Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - LA GIFFARDIERE ( RETOT to RUE D'ALBECQ )
Description: Mains replacement program to enhance the safety, reliability, and efficiency of the gas network.
Start date: Tuesday, 08/04/25 End date: Monday, 28/04/25 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Castel 3B; 42;N2 Cycle Access: Dismount past works

CASTEL - RUE DU FRIE PLAIDY
Description: Scaffolding; Property: Le Frie Plaidy; Purpose: Other (see Details)
Start date: Saturday, 15/03/25 End date: Saturday, 10/05/25 Timing: Between AM and PM Peaks
Promoter: Island Scaffolding Contractor: Island Scaffolding
Bus Routes Affected: Cycle Access: Yes

CASTEL - RUE DU PRESBYTERE
Description: Work starting 08:30 AM on Mon 03 Mar 25 and finishing 05:00 PM on Mon 02 Jun 25 - Install new water transfer pipework
Start date: Monday, 03/03/25 End date: Monday, 02/06/25 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Castel 1A; St Martin 1B; 51;52 Cycle Access: Dismount past works

CASTEL - RUETTE DE TOUILLETS ( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
Description: Work starting 08:00 AM on Sat 19 Aug 23 and finishing 11:59 PM on Wed 30 Apr 25 - Investigation and repairs to roadside wall
Start date: Saturday, 19/08/23 End date: Wednesday, 30/04/25 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

Emergency Activity - CASTEL - ROUTE DE LA HOUGUE DU POMMIER
Description: Work starting 07:18 PM on Tue 15 Apr 25 and finishing 05:00 PM on Wed 23 Apr 25 - Emergency Works - LV Fault
Start date: Tuesday, 15/04/25 End date: Wednesday, 23/04/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: LMDC 6A / LV 6A; SS 8A; SS 8B; 41;N2 Cycle Access: Yes

ST. PETER PORT - BACK STREET ( MANSELL STREET to VAUVERT )
Description: Work starting 08:00 AM and finishing 04:00 PM daily between Mon 14 Apr 25 and Fri 25 Apr 25 - Cable splicing
Start date: Monday, 14/04/25 End date: Friday, 25/04/25 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BERTHELOT STREET
Description: Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
Start date: Monday, 17/03/25 End date: Monday, 04/05/26 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BURNT LANE
Description: Chamber and duct installations
Start date: Monday, 14/04/25 End date: Friday, 25/04/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - HIGH STREET ( LEFEBVRE STREET to BERTHELOT STREET )
Description: Work starting 10:00 AM and finishing 06:00 PM daily between Mon 10 Mar 25 and Wed 30 Apr 25 - Stripping scaffolding.
Start date: Monday, 10/03/25 End date: Wednesday, 30/04/25 Timing: Between AM and PM Peaks
Promoter: Formula Scaffolding Contractor: Formula Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LES PETITES FONTAINES ( MOUNT HERMON to VALNORD ROAD )
Description: Work starting 11:30 AM on Fri 22 Nov 24 and finishing 05:00 PM on Wed 30 Apr 25 - wall repairs
Start date: Friday, 22/11/24 End date: Wednesday, 30/04/25 Timing: All Day
Promoter: TNT Stonemasons Contractor: TNT Stonemasons
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LES VAUXLAURENS
Description: Work starting 07:30 AM and finishing 05:00 PM daily between Fri 29 Nov 24 and Fri 30 May 25 - Scaffold to access for emergency works from storm damage; Property: Apartments 4 and 29 St Julians Avenue; Purpose: Roofing Works
Start date: Friday, 29/11/24 End date: Friday, 30/05/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LOWER CANICHERS ( LE TRUCHOT to DOYLE STREET )
Description: Work starting 08:00 AM on Mon 30 Sep 24 and finishing 07:00 AM on Mon 28 Apr 25 - building repair and refit
Start date: Monday, 30/09/24 End date: Monday, 28/04/25 Timing: All Day
Promoter: Ravenscroft Construction Ltd Contractor: Ravenscroft Construction Ltd
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - PORT VASE ( BURNT LANE to )
Description: Work starting 07:30 AM on Mon 14 Apr 25 and finishing 05:00 PM on Tue 22 Apr 25 - Supply line upgrade
Start date: Monday, 14/04/25 End date: Tuesday, 22/04/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - ROUTE DE LIHOU ( RUE DU LONGFRIE to RUE DES GRANDES RUES )
Description: Work starting 09:00 AM on Thu 29 Aug 24 and finishing 11:59 PM on Sat 31 May 25 - Road blocked due to collapsed granite wall approx 10m from the Route de Lihou and Rue du Longfrie junction, near property Longfrie House.
Start date: Thursday, 29/08/24 End date: Saturday, 31/05/25 Timing: All Day
Promoter: Traffic and Highways Contractor: Traffic and Highways
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DE LA POMARE ( RUE DES SALINES to RUE DE LA CACHE )
Description: Repairs to roadside wall.
Start date: Wednesday, 16/04/25 End date: Sunday, 27/04/25 Timing: All Day
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: Cycle Access: Yes

