Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - ROUTE DE LA HOUGUE DU POMMIER
Description: Work starting 08:30 AM on Tue 01 Sep 26 and finishing 05:00 PM on Mon 21 Dec 26 - Install new 400mm water ring main pipework
Start date: Tuesday, 01/09/26 End date: Monday, 21/12/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: LMDC 6A / LV 6A; 41;42;N2 Cycle Access: Dismount past works

FOREST - RUE DES AUBERTS ( LE BOURG to )
Description: Primary substation replacement
Start date: Monday, 22/06/26 End date: Friday, 27/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: No

ST. ANDREW - LES POIDEVINS
Description: Hiab Lift
Start date: Wednesday, 11/11/26 End date: Thursday, 19/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. ANDREW - LES RUETTES ( ROUTE DE LA CROIX AU BAILIFF to FOULON ROAD )
Description: Works to roadside driveway
Start date: Monday, 09/11/26 End date: Monday, 16/11/26 Timing: All Day
Promoter: Tarmac Services Contractor: Tarmac Services
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - COIN COLIN
Description: Work starting 07:30 AM on Mon 09 Nov 26 and finishing 04:00 PM on Fri 20 Nov 26 - Road resurfacing
Start date: Monday, 09/11/26 End date: Friday, 20/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: No

ST. MARTIN - VILLE AMPHREY ( RUETTE RABEY to )
Description: Roads resurfacing
Start date: Wednesday, 11/11/26 End date: Friday, 13/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: St Martin PS 3A;St Martin PS 3B;LBHS 1A;LBHS 1B;LBHS 2A;LBHS 3B;LV HS 4B;LV HS 6B;LV HS 9B Cycle Access: Dismount past works

ST. PETER PORT - BERTHELOT STREET
Description: Work starting 07:30 AM on Mon 17 Mar 25 and finishing 11:59 PM on Thu 31 Dec 26 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
Start date: Monday, 17/03/25 End date: Thursday, 31/12/26 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - COLLINGS ROAD
Description: supply line upgrade
Start date: Wednesday, 11/11/26 End date: Friday, 13/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vauvert 1A; Vauvert 1B Cycle Access: Dismount past works

ST. PETER PORT - DOYLE STREET ( LOWER CANICHERS to LE TRUCHOT )
Description: Construction of an accessible ramp outside the rear of Sarnia House on Doyle Street.
Start date: Sunday, 08/11/26 End date: Saturday, 14/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - FORT ROAD
Description: Fermain Lane Substation replacement phase 2
Start date: Monday, 09/11/26 End date: Monday, 30/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 2A; LB 3B; LV 4A; 91;92;93;94;95;N3 Cycle Access: Dismount past works

ST. PETER PORT - THE STRAND ( CLIFF STREET to HAVELET )
Description: works being done to 16 Hauteville in the back carpark which leads onto main road, large vehichels will need to access and will be in the way along with works to be carried out
Start date: Monday, 02/11/26 End date: Tuesday, 01/12/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - LES REINES
Description: Erect Scaffolding; Property: Les Reines; Purpose: Roofing Works
Start date: Monday, 19/10/26 End date: Friday, 11/12/26 Timing: All Day
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Forest PS 1A;Forest PS 1B;LB HS 6A;LB HS 6B;LV HS 5A;LV HS 5A Overflow;LV HS 5B;LV HS LB HS 5A;LV HS LB HS 5B Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DU BORDAGE ( RUE DU CAMP AU PRETRE to RUE DE LA FONTENELLE )
Description: building gable wall.
Start date: Friday, 28/08/26 End date: Wednesday, 23/12/26 Timing: All Day
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - ROUTE MILITAIRE
Description: Work starting 07:30 AM on Thu 12 Nov 26 and finishing 05:00 PM on Tue 17 Nov 26 - New supply line
Start date: Thursday, 12/11/26 End date: Tuesday, 17/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vale 1A; Vale 3B; SS 4A; SS 5A; SS 6A; SS 8A; 13;21 Cycle Access: Dismount past works

ST. SAMPSON - ROUTE MILITAIRE
Description: High voltage substation installation, high and low voltage cable upgrade and service upgrades
Start date: Monday, 28/09/26 End date: Friday, 18/12/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vale 1A; Vale 3B; SS 4A; SS 5A; SS 6A; SS 8A; 13;21 Cycle Access: Dismount past works

ST. SAMPSON - RUE QUERIPEL; SALTPANS ROAD to ROBERGERIE ( SALTPANS ROAD to ROBERGERIE )
Description: Scaffolding
Start date: Friday, 06/11/26 End date: Friday, 04/12/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - LES BUTTES
Description: Tree surgery
Start date: Monday, 09/11/26 End date: Friday, 13/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: 71 Cycle Access: No

ST. SAVIOUR - ROUTE DE LA PERELLE
Description: CAVITY IN THE ROAD
Start date: Tuesday, 10/11/26 End date: Tuesday, 17/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Traffic and Highway Services (Highways Inspector)
Bus Routes Affected: 61, 91, 92, N3 Cycle Access: Dismount past works

VALE - LA BAILLOTERIE LANE; LA ROUTE DU BRAYE to RUE DES HAIZES ( LA ROUTE DU BRAYE to RUE DES HAIZES )
Description: Essential upgrade to Gas Main Netork
Start date: Tuesday, 10/11/26 End date: Monday, 16/11/26 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: No

VALE - ROUTE DE LA CHARRUEE
Description: Work starting 08:30 AM on Tue 01 Sep 26 and finishing 05:00 PM on Wed 23 Dec 26 - Upsize existing water main
Start date: Tuesday, 01/09/26 End date: Wednesday, 23/12/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: LMDC 6A / LV 6A; 41;42;N2 Cycle Access: Dismount past works

VALE - RUE DES HAIZES
Description: Essential maintenance to gas Mains and Services.
Start date: Monday, 02/11/26 End date: Monday, 16/11/26 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: No

VALE - RUE DU CHARDRONNET ( LA RUE DE PARADIS to RUE DE DESSOUS )
Description: Erect Scaffold to enable roof repairs
Start date: Monday, 26/10/26 End date: Thursday, 26/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

VALE - VALE-MISC54 ( ROCQUE ES CAS to LA MOYE ROAD )
Description: Work starting 10:00 AM on Tue 14 Jul 26 and finishing 11:30 PM on Thu 31 Dec 26 - Deliveries and Barn renovations
Start date: Tuesday, 14/07/26 End date: Thursday, 31/12/26 Timing: All Day
Promoter: Omega Group Contractor: Omega Group
Bus Routes Affected: Vale PS 2B;Vale PS 3B Cycle Access: Dismount past works

One Ways
No current major delays due to one ways
Signals
CASTEL - RUE DE LA SALINE ( ROUTE DE LA MARE DE CARTERET to GRANDES ROCQUES BU )
Description: COASTAL WALL REPAIR.
Start date: Monday, 07/09/26 End date: Friday, 18/12/26 Timing: All Day
Promoter: States Property Unit Contractor: States Property Unit
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
CASTEL - ROUTE DES TALBOTS ( LES PETITES VALLEES to RUE DU TORVAL )
Description: Tree Surgery at National Trust land.
Start date: Monday, 16/11/26 End date: Tuesday, 17/11/26 Timing: All Day
Promoter: Guernsey Tree Service Ltd Contractor: Guernsey Tree Service Ltd
Bus Routes Affected: Cycle Access: Dismount past works

CASTEL - RUE DU PRESBYTERE
Description: service alteration
Start date: Monday, 16/11/26 End date: Wednesday, 18/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Castel 1A; St Martin 1B; 51;52 Cycle Access: Dismount past works

FOREST - LES REBOUQUETS ( LES HURETTES to FOREST ROAD )
Description: Treesurgery work from cherry picker
Start date: Wednesday, 18/11/26 End date: Thursday, 19/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

FOREST - RUE DE LA CORBIERE ( to LA RUE DE MANOIR COTE SUD )
Description: Rebuilding wall
Start date: Monday, 16/11/26 End date: Thursday, 19/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. ANDREW - ROUTE DE ST. ANDRE
Description: Emergency Tree Surgery
Start date: Wednesday, 18/11/26 End date: Wednesday, 18/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: 71, N4 Cycle Access: Dismount past works

