Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - RUE DE LA HOUGUE ( to RUE AU FERRE )
Description: Work starting 12:00 PM on Mon 23 Feb 26 and finishing 04:00 PM on Fri 20 Mar 26 - Rebuilding roadside wall
Start date: Monday, 23/02/26 End date: Friday, 20/03/26 Timing: All Day
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: Houguette PS 1B;Houguette PS 3B;LBHS 5A;LBHS 5B;LMDC HS 1A 2A;LMDC HS 1B 2B;LMDC HS 4A;LMDC HS 4B;LV HS 3B;LV HS 8A Cycle Access: Yes

CASTEL - RUE DES HOUGUES; RUETTE DU HAUT SEJOUR to SSAV-MISC13 ( RUETTE DU HAUT SEJOUR to SSAV-MISC13 )
Description: Work starting 08:30 AM on Thu 12 Mar 26 and finishing 07:30 AM on Sat 14 Mar 26 - Repair leaking air valve
Start date: Thursday, 12/03/26 End date: Saturday, 14/03/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

CASTEL - RUETTE DE TOUILLETS ( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
Description: Work starting 08:00 AM on Sat 19 Aug 23 and finishing 11:59 PM on Thu 30 Apr 26 - Investigation and repairs to roadside wall
Start date: Saturday, 19/08/23 End date: Thursday, 30/04/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

FOREST - LES VILLETS ( LA ROBERGE to LA RUE DE LA VRANGUE )
Description: Skips.
Start date: Monday, 26/01/26 End date: Friday, 03/04/26 Timing: All Day
Promoter: R C Ashplant construction Contractor: R C Ashplant construction
Bus Routes Affected: Houguette PS 2B;LMDC HS 3A;LMDC HS 3B;LV HS 5A;LMDC HS LB HS 3A;LMDC HS LB HS 3B;LV HS LB HS 5A;LV HS LB HS 5B Cycle Access: Dismount past works

ST. MARTIN - CALAIS LANE ( ROUTE DE JERBOURG to CALAIS ROAD )
Description: Essential maintenance to gas service.
Start date: Monday, 09/03/26 End date: Monday, 23/03/26 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: No

ST. MARTIN - LE COURTILLET
Description: Work starting 07:30 AM on Mon 09 Mar 26 and finishing 04:00 PM on Fri 20 Mar 26 - Road resurfacing
Start date: Monday, 09/03/26 End date: Friday, 20/03/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - BERTHELOT STREET
Description: Work starting 07:30 AM on Mon 17 Mar 25 and finishing 04:00 PM on Thu 30 Apr 26 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
Start date: Monday, 17/03/25 End date: Thursday, 30/04/26 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BRUCE LANE
Description: Work starting 07:00 AM and finishing 11:59 PM daily between Mon 13 Oct 25 and Tue 31 Mar 26 - Scaffolding; Property: No 4 Bruce Lane; Purpose: External Decoration
Start date: Monday, 13/10/25 End date: Tuesday, 31/03/26 Timing: Between AM and PM Peaks
Promoter: Island Scaffolding Contractor: Island Scaffolding
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - GUELLES LANE ( MONT ARRIVE to GUELLES ROAD )
Description: Work starting 07:30 AM on Mon 02 Mar 26 and finishing 05:00 PM on Thu 09 Apr 26 - High voltage substation connection and low voltage cable overlay
Start date: Monday, 02/03/26 End date: Thursday, 09/04/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: LV HS 7B Cycle Access: Dismount past works

ST. PETER PORT - LES OZOUETS ROAD
Description: Trial trench investigation works
Start date: Tuesday, 10/03/26 End date: Monday, 16/03/26 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: SS 1B; 51;52 Cycle Access: Dismount past works

ST. PETER PORT - LES PETITES FONTAINES ( MOUNT HERMON to VALNORD ROAD )
Description: Work starting 07:00 AM on Sun 21 Dec 25 and finishing 11:59 PM on Thu 30 Apr 26 - wall repairs
Start date: Sunday, 21/12/25 End date: Thursday, 30/04/26 Timing: All Day
Promoter: TNT Stonemasons Contractor: TNT Stonemasons
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LOWER VAUVERT ( TRINITY SQUARE to CONTREE MANSELL )
Description: Work starting 08:30 AM on Wed 11 Mar 26 and finishing 05:00 PM on Mon 16 Mar 26 - Upgrade existing water main
Start date: Wednesday, 11/03/26 End date: Monday, 16/03/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Vauvert 1B Cycle Access: Dismount past works