ST. SAVIOUR - VIEILLE RUE ( RUE DES CINQ VERGES to RUE DE LA GIROUETTE )
Description: Work starting 07:00 AM and finishing 05:00 PM daily between Mon 03 Feb 25 and Thu 01 May 25 - Rebuilding roadside wall.
Start date: Monday, 03/02/25 End date: Thursday, 01/05/25 Timing: Between AM and PM Peaks
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

VALE - Guernsey Velo Club - Cycling race
Description: Easter Festival
Start date: Friday, 18/04/25 End date: Friday, 18/04/25 Timing: All Day
Promoter: Guernsey Velo Club LBG Contractor: N/A
Bus Routes Affected: Cycle Access: No

VALE - ROUTE DE ST MAGLOIRE
Description: Work starting 07:30 AM on Wed 16 Apr 25 and finishing 05:00 PM on Wed 30 Apr 25 - Replacing electricity cable in La Ruette de S. Magloire and La Rue De Paradis Vale
Start date: Wednesday, 16/04/25 End date: Wednesday, 30/04/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

VALE - ROUTE DES COUTURES
Description: Work starting 07:30 AM on Mon 14 Apr 25 and finishing 04:00 PM on Fri 25 Apr 25 - Road resurfacing
Start date: Monday, 14/04/25 End date: Friday, 25/04/25 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Vale 1A; Vale 2A; P2;13 Cycle Access: Dismount past works

One Ways
ST. PETER PORT - LE BOUET
Description: Work starting 08:00 AM and finishing 04:00 PM daily between Wed 16 Oct 24 and Sun 04 May 25 - Scaffolding.; Property: No 10, Le Bouet; Purpose: Demolition / New Build
Start date: Wednesday, 16/10/24 End date: Sunday, 04/05/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

Signals
CASTEL - RUE D`ALBECQ ( SOUS LES COURTILS to LA NEUVE RUE )
Description: Mains replacement program to enhance the safety, reliability, and efficiency of the gas network.
Start date: Tuesday, 08/04/25 End date: Monday, 12/05/25 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Castel 3B; LMDC 4A; LMDC 4B; LV 3B; LV 8A; LMDC 3B / LB 8B; 42;91;92;N2 Cycle Access: Yes

ST. PETER PORT - LE BORDAGE
Description: Phase 2 of St Peter's House; Property: St Peter`s House; Purpose: Roofing Works
Start date: Saturday, 05/04/25 End date: Monday, 30/06/25 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - RUE SAUVAGE; LA ROUTE DES CAPELLES to LES BASSES CAPELLES ROAD ( LA ROUTE DES CAPELLES to LES BASSES CAPELLES ROAD )
Description: Rebuilding roadside wall.
Start date: Monday, 14/04/25 End date: Monday, 28/04/25 Timing: All Day
Promoter: Paul Bonnel Stonemasons Contractor: Paul Bonnel Stonemasons
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
FOREST - LA RUE DU MONT MARCHE ( to LE MONT MARCHE ESTATE )
Description: Chamber installation
Start date: Tuesday, 22/04/25 End date: Thursday, 24/04/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

FOREST - LES NICOLLES ( FST-MISC28 to LES REBOUQUETS )
Description: Work starting 08:00 AM and finishing 04:00 PM daily between Thu 24 Apr 25 and Fri 25 Apr 25 - CBT install and cable splicing 8am - 4pm daily
Start date: Thursday, 24/04/25 End date: Friday, 25/04/25 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LES MOUILPIEDS
Description: Work starting 08:00 AM and finishing 04:00 PM - CBT installations
Start date: Wednesday, 23/04/25 End date: Wednesday, 23/04/25 Timing: Before AM Peak
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: St Martin PS 1A;St Martin PS 1B;LBHS 4A;LB HS 4A Overflow;LBHS 5A;LBHS 5B;LB HS 9B;LMDC HS 4A;LV HS 6B Cycle Access: Yes

ST. MARTIN - LES MOUILPIEDS ( CHEMIN LE ROI to LA RUETTE DE LA POMPE )
Description: Jetting culvert
Start date: Thursday, 24/04/25 End date: Thursday, 24/04/25 Timing: Between AM and PM Peaks
Promoter: The Drain Squad Contractor: The Drain Squad
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - GMCCC Val Des Terres HILLCLIMB
Description: GMCCC Val Des Terres HILLCLIMB
Start date: Monday, 21/04/25 End date: Monday, 21/04/25 Timing: All Day
Promoter: GMCCC Guernsey Motorcycle and Car Club LBG Contractor: N/A
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 2A; LMDC 7B Cycle Access: No

