Only closures of main traffic routes are listed in this summary.
For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.
|
CASTEL - ROUTE DE COBO
|
|
|
Description:
|
High and low voltage cabling upgrade, replacement of roadside distribution pillar and service upgrades
|
|
Start date:
|
Monday, 23/03/26
|
End date:
|
Friday, 17/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
Castel 3B; LMDC 6B / LV 6B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; 41
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - RUETTE DE TOUILLETS
|
( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
|
|
Description:
|
Work starting 08:00 AM on Sat 19 Aug 23 and finishing 05:00 PM on Mon 31 Aug 26 - Investigation and repairs to roadside wall
|
|
Start date:
|
Saturday, 19/08/23
|
End date:
|
Monday, 31/08/26
|
Timing:
All Day
|
|
Promoter:
|
Private Individual
|
Contractor:
|
Private Individual
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
FOREST - LA RUE DES CROISEE
|
|
|
Description:
|
Work starting 07:30 AM on Mon 11 May 26 and finishing 04:00 PM on Fri 29 May 26 - Road resurfacing
|
|
Start date:
|
Monday, 11/05/26
|
End date:
|
Friday, 29/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. MARTIN - VAL AU BOURG
|
|
|
Description:
|
Install new substation and associated high and low voltage cabling, lay down area for ongoing works in Rue Tonnelle
|
|
Start date:
|
Tuesday, 07/04/26
|
End date:
|
Friday, 19/06/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
LBHS 1A;LBHS 2A
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - BERTHELOT STREET
|
|
|
Description:
|
Work starting 07:30 AM on Mon 17 Mar 25 and finishing 11:59 PM on Thu 31 Dec 26 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
|
|
Start date:
|
Monday, 17/03/25
|
End date:
|
Thursday, 31/12/26
|
Timing:
All Day
|
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - HAVILLAND STREET
|
|
|
Description:
|
Work starting 06:00 AM and finishing 10:00 AM daily between Sat 04 Apr 26 and Sat 30 May 26 - SCAFFOLDING WORKS; Property: HAVILLAND COTTAGE; Purpose: Roofing Works
|
|
Start date:
|
Saturday, 04/04/26
|
End date:
|
Saturday, 30/05/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Action Scaffolding
|
Contractor:
|
Action Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LES COTILS
|
|
|
Description:
|
Erecting scaffolding.; Property: Mont Bleu ; Purpose: Roofing Works
|
|
Start date:
|
Friday, 10/04/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Advanced Scaffolding (Guernsey)
|
Contractor:
|
Advanced Scaffolding (Guernsey)
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LES PETITES FONTAINES
|
( MOUNT HERMON to VALNORD ROAD )
|
|
Description:
|
wall repairs
|
|
Start date:
|
Saturday, 02/05/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
TNT Stonemasons
|
Contractor:
|
TNT Stonemasons
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - PIETTE ROAD
|
|
|
Description:
|
ERECTING SCAFFOLDING; Property: BURNLEY; Purpose: Roofing Works
|
|
Start date:
|
Wednesday, 22/04/26
|
End date:
|
Sunday, 12/07/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Advanced Scaffolding (Guernsey)
|
Contractor:
|
Advanced Scaffolding (Guernsey)
|
|
Bus Routes Affected:
|
Vauvert PS 1B
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - VALNORD LANE
|
( VALNORD ESTATE to GREEN LANES )
|
|
Description:
|
Work starting 08:00 AM and finishing 11:59 PM daily between Mon 23 Jun 25 and Tue 30 Jun 26 - Delivery of building materials.