ST. PETER PORT - MILL STREET
Description: Work starting 08:00 AM on Fri 02 Jan 26 and finishing 05:00 PM on Sun 22 Mar 26 - Relay 3` iron/asbestos main
Start date: Friday, 02/01/26 End date: Sunday, 22/03/26 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Vauvert PS 1A Cycle Access: No

ST. PETER PORT - VALNORD LANE ( VALNORD ESTATE to GREEN LANES )
Description: Work starting 08:00 AM and finishing 05:00 PM daily between Mon 23 Jun 25 and Mon 04 May 26 - Delivery of building materials.
Start date: Monday, 23/06/25 End date: Monday, 04/05/26 Timing: Between AM and PM Peaks
Promoter: Hillstone Guernsey Ltd Contractor: Hillstone Guernsey Ltd
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

One Ways
CASTEL - ROUTE DU TERTRE; RUE DE LA MASSE to LES QUERITES ( RUE DE LA MASSE to LES QUERITES )
Description: Repair and rebuild road side wall
Start date: Monday, 09/03/26 End date: Friday, 12/06/26 Timing: All Day
Promoter: Fixt Ltd Contractor: Fixt Ltd
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

VALE - LA GRANDE MAISON ROAD ( PLEINHEAUME ROAD to LES HAUTS COURTILS ROAD )
Description: Repair to roadside wall
Start date: Tuesday, 03/03/26 End date: Wednesday, 18/03/26 Timing: Between AM and PM Peaks
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: LV 1B; LV 8A; SS 1B Cycle Access: Yes, in direction of one-way

Signals
CASTEL - RUE COHU
Description: Work starting 08:00 AM on Mon 09 Mar 26 and finishing 05:00 PM on Fri 20 Mar 26 - Rebuilding roadside wall.
Start date: Monday, 09/03/26 End date: Friday, 20/03/26 Timing: All Day
Promoter: Keystone Masonry Contractor: Keystone Masonry
Bus Routes Affected: LMDC 6A / LV 6A; LMDC 7A; SS 4A; SS 4B; P2;41;42;N2 Cycle Access: Yes

FOREST - LE BOURG
Description: Investigation
Start date: Wednesday, 25/02/26 End date: Thursday, 26/03/26 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
CASTEL - ROUTE DES TALBOTS ( LES PETITES VALLEES to RUE DU TORVAL )
Description: Tree Surgery
Start date: Friday, 20/03/26 End date: Friday, 20/03/26 Timing: All Day
Promoter: Guernsey Tree Service Ltd Contractor: Guernsey Tree Service Ltd
Bus Routes Affected: LB 4A Cycle Access: Dismount past works

ST. ANDREW - ROHAIS DE HAUT
Description: Work starting 08:00 AM on Tue 17 Mar 26 and finishing 04:00 PM on Fri 17 Apr 26 - Road resurfacing
Start date: Tuesday, 17/03/26 End date: Friday, 17/04/26 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Castel 1A; Castel 1B; St Martin 1A; LB 1B; LV 3B; LV 4B; P2 Cycle Access: Dismount past works

ST. PETER PORT - IVY CASTLE LANE
Description: Drainage Cleaning and CCTV
Start date: Friday, 20/03/26 End date: Friday, 20/03/26 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Amherst PS 1A;SS HS 4A Cycle Access: Dismount past works

ST. PETER PORT - LES COTILS ( LES AMBALLES to BEAUREGARD LANE )
Description: House move
Start date: Wednesday, 18/03/26 End date: Friday, 20/03/26 Timing: Between AM and PM Peaks
Promoter: R and R Removals Contractor: R and R Removals
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - MANSELL STREET; BACK STREET to CONTREE CROIX MANSELL ( BACK STREET to CONTREE CROIX MANSELL )
Description: Service alteration
Start date: Saturday, 14/03/26 End date: Monday, 16/03/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vauvert PS 1A Cycle Access: Dismount past works