ST. PETER PORT - BACK STREET ( MANSELL STREET to VAUVERT )
Description: repairs and refurbishment works to three streetlights
Start date: Tuesday, 17/11/26 End date: Tuesday, 17/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BROCK ROAD
Description: Sewer cleaning
Start date: Monday, 16/11/26 End date: Monday, 16/11/26 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: 31 Cycle Access: Dismount past works

ST. PETER PORT - French Market
Description: French Market on Red Light Arm of Albert Pier.
Start date: Wednesday, 18/11/26 End date: Sunday, 22/11/26 Timing: All Day
Promoter: States of Guernsey - Communications and Marketing Contractor: N/A
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - LE TRUCHOT
Description: Work starting 08:00 AM on Sun 15 Nov 26 and finishing 04:00 PM on Sun 15 Nov 26 - Crane Lift
Start date: Sunday, 15/11/26 End date: Sunday, 15/11/26 Timing: All Day
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LES VAUXLAURENS ( ST. JULIAN'S AVENUE to )
Description: Gutter Cleaning and clearing using a cherry picker
Start date: Sunday, 15/11/26 End date: Sunday, 15/11/26 Timing: All Day
Promoter: Premium Cleaning Services Contractor: Premium Cleaning Services
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - ROHAIS
Description: Tree Surgery
Start date: Thursday, 19/11/26 End date: Thursday, 19/11/26 Timing: All Day
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: Vauvert 1B; LMDC 6A / LV 6A; LMDC 6B / LV 6B; LMDC 7A; LMDC 7B; LV 4A; 41;42;N2 Cycle Access: Dismount past works

ST. PETER PORT - SOUTH ESPLANADE ( LES ECHELONS to )
Description: Tree Surgery.
Start date: Sunday, 15/11/26 End date: Sunday, 15/11/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DES CLERCS ( ROUTE DE LA LAGUE to RUE DU CAMPERE )
Description: Site compound / welfare area for adjacent construction site
Start date: Thursday, 19/11/26 End date: Wednesday, 23/12/26 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DU PONT ( RUE TREMEL to RUE DES RAIES )
Description: Tree surgery in lane between 8am and 4pm each day.
Start date: Monday, 16/11/26 End date: Tuesday, 17/11/26 Timing: All Day
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAMPSON - Guernsey Football Association
Description: GFC match - road closure
Start date: Saturday, 14/11/26 End date: Saturday, 14/11/26 Timing: Between AM and PM Peaks
Promoter: Guernsey Football Association Contractor: N/A
Bus Routes Affected: Vale 2A Cycle Access: Yes:

ST. SAMPSON - SALINES LANE
Description: CCTV, Cleaning and Sewer Repair
Start date: Wednesday, 18/11/26 End date: Thursday, 19/11/26 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - RUE DU DOUIT MANCHOT
Description: Road resurfacing
Start date: Monday, 16/11/26 End date: Friday, 20/11/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Dismount past works

VALE - L`ETONNELLERIE ( LES GRANDES MIELLES LANE to PLEINHEAUME ROAD )
Description: Replace old water meters
Start date: Monday, 16/11/26 End date: Thursday, 19/11/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

VALE - LONGREE
Description: Install new telecoms connection
Start date: Monday, 16/11/26 End date: Monday, 23/11/26 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

VALE - LONGREE
Description: Work starting 07:30 AM on Mon 16 Nov 26 and finishing 05:00 PM on Mon 30 Nov 26 - Install new water services and shut off old service
Start date: Monday, 16/11/26 End date: Monday, 30/11/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

VALE - LONGREE
Description: Install new electric services
Start date: Monday, 16/11/26 End date: Monday, 30/11/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

One Ways
ST. ANDREW - ST. ANDREW - ST. ANDREW - Funeral at St Andrews Church
Description: Funeral
Start date: Tuesday, 17/11/26 End date: Tuesday, 17/11/26 Timing: Between AM and PM Peaks
Promoter: Beckfords Funeral Services Ltd Contractor: N/A
Bus Routes Affected: LB 4A Cycle Access: Yes, in direction of one-way

Signals
No future major delays due to signals