|
|
Start date:
|
Monday, 23/06/25
|
End date:
|
Tuesday, 30/06/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Hillstone Guernsey Ltd
|
Contractor:
|
Hillstone Guernsey Ltd
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes, in direction of one-way
|
|
ST. PETER PORT - WATER LANES
|
|
|
Description:
|
Low voltage distribution pillar installation and low voltage network upgrades
|
|
Start date:
|
Tuesday, 05/05/26
|
End date:
|
Friday, 05/06/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
Capelles PS 1A;SS HS 1B
|
Cycle Access:
|
No
|
|
ST. SAMPSON - ROUTE MILITAIRE
|
|
|
Description:
|
Repair manhole covers
|
|
Start date:
|
Monday, 11/05/26
|
End date:
|
Monday, 18/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Vale 1A; Vale 3B; SS 4A; SS 5A; SS 6A; SS 8A; 13;21
|
Cycle Access:
|
Dismount past works
|
|
ST. SAMPSON - ROUTE MILITAIRE
|
|
|
Description:
|
Work starting 09:30 AM on Mon 11 May 26 and finishing 05:30 PM on Fri 22 May 26 - Various repairs
|
|
Start date:
|
Monday, 11/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Highways Inspector)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Vale 1A; Vale 3B; SS 4A; SS 5A; SS 6A; SS 8A; 13;21
|
Cycle Access:
|
Yes
|
|
ST. SAVIOUR - LA RUE DU HAMEL
|
|
|
Description:
|
Work starting 08:00 AM on Mon 16 Mar 26 and finishing 05:00 PM on Fri 22 May 26 - Low voltage cabling and service upgrade
|
|
Start date:
|
Monday, 16/03/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Guernsey Electricity
|
|
Bus Routes Affected:
|
Houguette PS 1B;Houguette PS 3B;LBHS 5A;LBHS 5B;LMDC HS 1A 2A;LMDC HS 1B 2B;LMDC HS 4A;LMDC HS 4B;LV HS 3B;LV HS 8A
|
Cycle Access:
|
Dismount past works
|
|
ST. SAVIOUR - RUE DES CRABBES; RUE DE ST. APPOLINE to RUE PERELLE
|
( RUE DE ST. APPOLINE to RUE PERELLE )
|
|
Description:
|
Work starting 08:30 AM on Fri 15 May 26 and finishing 05:00 PM on Tue 19 May 26 - Repair water leak
|
|
Start date:
|
Friday, 15/05/26
|
End date:
|
Tuesday, 19/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Houguette PS 1B;Houguette PS 3B;LBHS 5A;LBHS 5B;LMDC HS 3A;LMDC HS 3B;LMDC HS 4A;LMDC HS 4B;LV HS 3B;LV HS 8A;LMDC HS LB HS 3A;LMDC HS LB HS 3B
|
Cycle Access:
|
Dismount past works
|
|
ST. SAVIOUR - RUE DES HURIAUX
|
( LA RUE DU HAMEL to RUE DU MONT SAINT )
|
|
Description:
|
Work starting 08:00 AM on Wed 15 Apr 26 and finishing 05:00 PM on Fri 22 May 26 - Low voltage cabling and service upgrades
|
|
Start date:
|
Wednesday, 15/04/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Guernsey Electricity
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
VALE - SUMMERFIELD ROAD
|
|
|
Description:
|
Work starting 07:30 AM on Tue 05 May 26 and finishing 04:00 PM on Sun 17 May 26 - Road resurfacing
|
|
Start date:
|
Tuesday, 05/05/26
|
End date:
|
Sunday, 17/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
Vale 1A; Vale 3B; LV 1A; LV 1B; SS 6A; SS 6B; 11;13;91;92
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - ROUTE DU TERTRE; RUE DE LA MASSE to LES QUERITES
|
( RUE DE LA MASSE to LES QUERITES )
|
|
Description:
|
Repair and rebuild road side wall
|
|
Start date:
|
Monday, 09/03/26
|
End date:
|
Friday, 12/06/26
|
Timing:
All Day
|
|
Promoter:
|
Fixt Ltd
|
Contractor:
|
Fixt Ltd
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes, in direction of one-way
|
|
ST. MARTIN - RUE DE LA VALLEE
|
|
|
Description:
|
SCAFFOLDING ERECTION; Property: BELLA LUCE; Purpose: Installation
|
|
Start date:
|
Monday, 13/04/26
|
End date:
|
Friday, 29/05/26
|
Timing:
All Day
|
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
|
Bus Routes Affected:
|
LV 4A; LV 4B; 81
|
Cycle Access:
|
Yes
|
|
CASTEL - KING'S MILLS ROAD; RUE DES BERGERS to LA SAUVARINERIE
|
( RUE DES BERGERS to LA SAUVARINERIE )
|
|
Description:
|
Work starting 08:00 AM on Mon 23 Mar 26 and finishing 04:00 PM on Fri 12 Jun 26 - Rebuilding a Roadside Wall.
|
|
Start date:
|
Monday, 23/03/26
|
End date:
|
Friday, 12/06/26
|
Timing:
All Day
|
|
Promoter:
|
NSP Foundations
|
Contractor:
|
NSP Foundations
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
CASTEL - Our Race For Life
|
|
|
Description:
|
Charity race between 10:30am and 1:00pm
|
|
Start date:
|
Sunday, 17/05/26
|
End date:
|
Sunday, 17/05/26
|
Timing:
All Day
|
|
Promoter:
|
race for life
|
Contractor:
|
N/A
|
|
Bus Routes Affected:
|
LMDC 7A; 41
|
Cycle Access:
|
No
|
|
CASTEL - RUE A L`EAU
|
( MOULIN DE HAUT to LA SAUVARINERIE )
|
|
Description:
|
Work starting 07:30 AM on Sat 16 May 26 and finishing 05:00 PM on Fri 22 May 26 - Repair defective bitmac
|
|
Start date:
|
Saturday, 16/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Highways Inspector)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
LB 4A; LB 4B; LB 4A Overflow
|
Cycle Access:
|
Yes
|
|
CASTEL - RUETTE DES MAROTTES
|
( RUETTE DE FRIES to RUETTE DU FROCQ )
|
|
Description:
|
Repairs to defective Asphalt
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Tuesday, 19/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Highways Inspector)
|
Contractor:
|
Tarmac Services
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
SEAFRONT SUNDAY - GSPCA Sunday 2026
|
|
|
Description:
|
Town seafront closed between 7am to 6pm
|
|
Start date:
|
Sunday, 17/05/26
|
End date:
|
Sunday, 17/05/26
|
Timing:
All Day
|
|
Promoter:
|
GSPCA
|
Contractor:
|
N/A
|
|
Bus Routes Affected:
|
St Martin PS 3A;St Martin PS 3B;LBHS 2A;LMDC HS 5A;LMDC HS 6B;LV HS 4A;SS HS 1A;SS HS 2A
|
Cycle Access:
|
Dismount past works:
|
|
ST. ANDREW - ROUTE DE LA CROIX AU BAILIFF
|
|
|
Description:
|
Install new water service
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Wednesday, 20/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
St Martin 1A; St Martin 1B; LB 1A; LB 1B; LB 2A; LB 2B; LB 3A; LB 3B; LV 4B; LV 5A / LB 6A; LV 5B / LB 6B; P2;51;52;60;61
|
Cycle Access:
|
Dismount past works
|
|
ST. ANDREW - ROUTE DE LA CROIX AU BAILIFF
|
( RUE DES POINTES to LES RUETTES )
|
|
Description:
|
New supply line
|
|
Start date:
|
Wednesday, 20/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
St Martin 1A; St Martin 1B; LB 1A; LB 1B; LB 2A; LB 2B; LB 3A; LB 3B; LV 4B; LV 5A / LB 6A; LV 5B / LB 6B; P2;51;52;60;61
|
Cycle Access:
|
Dismount past works
|
|
ST. MARTIN - ICART ROAD
|
|
|
Description:
|
Work starting 07:30 AM on Mon 18 May 26 and finishing 04:00 PM on Fri 05 Jun 26 - Road resurfacing
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Friday, 05/06/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - HAVELET
|
( THE STRAND to HAUTEVILLE )
|
|
Description:
|
Skip outside property to carry out renovation
|
|
Start date:
|
Friday, 22/05/26
|
End date:
|
Sunday, 07/06/26
|
Timing:
All Day
|
|
Promoter:
|
Private Individual
|
Contractor:
|
Private Individual
|
|
Bus Routes Affected:
|
St Martin PS 3A;St Martin PS 3B;LBHS 2A;LBHS 3B;LV HS 4A;LV HS 6B
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LE TRUCHOT
|
|
|
Description:
|
cherry picker for roof repairs
|
|
Start date:
|
Thursday, 21/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Savills
|
Contractor:
|
Savills
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - LES AMBALLES
|
( ST. JOHN'S ROAD to LE BOUET )
|
|
Description:
|
Main Drainage Investigation CCTV
|
|
Start date:
|
Friday, 22/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Guernsey Water (Wastewater)
|
|
Bus Routes Affected:
|
Vale PS 2A;LV HS 1A;SS HS 6A
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - LES COTILS
|
( LES AMBALLES to BEAUREGARD LANE )
|
|
Description:
|
Work starting 09:00 AM on Tue 19 May 26 and finishing 05:00 PM on Wed 20 May 26 - home furniture deliveries
|
|
Start date:
|
Tuesday, 19/05/26
|
End date:
|
Wednesday, 20/05/26
|
Timing:
All Day
|
|
Promoter:
|
White and Company
|
Contractor:
|
White and Company
