Only closures of main traffic routes are listed in this summary.
For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.
|
CASTEL - LES GRANDES ROCQUES
|
|
|
Description:
|
Supply line alteration
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Wednesday, 21/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
LMDC 7B; SS 8A; SS 8B; N2
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - RUETTE DE LA GENEROTTE
|
( ROUTE DE COBO to RUETTE DE FRIES )
|
|
Description:
|
Removal and rebuild of granite wall
|
|
Start date:
|
Monday, 05/01/26
|
End date:
|
Monday, 23/02/26
|
Timing:
All Day
|
|
Promoter:
|
Adie Exall Stonemason
|
Contractor:
|
Adie Exall Stonemason
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
CASTEL - RUETTE DE TOUILLETS
|
( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
|
|
Description:
|
Work starting 08:00 AM on Sat 19 Aug 23 and finishing 11:59 PM on Thu 30 Apr 26 - Investigation and repairs to roadside wall
|
|
Start date:
|
Saturday, 19/08/23
|
End date:
|
Thursday, 30/04/26
|
Timing:
All Day
|
|
Promoter:
|
Private Individual
|
Contractor:
|
Private Individual
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
Emergency Activity - CASTEL - ROUTE DE COBO
|
|
|
Description:
|
Work starting 08:00 AM on Fri 09 Jan 26 and finishing 05:00 PM on Thu 22 Jan 26 - fallen tree
|
|
Start date:
|
Friday, 09/01/26
|
End date:
|
Thursday, 22/01/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Roadworks Coordination)
|
Contractor:
|
|
|
Bus Routes Affected:
|
Castel 3B; LMDC 6B / LV 6B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; 41
|
Cycle Access:
|
No
|
|
Emergency Activity - CASTEL - ROUTE DE COBO
|
|
|
Description:
|
Work starting 05:45 AM on Fri 09 Jan 26 and finishing 06:00 PM on Fri 13 Feb 26 - Back entrance of park - tree down - road blocked
|
|
Start date:
|
Friday, 09/01/26
|
End date:
|
Friday, 13/02/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Roadworks Coordination)
|
Contractor:
|
|
|
Bus Routes Affected:
|
Castel 3B; LMDC 6B / LV 6B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; 41
|
Cycle Access:
|
No
|
|
ST. ANDREW - LA VASSALERIE
|
( ROUTE DE ST. ANDRE to MOURANTS ROAD )
|
|
Description:
|
Driveway works to Sleepy Hollow Bungalow
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Thursday, 22/01/26
|
Timing:
All Day
|
|
Promoter:
|
Tarmac Services
|
Contractor:
|
Tarmac Services
|
|
Bus Routes Affected:
|
Forest 2B; St Martin 1A
|
Cycle Access:
|
Yes
|
|
ST. ANDREW - ROHAIS DE BAS
|
|
|
Description:
|
reinstating failed tarmac
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Wednesday, 21/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
Castel 1A; Castel 1B; LB 1B; LMDC 6A / LV 6A; LMDC 6B / LV 6B; LMDC 7A; LMDC 7B; LV 3B; LV 4A; LV 4B; P2;41;42;N2
|
Cycle Access:
|
Dismount past works
|
|
ST. ANDREW - ROHAIS DE BAS
|
|
|
Description:
|
resurfacing due to failed works
|
|
Start date:
|
Saturday, 17/01/26
|
End date:
|
Wednesday, 21/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
Castel 1A; Castel 1B; LB 1B; LMDC 6A / LV 6A; LMDC 6B / LV 6B; LMDC 7A; LMDC 7B; LV 3B; LV 4A; LV 4B; P2;41;42;N2
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - BERTHELOT STREET
|
|
|
Description:
|
Work starting 07:30 AM on Mon 17 Mar 25 and finishing 04:00 PM on Thu 30 Apr 26 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
|
|
Start date:
|
Monday, 17/03/25
|
End date:
|
Thursday, 30/04/26
|
Timing:
All Day
|
