Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.
CASTEL - RUETTE DE LA GENEROTTE
|
( ROUTE DE COBO to RUETTE DE FRIES )
|
Description:
|
Rebuilding roadside wall.
|
Start date:
|
Monday, 06/01/25
|
End date:
|
Monday, 03/02/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Adie Exall Stonemason
|
Contractor:
|
Adie Exall Stonemason
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
CASTEL - RUETTE DE TOUILLETS
|
( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
|
Description:
|
Work starting 08:00 AM on Sat 19 Aug 23 and finishing 05:00 PM on Fri 28 Feb 25 - Investigation and repairs to roadside wall
|
Start date:
|
Saturday, 19/08/23
|
End date:
|
Friday, 28/02/25
|
Timing:
All Day
|
Promoter:
|
Private Individual
|
Contractor:
|
Private Individual
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
Emergency Activity - CASTEL - RUE DE LA RONDE CHEMINEE
|
|
Description:
|
Carry out emergency network repair works
|
Start date:
|
Friday, 17/01/25
|
End date:
|
Friday, 31/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
41
|
Cycle Access:
|
Dismount past works
|
Emergency Activity - ST. MARTIN - LES CAMPS
|
|
Description:
|
Work starting 02:00 PM on Mon 20 Jan 25 and finishing 05:00 PM on Thu 06 Feb 25 - Emergency works to repair High voltage cable fault
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Thursday, 06/02/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
81;91;93;94;95;N3;LBHS 2A;LV HS 4A;LV HS 4B
|
Cycle Access:
|
No
|
FOREST - ROUTE DES BLICQS
|
( LE RUSSEL ROAD to LES BLICQS LANE )
|
Description:
|
New supply line
|
Start date:
|
Tuesday, 21/01/25
|
End date:
|
Thursday, 23/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. MARTIN - LA BELLIEUSE
|
|
Description:
|
Work starting 08:30 AM on Mon 13 Jan 25 and finishing 05:00 PM on Mon 03 Feb 25 - Relay approx. 200 meters of new water main
|
Start date:
|
Monday, 13/01/25
|
End date:
|
Monday, 03/02/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
ST. MARTIN - LE ROCHER
|
( LES AUBRETS to LA FOSSE DE BAS )
|
Description:
|
Work starting 08:00 AM on Mon 13 Jan 25 and finishing 05:00 PM on Wed 22 Jan 25 - Excavate, clear and rod blocked ducts
|
Start date:
|
Monday, 13/01/25
|
End date:
|
Wednesday, 22/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. MARTIN - LES HURETTES
|
|
Description:
|
Work starting 07:00 AM on Mon 06 Jan 25 and finishing 05:00 PM on Wed 12 Feb 25 - High and low voltage cable installation, jointing and fibre duct pull
|
Start date:
|
Monday, 06/01/25
|
End date:
|
Wednesday, 12/02/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Guernsey Electricity
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - HAVILLAND STREET
|
( GRANGE ROAD to ALLEZ STREET )
|
Description:
|
Excavate blocked duct
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Tuesday, 21/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - LE BOUET
|
|
Description:
|
Work starting 08:00 AM and finishing 05:00 PM daily between Wed 16 Oct 24 and Fri 07 Mar 25 - Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
|
Start date:
|
Wednesday, 16/10/24
|
End date:
|
Friday, 07/03/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. PETER PORT - LE BOUET
|
|
Description:
|
Work starting 08:00 AM and finishing 11:59 PM daily between Wed 16 Oct 24 and Sun 30 Mar 25 - Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
|
Start date:
|
Wednesday, 16/10/24
|
End date:
|
Sunday, 30/03/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
ST. PETER PORT - LES PETITES FONTAINES
|
( MOUNT HERMON to VALNORD ROAD )
|
Description:
|
Work starting 11:30 AM on Fri 22 Nov 24 and finishing 05:00 PM on Fri 31 Jan 25 - wall repairs
|
Start date:
|
Friday, 22/11/24
|
End date:
|
Friday, 31/01/25
|
Timing:
All Day
|
Promoter:
|
TNT Stonemasons
|
Contractor:
|
TNT Stonemasons
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - LES VAUXLAURENS
|
|
Description:
|
Scaffolding; Property: No 1 St Julians Avenue; Purpose: Roofing Works
|
Start date:
|
Friday, 29/11/24
|
End date:
|
Sunday, 26/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. PETER PORT - LES VAUXLAURENS
|
|
Description:
|
Scaffold to access for emergency works from storm damage; Property: Apartments 4 and 29 St Julians Avenue; Purpose: Roofing Works
|
Start date:
|
Friday, 29/11/24
|
End date:
|
Sunday, 26/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. PETER PORT - LOWER CANICHERS