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LES VAUXLAURENS
|
|
|
Description:
|
Gutter cleaning
|
|
Start date:
|
Sunday, 17/05/26
|
End date:
|
Sunday, 17/05/26
|
Timing:
All Day
|
|
Promoter:
|
Premium Cleaning Services
|
Contractor:
|
Premium Cleaning Services
|
|
Bus Routes Affected:
|
31;32;41;42;60;61;71;81;N2;N4
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - VICTORIA ROAD
|
|
|
Description:
|
Work starting 08:30 AM on Wed 20 May 26 and finishing 05:00 PM on Fri 22 May 26 - Install new water service
|
|
Start date:
|
Wednesday, 20/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PIERRE DU BOIS - RUE DE LA CACHE
|
( RUE DE LA POMARE to RUE DU DOUIT DU MOULIN )
|
|
Description:
|
Work starting 08:30 AM on Wed 20 May 26 and finishing 05:00 PM on Tue 26 May 26 - Drainage works
|
|
Start date:
|
Wednesday, 20/05/26
|
End date:
|
Tuesday, 26/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Highways Inspector)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Houguette PS 1A;Houguette PS 1B;Houguette PS 2A;Houguette PS 2B;Houguette PS 3A;Houguette PS 4B;LB HS 6A;LB HS 6B;LMDC HS 3B;LMDC HS 4A;LMDC HS 4B;LV HS 5A;LV HS 5B;LV HS LB HS 5A;LV HS LB HS 5B
|
Cycle Access:
|
No
|
|
ST. SAVIOUR - SSAV-MISC6
|
( RUE FEVERESSE to RUE DES ISSUES )
|
|
Description:
|
Tree surgery work
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Monday, 18/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Tree Service Ltd
|
Contractor:
|
Guernsey Tree Service Ltd
|
|
Bus Routes Affected:
|
Houguette PS 2A;Houguette PS 2B;Houguette PS 4B;LB HS 6A;LB HS 6B;LV HS 6B
|
Cycle Access:
|
No
|
|
TORTEVAL - RUE DES BROUARDS
|
|
|
Description:
|
Replace decayed telephone pole
|
|
Start date:
|
Wednesday, 20/05/26
|
End date:
|
Wednesday, 20/05/26
|
Timing:
All Day
|
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Sure Guernsey
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
VALE - BUNKER HILL
|
|
|
Description:
|
concrete pump
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Monday, 18/05/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Ray Green Ltd
|
Contractor:
|
Ray Green Ltd
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
VALE - LA HOUGUE JEHANNET; SUMMERFIELD ROAD to
|
( SUMMERFIELD ROAD to )
|
|
Description:
|
High voltage cabling for emergency substation replacement
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Friday, 26/06/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
No future major delays due to one ways
|
CASTEL - COBO COAST ROAD
|
( ROUTE DE COBO to ROUTE DE CARTERET )
|
|
Description:
|
Work starting 07:30 AM on Mon 18 May 26 and finishing 05:00 PM on Fri 22 May 26 - Rendering to roadside face of boundary wall and installing glazing
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Friday, 22/05/26
|
Timing:
All Day
|
|
Promoter:
|
J W Rihoy Builders
|
Contractor:
|
J W Rihoy Builders
|
|
Bus Routes Affected:
|
LMDC 4A; LMDC 4B; LMDC 6B / LV 6B; LV 3B; LV 8A; LMDC 3B / LB 8B; 41;42;91;92;N2
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - FORT ROAD; LE VAL DES TERRES to CROUTES HAVILLAND
|
( LE VAL DES TERRES to CROUTES HAVILLAND )
|
|
Description:
|
Supply line upgrade
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Wednesday, 20/05/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PIERRE DU BOIS - ROUTE DE PLAISANCE
|
|
|
Description:
|
Work starting 08:30 AM on Mon 18 May 26 and finishing 05:00 PM on Wed 20 May 26 - Repair defective gully
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Wednesday, 20/05/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Highways Inspector)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
VALE - L'ANCRESSE ROAD
|
|
|
Description:
|
Essential maintenance to gas Mains and Services.
|
|
Start date:
|
Monday, 18/05/26
|
End date:
|
Monday, 08/06/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Gas
|
Contractor:
|
Guernsey Gas
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|