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - BRUCE LANE
|
|
|
Description:
|
Work starting 07:00 AM and finishing 05:00 PM daily between Tue 28 Oct 25 and Sat 31 Jan 26 - Scaffolding; Property: Stratton House; Purpose: Roofing Works
|
|
Start date:
|
Tuesday, 28/10/25
|
End date:
|
Saturday, 31/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Impact Scaffolding
|
Contractor:
|
Impact Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. PETER PORT - BRUCE LANE
|
|
|
Description:
|
Scaffolding; Property: No 4 Bruce Lane; Purpose: External Decoration
|
|
Start date:
|
Monday, 13/10/25
|
End date:
|
Friday, 13/02/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Island Scaffolding
|
Contractor:
|
Island Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. PETER PORT - COLBORNE ROAD
|
( RUETTES BRAYES to HAVILLAND ROAD )
|
|
Description:
|
Tree surgery
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Wednesday, 21/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Treevolution
|
Contractor:
|
Treevolution
|
|
Bus Routes Affected:
|
LB 3A; LB 3B; LMDC 7A; LMDC 7B; LV 4A; 91;92;93;94;95;N3
|
Cycle Access:
|
No
|
|
ST. PETER PORT - CROUTES HAVILLAND
|
( FORT ROAD to DAMOUETTES LANE )
|
|
Description:
|
Skips outside No 2
|
|
Start date:
|
Thursday, 01/01/26
|
End date:
|
Sunday, 15/02/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
C M Building
|
Contractor:
|
C M Building
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. PETER PORT - LE POLLET
|
|
|
Description:
|
Work starting 07:30 AM on Mon 19 Jan 26 and finishing 04:00 PM on Wed 28 Jan 26 - Road resurfacing
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Wednesday, 28/01/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
St Martin PS 3A;St Martin PS 3B;LBHS 2A""LMDC HS 7B;LV HS 6B
|
Cycle Access:
|
No
|
|
ST. PETER PORT - LES PETITES FONTAINES
|
( MOUNT HERMON to VALNORD ROAD )
|
|
Description:
|
wall repairs
|
|
Start date:
|
Sunday, 21/12/25
|
End date:
|
Friday, 27/02/26
|
Timing:
All Day
|
|
Promoter:
|
TNT Stonemasons
|
Contractor:
|
TNT Stonemasons
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - MILL STREET
|
|
|
Description:
|
Work starting 08:00 AM on Fri 02 Jan 26 and finishing 05:00 PM on Fri 27 Feb 26 - Relay 3` iron/asbestos main
|
|
Start date:
|
Friday, 02/01/26
|
End date:
|
Friday, 27/02/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Vauvert PS 1A
|
Cycle Access:
|
No
|
|
ST. PETER PORT - RUE DE BELVEDERE
|
|
|
Description:
|
Work starting 08:00 AM and finishing 04:00 PM daily between Mon 19 Jan 26 and Fri 23 Jan 26 - Tree surgery
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Friday, 23/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Arbology
|
Contractor:
|
Arbology
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. PETER PORT - ST. STEPHEN`S LANE
|
( YORK AVENUE to LES CROUTES )
|
|
Description:
|
Work starting 07:00 AM and finishing 05:00 PM daily between Mon 05 Jan 26 and Fri 23 Jan 26 - Removing road side wall and rebuilding gateway
|
|
Start date:
|
Monday, 05/01/26
|
End date:
|
Friday, 23/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Paul Bonnel Stonemasons
|
Contractor:
|
Paul Bonnel Stonemasons
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - VALNORD LANE
|
( VALNORD ESTATE to GREEN LANES )
|
|
Description:
|
Work starting 08:00 AM and finishing 05:00 PM daily between Mon 23 Jun 25 and Sat 28 Feb 26 - Delivery of building materials.