|
( LE TRUCHOT to DOYLE STREET )
|
Description:
|
Work starting 08:00 AM on Mon 30 Sep 24 and finishing 07:00 AM on Mon 28 Apr 25 - building repair and refit
|
Start date:
|
Monday, 30/09/24
|
End date:
|
Monday, 28/04/25
|
Timing:
All Day
|
Promoter:
|
Ravenscroft Construction Ltd
|
Contractor:
|
Ravenscroft Construction Ltd
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - LOWER POLLET
|
( ST. JULIAN'S WEIGHBRIDGE to LA TOURGAND )
|
Description:
|
Work starting 08:00 AM on Mon 20 Jan 25 and finishing 05:00 PM on Wed 22 Jan 25 - Chamber installation
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Wednesday, 22/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - THE STRAND
|
|
Description:
|
Scaffold for construction; Property: La Coquere; Purpose: Demolition / New Build
|
Start date:
|
Wednesday, 10/07/24
|
End date:
|
Saturday, 12/04/25
|
Timing:
All Day
|
Promoter:
|
Impact Scaffolding
|
Contractor:
|
Impact Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PIERRE DU BOIS - ROUTE DE LIHOU
|
( RUE DU LONGFRIE to RUE DES GRANDES RUES )
|
Description:
|
Work starting 09:00 AM on Thu 29 Aug 24 and finishing 05:00 PM on Sat 15 Mar 25 - Road blocked due to collapsed granite wall approx 10m from the Route de Lihou and Rue du Longfrie junction, near property Longfrie House.
|
Start date:
|
Thursday, 29/08/24
|
End date:
|
Saturday, 15/03/25
|
Timing:
All Day
|
Promoter:
|
Traffic and Highways
|
Contractor:
|
Traffic and Highways
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
ST. PIERRE DU BOIS - ROUTE DU LONGFRIE
|
|
Description:
|
Work starting 07:30 AM on Mon 20 Jan 25 and finishing 04:00 PM on Fri 31 Jan 25 - Road resurfacing
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Friday, 31/01/25
|
Timing:
All Day
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
Bus Routes Affected:
|
60;71;93;94;N3;N4
|
Cycle Access:
|
Dismount past works
|
ST. SAMPSON - SANDY LANE
|
|
Description:
|
Low voltage cabling and service upgrades
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Friday, 21/02/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
P2;13;21;N1;Capelles PS 2B;LV HS 1B;LV HS 8A;SS HS 1A;SS HS 1B
|
Cycle Access:
|
Yes, in direction of one-way
|
ST. SAVIOUR - LES TRANQUESOUS
|
( RUE DES BOULAINS to RUE DES CACHES )
|
Description:
|
Node installation 9am - 4pm daily
|
Start date:
|
Tuesday, 21/01/25
|
End date:
|
Thursday, 23/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Sure Guernsey
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. SAVIOUR - ROUTE DE SOUS L`EGLISE
|
|
Description:
|
Chamber and duct installations
|
Start date:
|
Thursday, 02/01/25
|
End date:
|
Monday, 27/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
N4;Houguette PS 2B;Houguette PS 4B;LMDC HS 3A;LMDC HS 3B;LV HS 5A;LMDC HS LB HS 3A;LMDC HS LB HS 3B;LV HS LB HS 5A;LV HS LB HS 5B
|
Cycle Access:
|
Dismount past works
|
ST. SAVIOUR - RUE DES ISSUES
|
|
Description:
|
Fibre cable installations
|
Start date:
|
Tuesday, 21/01/25
|
End date:
|
Tuesday, 21/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Sure Guernsey
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
TORTEVAL - RUE DES JEHANS
|
|
Description:
|
Work starting 07:30 AM on Mon 20 Jan 25 and finishing 04:00 PM on Fri 07 Feb 25 - Road resurfacing
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Friday, 07/02/25
|
Timing:
All Day
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
CASTEL - RUE DU FRIQUET
|
|
Description:
|
Alteration to network control box
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Tuesday, 21/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
P2
|
Cycle Access:
|
No
|
Emergency Activity - ST. PETER PORT - QUEENS ROAD
|
|
Description:
|
Work starting 05:55 PM on Mon 20 Jan 25 and finishing 05:00 PM on Tue 21 Jan 25 - Emergency Works - Streetlight Damage
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Tuesday, 21/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
60;61;71;81;N4;Forest PS 2B;St Martin PS 1A
|
Cycle Access:
|
Dismount past works
|
CASTEL - ROUTE DE COBO
|
|
Description:
|
Rebuilding roadside wall.
|
Start date:
|
Monday, 13/01/25
|
End date:
|
Sunday, 26/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Granite Le Pelley
|
Contractor:
|
Granite Le Pelley
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
CASTEL - ROUTE DE COBO
|
|
Description:
|
Rebuilding roadside wall.