ST. PETER PORT - THE QUAY
Description: Crane lift
Start date: Sunday, 15/03/26 End date: Sunday, 15/03/26 Timing: Between AM and PM Peaks
Promoter: AFM Contractor: AFM
Bus Routes Affected: 11;12;13;21;31;32;41;42;52;60;61;71;81;91;N1;N2;N4 Cycle Access: No

ST. PIERRE DU BOIS - ROUTE DES CLOS LANDAIS ( RUE DE LA FLAGUEE to RUE DES MASSIES )
Description: Drainage works
Start date: Monday, 16/03/26 End date: Monday, 23/03/26 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Geomarine
Bus Routes Affected: Houguette 1B; Houguette 3B; Houguette 4A; LMDC 3A / LB 8A; LMDC 3B / LB 8B; 60;N4 Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DES PRES
Description: Erect Scaffolding; Property: Le Pre; Purpose: Roofing Works
Start date: Wednesday, 18/03/26 End date: Thursday, 19/03/26 Timing: All Day
Promoter: Island Scaffolding Contractor: Island Scaffolding
Bus Routes Affected: Houguette PS 1A Cycle Access: Yes

ST. SAMPSON - LES CANUS ( LES ABREUVEURS ROAD to LA ROUTE DES CAPELLES )
Description: unloading container
Start date: Monday, 16/03/26 End date: Tuesday, 17/03/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Vauvert PS 1A;SS HS 2B;SS HS 7B Cycle Access: Yes

ST. SAVIOUR - LA RUE DU HAMEL
Description: Low voltage cabling and service upgrade
Start date: Monday, 16/03/26 End date: Friday, 05/06/26 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Houguette PS 1B;Houguette PS 3B;LBHS 5A;LBHS 5B;LMDC HS 1A 2A;LMDC HS 1B 2B;LMDC HS 4A;LMDC HS 4B;LV HS 3B;LV HS 8A Cycle Access: Dismount past works

ST. SAVIOUR - RUE DES BOULAINS ( RUE DES GRANTEZ to RUE DES FAUXQUETS )
Description: Tree Surgery
Start date: Wednesday, 18/03/26 End date: Friday, 20/03/26 Timing: Between AM and PM Peaks
Promoter: treeworks Contractor: treeworks
Bus Routes Affected: Cycle Access: No

VALE - LA GRANDE RUE
Description: Works to driveway at `Blaenwern`
Start date: Monday, 16/03/26 End date: Friday, 20/03/26 Timing: All Day
Promoter: Tarmac Services Contractor: Tarmac Services
Bus Routes Affected: SS 5A; SS 5B; 11;12;N1 Cycle Access: Yes

VALE - LA ROUTE DU BRAYE ( LA BAILLOTERIE LANE to LA ROUTE MILITAIRE )
Description: Repair manhole covers
Start date: Saturday, 14/03/26 End date: Sunday, 15/03/26 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: Vale 2B; Vale 3B; SS 2B; P2;12;13;N1 Cycle Access: Dismount past works

One Ways
ST. PETER PORT - TOWER HILL
Description: Work starting 08:00 AM on Mon 16 Mar 26 and finishing 04:30 PM on Tue 17 Mar 26 - Splicing Work
Start date: Monday, 16/03/26 End date: Tuesday, 17/03/26 Timing: All Day
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

VALE - Chertsey House Dental 5K Race ( LA JAONNEUSE ROAD to MONT CUET ROAD )
Description: Event between 7am and 12pm
Start date: Sunday, 15/03/26 End date: Sunday, 15/03/26 Timing: All Day
Promoter: Guernsey Athletics Club Contractor: N/A
Bus Routes Affected: Cycle Access: Yes, in direction of one-way

Signals
CASTEL - LA NEUVE RUE; RUE D'ALBECQ to COBO COAST ROAD ( RUE D'ALBECQ to COBO COAST ROAD )
Description: Road side patch repair
Start date: Monday, 16/03/26 End date: Monday, 16/03/26 Timing: Between AM and PM Peaks
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - LA ROUTE DES CORNUS ( LA RUE MAZE to LA PLANQUE LANE )
Description: Driveway works
Start date: Monday, 16/03/26 End date: Friday, 20/03/26 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: St Martin 1A; St Martin 1B; LB 2B; LB 4B; LB 9B; LMDC 4A; LV 4A; 81;91;92;93;94;95;N3 Cycle Access: Yes