|
|
Start date:
|
Monday, 23/06/25
|
End date:
|
Saturday, 28/02/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Hillstone Guernsey Ltd
|
Contractor:
|
Hillstone Guernsey Ltd
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes, in direction of one-way
|
|
ST. PIERRE DU BOIS - ROUTE DE LIHOU
|
( RUE DU LONGFRIE to RUE DES GRANDES RUES )
|
|
Description:
|
Tree surgery
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Thursday, 22/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Guernsey Tree Service Ltd
|
Contractor:
|
Guernsey Tree Service Ltd
|
|
Bus Routes Affected:
|
Houguette 1A
|
Cycle Access:
|
No
|
|
ST. PIERRE DU BOIS - RUE DES CACHES
|
( RUE DES BREHAUTS to RUE DES RONDIAUX )
|
|
Description:
|
Lane blocked by two trees from Storm Goretti. Trees being removed during week ending Friday 23 JAN
|
|
Start date:
|
Thursday, 08/01/26
|
End date:
|
Friday, 23/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Tree Service Ltd
|
Contractor:
|
Guernsey Tree Service Ltd
|
|
Bus Routes Affected:
|
LB HS 9B;LMDC HS 1A 2A;LMDC HS 1B 2B;LMDC HS 4A;LMDC HS 4B;LV HS 6B;LMDC HS LB HS 1A;LMDC HS LB HS 1B
|
Cycle Access:
|
No
|
|
ST. SAMPSON - LES SAUVAGEES
|
( OATLANDS LANE to DUVEAUX LANE )
|
|
Description:
|
service alteration
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Tuesday, 20/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. SAVIOUR - ROUTE DES BAS COURTILS
|
|
|
Description:
|
Work starting 07:30 AM on Mon 19 Jan 26 and finishing 04:00 PM on Fri 06 Feb 26 - Road resurfacing
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Friday, 06/02/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
Houguette 2A; Houguette 2B; LMDC 3A / LB 8A; LMDC 3B / LB 8B; LV 5A / LB 6A; LV 5B / LB 6B; 71;N4
|
Cycle Access:
|
Dismount past works
|
|
ST. SAVIOUR - RUE DE L`EGLISE
|
( ROUTE DE SOUS L'EGLISE to RUE DES COMTES )
|
|
Description:
|
GW Assistance ( Abreuveurs Repair )
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Friday, 23/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Guernsey Water (Wastewater)
|
|
Bus Routes Affected:
|
LBHS 5A;LBHS 5B;LMDC HS 3A;LMDC HS 3B;LV HS 5A;LV HS 5B;LMDC HS LB HS 3A;LMDC HS LB HS 3B;LV HS LB HS 5A;LV HS LB HS 5B
|
Cycle Access:
|
No
|
|
ST. SAVIOUR - RUE PERELLE
|
|
|
Description:
|
Asphalt rectification
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Tuesday, 20/01/26
|
Timing:
All Day
|
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Houguette 1B; Houguette 3B; LB 5A; LB 5B; LMDC 4A; LMDC 4B; LV 3B; LV 8A; LMDC 3A / LB 8A; LMDC 3B / LB 8B; 60;61
|
Cycle Access:
|
Dismount past works
|
|
ST. SAVIOUR - RUE PERELLE
|
|
|
Description:
|
Work starting 08:30 AM on Mon 19 Jan 26 and finishing 05:00 PM on Wed 21 Jan 26 - Install new water service
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Wednesday, 21/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Houguette 1B; Houguette 3B; LB 5A; LB 5B; LMDC 4A; LMDC 4B; LV 3B; LV 8A; LMDC 3A / LB 8A; LMDC 3B / LB 8B; 60;61
|
Cycle Access:
|
Dismount past works
|
|
VALE - L'ABBAYE
|
|
|
Description:
|
Work starting 07:00 AM on Mon 19 Jan 26 and finishing 12:00 PM on Tue 20 Jan 26 - Removal of granite wall; Property: Vale Church; Purpose: Other (see Details)
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Tuesday, 20/01/26
|
Timing:
All Day
|
|
Promoter:
|
Impact Scaffolding
|
Contractor:
|
Impact Scaffolding
|
|
Bus Routes Affected:
|
LV 1B; 13;91;92;N1
|
Cycle Access:
|
No
|
|
VALE - LONGREE
|
( NORTH SIDE to )
|
|
Description:
|
New service installation
|
|
Start date:
|
Monday, 19/01/26
|
End date:
|
Wednesday, 21/01/26
|
Timing:
All Day
|
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Vale PS 2A;Vale PS 2B;LV HS 1A;LV HS 1B;LV HS 2B;SS HS 2B
|
Cycle Access:
|
Dismount past works
|
No current major delays due to one ways
|
ST. PETER PORT - SOUTH ESPLANADE
|
|
|
Description:
|
Work starting 09:00 AM on Mon 12 Jan 26 and finishing 05:00 PM on Mon 26 Jan 26 - Essential maintenance upgrade to gas services.