|
Start date:
|
Monday, 13/01/25
|
End date:
|
Sunday, 26/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Granite Le Pelley
|
Contractor:
|
Granite Le Pelley
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. PETER PORT - FORT ROAD; LE VAL DES TERRES to CROUTES HAVILLAND
|
( LE VAL DES TERRES to CROUTES HAVILLAND )
|
Description:
|
Supply line upgrade
|
Start date:
|
Monday, 20/01/25
|
End date:
|
Thursday, 23/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. PETER PORT - LES BANQUES
|
|
Description:
|
Work starting 05:00 AM on Mon 13 Jan 25 and finishing 05:00 PM on Tue 28 Jan 25 - repair of sea defences
|
Start date:
|
Monday, 13/01/25
|
End date:
|
Tuesday, 28/01/25
|
Timing:
All Day
|
Promoter:
|
States Property Services
|
Contractor:
|
States Property Services
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - LES GRAVEES; ROCQUETTES LANE to YORK AVENUE
|
( ROCQUETTES LANE to YORK AVENUE )
|
Description:
|
Work starting 09:00 AM and finishing 05:00 PM daily between Mon 13 Jan 25 and Sun 09 Mar 25 - Repairs to roadside wall
|
Start date:
|
Monday, 13/01/25
|
End date:
|
Sunday, 09/03/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
J W Rihoy Builders
|
Contractor:
|
J W Rihoy Builders
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
CASTEL - RUE DE LA HAYE
|
( RUE DES CACHES to RUE DES GRANTEZ )
|
Description:
|
Node installation 8am - 4pm daily
|
Start date:
|
Thursday, 23/01/25
|
End date:
|
Friday, 24/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Sure Guernsey
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
CASTEL - RUE DE LA VIEILLE MARE
|
|
Description:
|
supply line alteration
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Wednesday, 29/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
42;60;Castel PS 2A;LMDC HS LB HS 3B
|
Cycle Access:
|
Dismount past works
|
CASTEL - RUE DU FRIQUET
|
( LES BAISSIERES to ROUTE DE COBO )
|
Description:
|
Work starting 07:00 AM on Mon 27 Jan 25 and finishing 05:00 PM on Fri 31 Jan 25 - Install new water service
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Friday, 31/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
P2;51;52;LMDC HS 5A;LMDC HS 5B;LMDC HS 6B;SS HS 8A;SS HS 8B
|
Cycle Access:
|
Dismount past works
|
CASTEL - RUE DU FRIQUET
|
|
Description:
|
Work starting 07:00 AM on Wed 22 Jan 25 and finishing 05:00 PM on Mon 10 Feb 25 - INSTALL NEW SEWER and SERVICES
|
Start date:
|
Wednesday, 22/01/25
|
End date:
|
Monday, 10/02/25
|
Timing:
All Day
|
Promoter:
|
Geomarine
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
P2;51;52;LMDC HS 5A;LMDC HS 5B;LMDC HS 6B;SS HS 8A;SS HS 8B
|
Cycle Access:
|
Dismount past works
|
CASTEL - RUE DU FRIQUET; LES BAISSIERES to ROUTE DE COBO
|
( LES BAISSIERES to ROUTE DE COBO )
|
Description:
|
Install telecoms connection to new site (to coincide with existing closure)
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Monday, 03/02/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
P2;51;52;LMDC HS 5A;LMDC HS 5B;LMDC HS 6B;SS HS 8A;SS HS 8B
|
Cycle Access:
|
Dismount past works
|
ST. ANDREW - LES MAUXMARQUIS (ROUTE DE ST. ANDRE)
|
( ROUTE DE LA CROIX AU BAILIFF to ROUTE DE ST. ANDRE )
|
Description:
|
Tree surgery works.
|
Start date:
|
Tuesday, 28/01/25
|
End date:
|
Wednesday, 29/01/25
|
Timing:
All Day
|
Promoter:
|
Spruce Up
|
Contractor:
|
Spruce Up
|
Bus Routes Affected:
|
71;N4;St Martin PS 1A;St Martin PS 1B;LB HS 6A;LB HS 6B;LV HS 5A;LV HS 6B;LV HS LB HS 5A;LV HS LB HS 5B
|
Cycle Access:
|
Dismount past works
|
ST. MARTIN - LES TRAUDES
|
( LES BLANCHES PIERRES to LES HUBITS )
|
Description:
|
Work starting 08:00 AM and finishing 04:00 PM - Tree surgery works.
