08:00 AM on Thu 02 Dec 21 and finishing 05:00 PM on Wed 22 Dec 21 - REPLACE VALVES AND LEAVE LEGS INTO CLOS
Start date: Thursday, 02/12/21 End date: Wednesday, 22/12/21 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: 42 Cycle Routes Affected: Yes

CASTEL - ROUTE DU TERTRE ( RUE DE LA MASSE to LES QUERITES )
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Wed 01 Dec 21 - Closure to allow for a replacement Service
Start date: Monday, 29/11/21 End date: Wednesday, 01/12/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Routes Affected: Yes

CASTEL - RUE DU GELE ( LES GRANDS MOULINS to RUETTE DU ROCHER )
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Wed 01 Dec 21 - Closure to allow for service alteration
Start date: Monday, 29/11/21 End date: Wednesday, 01/12/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 60, 61, N2 Cycle Routes Affected: Yes

ST. ANDREW - LA BRIGADE ( LES VAURIOUFS to LES MAUXMARQUIS (ROUTE DE ST. AND )
Description: Work starting 07:00 AM on Sun 28 Nov 21 and finishing 06:00 PM on Sun 28 Nov 21 - CCTV Investigation ( Onsite )
Start date: Sunday, 28/11/21 End date: Sunday, 28/11/21 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Routes Affected: Yes

ST. ANDREW - RUE DES POINTES ( ROUTE DE LA CROIX AU BAILIFF to )
Description: Work starting 08:00 AM on Sat 04 Dec 21 and finishing 04:00 PM on Sun 05 Dec 21 - Road improvements
Start date: Saturday, 04/12/21 End date: Sunday, 05/12/21 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Ronez (Private Works)
Bus Routes Affected: Cycle Routes Affected: NoDetails: Works in narrow road

ST. MARTIN - LES HUBITS ( LES TRAUDES to HUBITS DE BAS )
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Mon 10 Jan 22 - Building of canopy scaffolding
Start date: Monday, 29/11/21 End date: Monday, 10/01/22 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - COLLINGS ROAD
Description: Work starting 06:30 PM and finishing 06:00 AM - CCTV Investigation ( Onsite )
Start date: Wednesday, 01/12/21 End date: Thursday, 02/12/21 Timing: After PM Peak
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 51, 52 Cycle Routes Affected: Yes

ST. PETER PORT - CROUTES HAVILLAND ( FORT ROAD to DAMOUETTES LANE )
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Thu 02 Dec 21 - Electricity service cable upgrade
Start date: Monday, 29/11/21 End date: Thursday, 02/12/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Routes Affected: RestrictedDetails: Barriered Walkway, dismount

ST. PETER PORT - FIRST TOWER LANE ( LE GRAND BOUET to LES BANQUES )
Description: Work starting 08:00 AM on Wed 01 Dec 21 and finishing 04:00 PM on Fri 03 Dec 21 - cut off gas service from road
Start date: Wednesday, 01/12/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - LA COUTURE ( COLLINGS ROAD to LA VRANGUE )
Description: Work starting 07:00 PM and finishing 06:00 AM - CCTV Investigation ( Onsite )
Start date: Tuesday, 30/11/21 End date: Wednesday, 01/12/21 Timing: After PM Peak
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 51, 52 Cycle Routes Affected: Yes

ST. PETER PORT - LA COUTURE
Description: Work starting 12:05 AM and finishing 06:00 AM - CCTV Survey ( Onsite )
Start date: Wednesday, 01/12/21 End date: Wednesday, 01/12/21 Timing: Before AM Peak
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 51, 52 Cycle Routes Affected: Yes

ST. PETER PORT - LES ECHELONS ( SOUTH ESPLANADE to SOUTH ESPLANADE )
Description: Work starting 07:00 AM and finishing 01:00 PM - Building Maintenance
Start date: Sunday, 28/11/21 End date: Sunday, 28/11/21 Timing: Between AM and PM Peaks
Promoter: q3 services Contractor: q3 services
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - LES GRAVEES /
Description: Work starting 07:00 PM and finishing 06:00 AM - CCTV Investigation ( Onsite )
Start date: Monday, 29/11/21 End date: Tuesday, 30/11/21 Timing: After PM Peak
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 41, 42, 51, 52, 61, 71, 81, N2 Cycle Routes Affected: Yes

ST. PETER PORT - Xmas Town Shopping
Description: Work starting 05:00 PM and finishing 09:00 PM - Xmas Town Shopping
Start date: Thursday, 02/12/21 End date: Thursday, 02/12/21 Timing: After PM Peak
Promoter: ND Events Contractor: N/A
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PIERRE DU BOIS - RUE DES LANDES ( RUE DES RONDIAUX to RUE DES PRES )
Description: Work starting 08:00 AM on Mon 29 Nov 21 and finishing 12:00 PM on Mon 29 Nov 21 - House move
Start date: Monday, 29/11/21 End date: Monday, 29/11/21 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Routes Affected: Yes

ST. SAMPSON - RONDE CHEMINEE ( to BROCK ROAD )
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Wed 15 Dec 21 - Installation of services
Start date: Monday, 29/11/21 End date: Wednesday, 15/12/21 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Routes Affected: RestrictedDetails: Mount/dismount passed working area

ST. SAVIOUR - RUE DES BOULAINS ( LES TRANQUESOUS to RUE DES GRANTEZ )
Description: Work starting 08:00 AM on Wed 01 Dec 21 and finishing 05:00 PM on Wed 01 Dec 21 - Road improvements
Start date: Wednesday, 01/12/21 End date: Wednesday, 01/12/21 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Routes Affected: RestrictedDetails: minor lane

ST. SAVIOUR - RUE DU DOUIT MANCHOT
Description: Work starting 08:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Tue 30 Nov 21 - Road improvements
Start date: Monday, 29/11/21 End date: Tuesday, 30/11/21 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Ronez (Private Works)
Bus Routes Affected: Cycle Routes Affected: RestrictedDetails: Minor lane

VALE - LANDES DU MARCHE ( DOUIT LANE to LONGUE RUE )
Description: Work starting 07:00 AM and finishing 10:00 AM - Replace pumping valve
Start date: Sunday, 28/11/21 End date: Sunday, 28/11/21 Timing: Between AM and PM Peaks
Promoter: States Works Dept Contractor: States Works Dept
Bus Routes Affected: P2 Cycle Routes Affected: Yes

VALE - LANDES DU MARCHE ( DOUIT LANE to LONGUE RUE )
Description: Work starting 07:00 AM and finishing 10:00 AM - Change air valve
Start date: Sunday, 28/11/21 End date: Sunday, 28/11/21 Timing: Between AM and PM Peaks
Promoter: States Works Dept Contractor: States Works Dept
Bus Routes Affected: P2 Cycle Routes Affected: Yes

VALE - LES BARRAS LANE ( LES GRANDES MIELLES LANE to PLEINHEAUME ROAD )
Description: Work starting 06:00 AM on Wed 01 Dec 21 and finishing 05:00 PM on Wed 08 Dec 21 - Drainage Connection
Start date: Wednesday, 01/12/21 End date: Wednesday, 08/12/21 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Routes Affected: Yes

VALE - ROUTE DE LA CHARRUEE ( RUE COHU to PRIVATE ROAD )
Description: Work starting 07:00 AM on Wed 01 Dec 21 and finishing 05:00 PM on Wed 15 Dec 21 - Replace fuse pillar.
Start date: Wednesday, 01/12/21 End date: Wednesday, 15/12/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 41, 42, N2 Cycle Routes Affected: Yes

VALE - SOHIER ROAD
Description: Work starting 09:00 AM and finishing 12:00 PM - Replace pumping valve
Start date: Sunday, 28/11/21 End date: Sunday, 28/11/21 Timing: Between AM and PM Peaks
Promoter: States Works Dept Contractor: States Works Dept
Bus Routes Affected: P2, 11 Cycle Routes Affected: Yes

VALE - SOHIER ROAD
Description: Work starting 10:00 AM and finishing 12:00 PM - Change air valve
Start date: Sunday, 28/11/21 End date: Sunday, 28/11/21 Timing: Between AM and PM Peaks
Promoter: States Works Dept Contractor: States Works Dept
Bus Routes Affected: P2, 11 Cycle Routes Affected: Yes

VALE_ST. SAMPSON - Father Christmas turnining on Christmas lights
Description: Work starting 02:00 PM on Fri 03 Dec 21 and finishing 07:00 PM on Fri 03 Dec 21 - Father Christmas turnining on Christmas lights
Start date: Friday, 03/12/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Private Individual Contractor: N/A
Bus Routes Affected: P2 (Off Route), 11, 12, 13, 91, 92, N1 Cycle Routes Affected: Yes

One Ways
ST. ANDREW - LA VASSALERIE ( ROUTE DE ST. ANDRE to MOURANTS ROAD )
Description: Work starting 07:00 AM on Wed 01 Dec 21 and finishing 05:00 PM on Fri 03 Dec 21 - Repair road gullies
Start date: Wednesday, 01/12/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Geomarine
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - FOSSE ANDRE ( CORONATION ROAD to MAUREPAS ROAD )
Description: Work starting 08:00 AM on Wed 01 Dec 21 and finishing 04:00 PM on Wed 01 Dec 21 - House move from Maple Leaf Cottage
Start date: Wednesday, 01/12/21 End date: Wednesday, 01/12/21 Timing: All Day
Promoter: relocation worldwide Contractor: relocation worldwide
Bus Routes Affected: Cycle Routes Affected: Yes

ST. PETER PORT - LA COUTURE ( COLLINGS ROAD to LA VRANGUE )
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Tue 30 Nov 21 - Streetlight replacement La Couture St. Peter Port
Start date: Monday, 29/11/21 End date: Tuesday, 30/11/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 51, 52 Cycle Routes Affected: Yes

ST. PETER PORT - LE GRAND BOUET
Description: Rebuild roadside wall
Start date: Wednesday, 01/12/21 End date: Friday, 03/12/21 Timing: All Day
Promoter: Stoneworks Ltd Contractor: Stoneworks Ltd
Bus Routes Affected: 31, 32, 51, 52 Cycle Routes Affected: Yes

ST. SAVIOUR - RUE FEVERESSE
Description: Work starting 04:00 PM and finishing 10:00 PM - Xmas lighting display
Start date: Wednesday, 01/12/21 End date: Wednesday, 01/12/21 Timing: After PM Peak
Promoter: Cancer Research Contractor: N/A
Bus Routes Affected: Cycle Routes Affected: Yes

Signals
ST. PETER PORT - ST. GEORGE'S ESPLANADE
Description: Work starting 07:00 AM on Mon 29 Nov 21 and finishing 05:00 PM on Thu 02 Dec 21 - Suspended Parking & Traffic Lights in order to replace a service. PLEASE NOTE: Day one is suspended parking only. Traffic Lights to commence on Tuesday 30th until Thurs 2nd
Start date: Monday, 29/11/21 End date: Thursday, 02/12/21 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Routes Affected: Yes