|
|
Start date:
|
Monday, 12/01/26
|
End date:
|
Monday, 26/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Gas
|
Contractor:
|
Guernsey Gas
|
|
Bus Routes Affected:
|
St Martin 3A; St Martin 3B; LB 2A; LMDC 7B
|
Cycle Access:
|
Dismount past works
|
|
ST. ANDREW - LES MAUXMARQUIS (ROUTE DE ST. ANDRE)
|
|
|
Description:
|
Supply line upgrade
|
|
Start date:
|
Wednesday, 21/01/26
|
End date:
|
Friday, 23/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
St Martin 1A; St Martin 1B; LV 5A / LB 6A; LV 5B / LB 6B; 71;N4
|
Cycle Access:
|
Dismount past works
|
|
ST. ANDREW - ROUTE DE LA CROIX AU BAILIFF
|
|
|
Description:
|
Trial Hole Excavations
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Friday, 30/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Guernsey Electricity
|
|
Bus Routes Affected:
|
St Martin 1A; St Martin 1B; LB 1A; LB 1B; LB 2A; LB 2B; LB 3A; LB 3B; LV 4B; LV 5A / LB 6A; LV 5B / LB 6B; P2;51;52;60;61
|
Cycle Access:
|
Dismount past works
|
|
ST. MARTIN - RUE DE L`EGLISE
|
( LA BELLIEUSE to LES MERRIENNES )
|
|
Description:
|
Work starting 07:00 AM and finishing 06:00 PM daily between Mon 26 Jan 26 and Fri 30 Jan 26 - Tree surgery
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Friday, 30/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Treemendous
|
Contractor:
|
Treemendous
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. PETER PORT - GUELLES LANE
|
( MONT ARRIVE to GUELLES ROAD )
|
|
Description:
|
CCTV Investigation
|
|
Start date:
|
Sunday, 25/01/26
|
End date:
|
Sunday, 25/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Guernsey Water (Wastewater)
|
|
Bus Routes Affected:
|
LV HS 7B
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LE VAL DES TERRES
|
|
|
Description:
|
Work starting 09:30 AM and finishing 04:30 PM daily between Mon 26 Jan 26 and Fri 30 Jan 26 - Repair to rockfall netting
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Friday, 30/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
States Property Unit
|
Contractor:
|
Traffic and Highway Services (Parking Suspensions and Events)
|
|
Bus Routes Affected:
|
St Martin 3A; St Martin 3B; LB 2A; LMDC 7B
|
Cycle Access:
|
No
|
|
ST. PETER PORT - LE VAL DES TERRES
|
|
|
Description:
|
Work starting 07:30 AM on Mon 26 Jan 26 and finishing 05:00 PM on Fri 30 Jan 26 - Streetlight Replacement
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Friday, 30/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
St Martin 3A; St Martin 3B; LB 2A; LMDC 7B
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - LES COTILS
|
|
|
Description:
|
Work starting 07:30 AM on Mon 26 Jan 26 and finishing 05:00 PM on Mon 02 Feb 26 - supply line alteration
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Monday, 02/02/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - MONT ARRIVE
|
|
|
Description:
|
Sewer Repair ( O/S Old Spa Del La Mare Site )
|
|
Start date:
|
Saturday, 24/01/26
|
End date:
|
Saturday, 24/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Guernsey Water (Wastewater)
|
|
Bus Routes Affected:
|
Amherst 1A; 32
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - PARIS STREET
|
( NEW PARIS ROAD to ST. GEORGE'S ESPLANADE )
|
|
Description:
|
House move
|
|
Start date:
|
Tuesday, 20/01/26
|
End date:
|
Tuesday, 20/01/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Safemoves Removals
|
Contractor:
|
Safemoves Removals
|
|
Bus Routes Affected:
|
St Martin PS 3A;St Martin PS 3B;LBHS 2A""LMDC HS 7B;LV HS 6B
|
Cycle Access:
|
No
|
|
ST. SAMPSON - MONT MORIN
|
( RUE DES MONTS to RODLEY PARK )
|
|
Description:
|
Supply line alteration
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Wednesday, 28/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
TORTEVAL - RUE DU SAUCHET
|
( RUE DU BELLE to RUE DES ROCQUES )
|
|
Description:
|
Supply line upgrade
|
|
Start date:
|
Tuesday, 20/01/26
|
End date:
|
Thursday, 22/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
VALE - LANDES DU MARCHE
|
|
|
Description:
|
Repair manhole cover
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Thursday, 29/01/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
LMDC 7A; LMDC 7B; LV 1A; LV 1B; LV 2B; LV 8A; SS 1B; SS 4A; SS 4B; P2
|
Cycle Access:
|
Dismount past works
|
|
VALE - LANDES DU MARCHE
|
|
|
Description:
|
Repair various failed tarmac areas
|
|
Start date:
|
Monday, 26/01/26
|
End date:
|
Thursday, 29/01/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Highways Inspector)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
LMDC 7A; LMDC 7B; LV 1A; LV 1B; LV 2B; LV 8A; SS 1B; SS 4A; SS 4B; P2
|
Cycle Access:
|
No
|
No future major delays due to one ways
No future major delays due to signals