|
Start date:
|
Friday, 24/01/25
|
End date:
|
Friday, 24/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Guernsey Tree Service Ltd
|
Contractor:
|
Guernsey Tree Service Ltd
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. MARTIN - RUE DES MARETTES
|
( LONG TRAC to RUE DES CROUTES )
|
Description:
|
Chamber and duct installation
|
Start date:
|
Wednesday, 22/01/25
|
End date:
|
Sunday, 26/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. MARTIN - SAINTS ROAD
|
( RUE DES GRONS to ICART ROAD )
|
Description:
|
supply line upgrade
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Thursday, 30/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
LBHS 4A;LV HS 4A;LV HS 4B;LV HS 9B
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - HAUTEVILLE
|
( PEDVIN STREET to HAVELET )
|
Description:
|
Work starting 08:00 AM on Mon 27 Jan 25 and finishing 05:00 PM on Tue 28 Jan 25 - Excavation to enable cable installation
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Tuesday, 28/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - LE MARCHANT STREET
|
( to RUE DU MANOIR )
|
Description:
|
Work starting 08:00 AM on Mon 27 Jan 25 and finishing 05:00 PM on Mon 03 Feb 25 - Chamber and duct installations
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Monday, 03/02/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - LE POLLET
|
|
Description:
|
SCAFFOLDING CAFE EMILIA NOTHING CAN PASS INCLUDING PEDESTRIANS.; Property: CAFE EMILIA; Purpose: External Decoration
|
Start date:
|
Sunday, 26/01/25
|
End date:
|
Sunday, 27/04/25
|
Timing:
All Day
|
Promoter:
|
Impact Scaffolding
|
Contractor:
|
Impact Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
ST. PETER PORT - LES VAUXLAURENS
|
( CAMBRIDGE PARK ROAD to )
|
Description:
|
Work starting 08:00 AM on Mon 27 Jan 25 and finishing 05:00 PM on Fri 31 Jan 25 - Chamber and duct installation
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Friday, 31/01/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - MILL STREET
|
( MANSELL STREET to PETIT CARRE FOUR )
|
Description:
|
Crane Lift.
|
Start date:
|
Sunday, 26/01/25
|
End date:
|
Sunday, 26/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
J W Rihoy Builders
|
Contractor:
|
J W Rihoy Builders
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. PETER PORT - MOUNT DURAND
|
( PRINCE ALBERT ROAD to VALNORD ROAD )
|
Description:
|
Crane lift.
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Monday, 27/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Impact Scaffolding
|
Contractor:
|
Impact Scaffolding
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - THE STRAND
|
( CLIFF STREET to HAVELET )
|
Description:
|
Household removal.
|
Start date:
|
Tuesday, 28/01/25
|
End date:
|
Wednesday, 29/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
White and Company
|
Contractor:
|
White and Company
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - UNION STREET
|
( ALLEZ STREET to ST. JOHN STREET )
|
Description:
|
Crane lift
|
Start date:
|
Sunday, 26/01/25
|
End date:
|
Sunday, 26/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Bob Froome and Sons
|
Contractor:
|
Bob Froome and Sons
|
Bus Routes Affected:
|
|
Cycle Access:
|
No:
|
ST. SAMPSON - DELANCEY LANE; LES BAS COURTILS ROAD to CAMP CODE LANE
|
( LES BAS COURTILS ROAD to CAMP CODE LANE )
|
Description:
|
Repair water leak
|
Start date:
|
Wednesday, 22/01/25
|
End date:
|
Friday, 24/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
Vale PS 2B;Vale PS 3B;LV HS 1A;LV HS 1B;LV HS 2B;SS HS 2A;SS HS 2B;SS HS 3A;SS HS 3B;SS HS 7B
|
Cycle Access:
|
Dismount past works
|
TORTEVAL - RUE DE L`AITTE
|
( RUE COLLAS SIMON to )
|
Description:
|
supply line upgrade
|
Start date:
|
Thursday, 23/01/25
|
End date:
|
Monday, 27/01/25
|
Timing:
All Day
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
ST. PETER PORT - CANDIE ROAD; BROCK ROAD to CAMBRIDGE PARK ROAD
|
( BROCK ROAD to CAMBRIDGE PARK ROAD )
|
Description:
|
Chamber and duct installations
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Friday, 07/02/25
|
Timing:
All Day
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. SAMPSON - LE GRAND FORT ROAD; LES PETITES CAPELLES ROAD to ROUTE CARRE
|
( LES PETITES CAPELLES ROAD to ROUTE CARRE )
|
Description:
|
Concrete pump.
|
Start date:
|
Monday, 27/01/25
|
End date:
|
Monday, 27/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Flint Carver Carpentry
|
Contractor:
|
Flint Carver Carpentry
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
ST. SAMPSON - RUE DES COTTES; PLEINHEAUME ROAD to ROUTE DE LA PASSEE
|
( PLEINHEAUME ROAD to ROUTE DE LA PASSEE )
|
Description:
|
Cable installation and splicing
|
Start date:
|
Thursday, 23/01/25
|
End date:
|
Thursday, 23/01/25
|
Timing:
Between AM and PM Peaks
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Sure Guernsey
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|