ST. PETER PORT - IVY CASTLE LANE
Description: Scaffolding.; Property: Apartment 1, Meadowview; Purpose: Roofing Works
Start date: Thursday, 24/04/25 End date: Saturday, 10/05/25 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - QUEENS ROAD
Description: Replace failing chamber cover
Start date: Tuesday, 22/04/25 End date: Thursday, 24/04/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Vauvert 1B; LMDC 7A; 60;61;71;81;N4 Cycle Access: Dismount past works

ST. PETER PORT - ROUTE DE LA RAMEE ( LA HAMEAU to LA ROUTE DES LONGS CAMPS )
Description: Tree works
Start date: Tuesday, 22/04/25 End date: Tuesday, 22/04/25 Timing: Between AM and PM Peaks
Promoter: Dave Brouard Limited Contractor: Dave Brouard Limited
Bus Routes Affected: 31;32 Cycle Access: No

ST. PETER PORT - ROUTE DE LA RAMEE
Description: New supply line
Start date: Tuesday, 22/04/25 End date: Thursday, 24/04/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 31;32 Cycle Access: Dismount past works

ST. PETER PORT - UPPER ST. JACQUES
Description: CCTV Camera clean
Start date: Tuesday, 22/04/25 End date: Tuesday, 22/04/25 Timing: Before AM Peak
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - VAUVERT ( LA COUPERDERIE to ALLEZ STREET )
Description: Work starting 07:30 AM and finishing 05:00 PM daily between Wed 23 Apr 25 and Fri 25 Apr 25 - Erecting scaffolding.
Start date: Wednesday, 23/04/25 End date: Friday, 25/04/25 Timing: Between AM and PM Peaks
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Vauvert 1A; Vauvert 1B Cycle Access: Dismount past works

ST. SAMPSON - Guernsey Football Association - Victoria Park Stadium
Description: Guernsey Football Association - Victoria Park Stadium
Start date: Monday, 21/04/25 End date: Monday, 21/04/25 Timing: Between AM and PM Peaks
Promoter: Guernsey Football Association Contractor: N/A
Bus Routes Affected: Vale 2A Cycle Access: Yes

TORTEVAL - Guernsey Velo Club - Hill Climb
Description: Easter Festival
Start date: Saturday, 19/04/25 End date: Saturday, 19/04/25 Timing: All Day
Promoter: Guernsey Velo Club LBG Contractor: N/A
Bus Routes Affected: Houguette PS 1A;LB HS 6A;LB HS 6B;LMDC HS 1A 2A;LMDC HS 1B 2B;LV HS 5A;LV HS 5B;LMDC HS LB HS 1A;LMDC HS LB HS 1B;LV HS LB HS 5A;LV HS LB HS 5B Cycle Access: No

VALE - Easter Festival Road Race ( LONGREE to TRAFALGAR ROAD )
Description: Easter Festival Road Race
Start date: Monday, 21/04/25 End date: Monday, 21/04/25 Timing: Between AM and PM Peaks
Promoter: Guernsey Athletics Club Contractor: N/A
Bus Routes Affected: 13;N1 Cycle Access: Dismount past works

One Ways
ST. PETER PORT - Funeral at Notre Dame Church ( NEW PLACE to GEORGE STREET )
Description: Funeral
Start date: Thursday, 24/04/25 End date: Thursday, 24/04/25 Timing: Between AM and PM Peaks
Promoter: Argent Funeral Care Contractor: N/A
Bus Routes Affected: Vauvert 1B Cycle Access: Yes, in direction of one-way

VALE - Easter Festival Cross Country Race
Description: Easter Festival Cross Country Race
Start date: Saturday, 19/04/25 End date: Saturday, 19/04/25 Timing: Between AM and PM Peaks
Promoter: Guernsey Athletics Club Contractor: N/A
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

VALE - Easter Festival Les Amarreurs Cross Country Run OW ( Cotes de Amarreurs to L'Ancresse Road )
Description: Easter Festival Les Amarreurs Cross Country Run OW
Start date: Saturday, 19/04/25 End date: Saturday, 19/04/25 Timing: Between AM and PM Peaks
Promoter: Guernsey Athletics Club Contractor: N/A
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

Signals
CASTEL - COBO COAST ROAD; ROUTE DE COBO to ROUTE DE CARTERET ( ROUTE DE COBO to ROUTE DE CARTERET )
Description: Supply line alteration
Start date: Wednesday, 23/04/25 End date: Friday, 25/04/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - QUEENS ROAD; BELMONT ROAD to MOUNT ROW ( BELMONT ROAD to MOUNT ROW )
Description: Repair damaged duct
Start date: Tuesday, 22/04/25 End date: Thursday, 24/04/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes