Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - ROUTE DE L`EGLISE
Description: Work starting 04:00 PM on Mon 19 May 25 and finishing 05:00 PM on Fri 18 Jul 25 - Lay new water transfer main
Start date: Monday, 19/05/25 End date: Friday, 18/07/25 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Castel 1B; LB 1A; LB 2A; LB 2B; LB 3A; LB 3B; LV 3B; LV 5A / LB 6A; LV 5B / LB 6B; 60;61 Cycle Access: Dismount past works

CASTEL - RUE DES GODDARDS ( VAZON ROAD to ROUTE DE LA MARE )
Description: Work starting 09:00 AM on Mon 19 May 25 and finishing 05:00 PM on Mon 30 Jun 25 - Mains replacement program to enhance the safety, reliability, and efficiency of the gas network.
Start date: Monday, 19/05/25 End date: Monday, 30/06/25 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Castel PS 2A;Castel PS 3B;LMDC HS 1A 2A;LMDC HS 1B 2B;LMDC HS 3A;LMDC HS 3B;LMDC HS 4A;LMDC HS 4B;LV HS 3B;LV HS 8A;LMDC HS LB HS 3B Cycle Access: Dismount past works

CASTEL - RUE DU FRIE PLAIDY
Description: Work starting 07:00 AM and finishing 11:59 PM daily between Sat 15 Mar 25 and Sat 31 May 25 - Scaffolding; Property: Le Frie Plaidy; Purpose: Other (see Details)
Start date: Saturday, 15/03/25 End date: Saturday, 31/05/25 Timing: Between AM and PM Peaks
Promoter: Island Scaffolding Contractor: Island Scaffolding
Bus Routes Affected: Cycle Access: Yes

CASTEL - RUETTE DE TOUILLETS ( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
Description: Work starting 08:00 AM on Sat 19 Aug 23 and finishing 11:59 PM on Mon 30 Jun 25 - Investigation and repairs to roadside wall
Start date: Saturday, 19/08/23 End date: Monday, 30/06/25 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

CASTEL - SOUS LES COURTILS; ROUTE DE LA MARE to RUE D'ALBECQ ( ROUTE DE LA MARE to RUE D'ALBECQ )
Description: To replace a faulty Sub Station, and replacement of High Voltage Cable.
Start date: Monday, 19/05/25 End date: Monday, 11/08/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Castel 2A; Castel 3B; 60 Cycle Access: Dismount past works

Emergency Activity - CASTEL - ROUTE DE SAUMAREZ
Description: Work starting 02:30 PM on Thu 22 May 25 and finishing 04:00 PM on Fri 30 May 25 - To repair a faulty High Voltage cable
Start date: Thursday, 22/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: LMDC 6A / LV 6A; LMDC 7A; SS 4A; SS 4B; P2;41;42;N2 Cycle Access: Dismount past works

FOREST - LE BOURG ( LE CHENE to RUE DES AUBERTS )
Description: Work starting 08:30 AM on Tue 20 May 25 and finishing 05:00 PM on Fri 23 May 25 - Install new water service
Start date: Tuesday, 20/05/25 End date: Friday, 23/05/25 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Forest 2A; Forest 2B; LB 4A Overflow; LB 5A; LB 5B; LB 9B; LMDC 4A; LV 5A / LB 6A; LV 5B / LB 6B; 91;92;93;94;95;N3 Cycle Access: Dismount past works

FOREST - LE BOURG
Description: new supply line
Start date: Monday, 19/05/25 End date: Friday, 23/05/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Forest 2A; Forest 2B; LB 4A Overflow; LB 5A; LB 5B; LB 9B; LMDC 4A; LV 5A / LB 6A; LV 5B / LB 6B; 91;92;93;94;95;N3 Cycle Access: Dismount past works

ST. ANDREW - ROUTE DES FAUCONNAIRES
Description: Work starting 07:30 AM on Mon 19 May 25 and finishing 04:00 PM on Fri 13 Jun 25 - Road resurfacing
Start date: Monday, 19/05/25 End date: Friday, 13/06/25 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - BERTHELOT STREET
Description: Work starting 07:30 AM on Mon 17 Mar 25 and finishing 11:59 PM on Sun 30 Nov 25 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
Start date: Monday, 17/03/25 End date: Sunday, 30/11/25 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - IVY CASTLE LANE
Description: Work starting 07:30 AM on Thu 24 Apr 25 and finishing 07:00 PM on Fri 06 Jun 25 - Scaffolding.; Property: Apartment 1, Meadowview; Purpose: Roofing Works
Start date: Thursday, 24/04/25 End date: Friday, 06/06/25 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LE TRUCHOT ( LOWER CANICHERS to ST. JULIAN'S WEIGHBRIDGE )
Description: Strike of scaffolding at ETWH, Lower Truchot.
Start date: Wednesday, 21/05/25 End date: Friday, 23/05/25 Timing: All Day
Promoter: States Property Services Contractor: States Property Services
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LES PETITES FONTAINES ( MOUNT HERMON to VALNORD ROAD )
Description: Work starting 11:30 AM on Fri 22 Nov 24 and finishing 11:59 PM on Fri 30 May 25 - wall repairs
Start date: Friday, 22/11/24 End date: Friday, 30/05/25 Timing: All Day
Promoter: TNT Stonemasons Contractor: TNT Stonemasons
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LES VAUXLAURENS
Description: Work starting 07:30 AM and finishing 05:00 PM daily between Fri 29 Nov 24 and Fri 30 May 25 - Scaffold to access for emergency works from storm damage; Property: Apartments 4 and 29 St Julians Avenue; Purpose: Roofing Works
Start date: Friday, 29/11/24 End date: Friday, 30/05/25 Timing: Between AM and PM Peaks
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - ROUTE DE LIHOU ( RUE DU LONGFRIE to RUE DES GRANDES RUES )
Description: Work starting 09:00 AM on Thu 29 Aug 24 and finishing 11:59 PM on Sat 31 May 25 - Road blocked due to collapsed granite wall approx 10m from the Route de Lihou and Rue du Longfrie junction, near property Longfrie House.
Start date: Thursday, 29/08/24 End date: Saturday, 31/05/25 Timing: All Day
Promoter: Traffic and Highways Contractor: Traffic and Highways
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DE LA VALLEE ( RUE DES BUTTES to RUE TREMEL )
Description: Work starting 07:00 AM on Mon 19 May 25 and finishing 05:00 PM on Tue 27 May 25 - Unloading scaffolding
Start date: Monday, 19/05/25 End date: Tuesday, 27/05/25 Timing: All Day
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: No

ST. SAMPSON - LES GRANDES MAISONS ROAD ( LES BAS COURTILS ROAD to LONGUE HOUGUE LANE )
Description: Work starting 07:00 AM on Tue 06 May 25 and finishing 05:00 PM on Fri 11 Jul 25 - Low voltage cable upgrade and service connections
Start date: Tuesday, 06/05/25 End date: Friday, 11/07/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Vale 2A; Vale 2B; LV 1A; LV 1B; LV 2B; SS 2B; SS 6A; SS 6B; 11;12;91;92;N1 Cycle Access: Dismount past works

One Ways
No current major delays due to one ways
Signals
CASTEL - VAZON ROAD
Description: Work starting 09:00 AM on Mon 12 May 25 and finishing 05:00 PM on Tue 03 Jun 25 - Mains replacement program to enhance the safety, reliability, and efficiency of the gas network.
Start date: Monday, 12/05/25 End date: Tuesday, 03/06/25 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Castel 2A; Castel 3B; LMDC 4A; LMDC 4B; LV 3B; LV 8A; LMDC 3B / LB 8B; 42;60;91;92;N2 Cycle Access: Yes

ST. ANDREW - ROHAIS DE BAS; RUETTE CRESSARD to ROHAIS ( RUETTE CRESSARD to ROHAIS )
Description: Repair water leak
Start date: Thursday, 22/05/25 End date: Friday, 23/05/25 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LE BORDAGE
Description: Phase 2 of St Peter's House; Property: St Peter`s House; Purpose: Roofing Works
Start date: Saturday, 05/04/25 End date: Monday, 30/06/25 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LES GRANDES MAISONS ROAD; LES BAS COURTILS ROAD to LONGUE HOUGUE LANE ( LES BAS COURTILS ROAD to LONGUE HOUGUE LANE )
Description: Rebuilding roadside wall.
Start date: Tuesday, 13/05/25 End date: Friday, 06/06/25 Timing: Between AM and PM Peaks
Promoter: A J Watson Contractor: A J Watson
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
CASTEL - Cobo Balcony Gig ( ROUTE DE COBO to ROUTE DE CARTERET )
Description: Cobo Balcony Gig
Start date: Monday, 26/05/25 End date: Monday, 26/05/25 Timing: All Day
Promoter: Cobo Bay Hotel - Nut Tree Ltd Contractor: N/A
Bus Routes Affected: LMDC 4A; LMDC 4B; LMDC 6B / LV 6B; LV 3B; LV 8A; LMDC 3B / LB 8B; 41;42;91;92;N2 Cycle Access: Dismount past works

CASTEL - ROUTE DE CARTERET
Description: Work starting 08:30 AM on Tue 27 May 25 and finishing 05:00 PM on Mon 09 Jun 25 - Install new foul sewer connection
Start date: Tuesday, 27/05/25 End date: Monday, 09/06/25 Timing: All Day
Promoter: Geomarine Contractor: Geomarine
Bus Routes Affected: SS 8A; SS 8B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; 42 Cycle Access: Dismount past works

ST. ANDREW - CANDIE ROAD ( LA MARE to RUE DES ROQUETTES )
Description: Work starting 07:00 AM on Tue 27 May 25 and finishing 05:00 PM on Thu 29 May 25 - Supply line upgrade
Start date: Tuesday, 27/05/25 End date: Thursday, 29/05/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. ANDREW - RUE DE LA BOULLERIE ( RUE DES BAILLEULS to LES NAFTIAUX ESTATE )
Description: Work starting 08:00 AM on Tue 27 May 25 and finishing 05:00 PM on Wed 28 May 25 - Excavate blocked duct
Start date: Tuesday, 27/05/25 End date: Wednesday, 28/05/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Forest 2A; Forest 2B; St Martin 1A; St Martin 1B; LB 4B Cycle Access: Dismount past works

ST. ANDREW - RUE DE LA BOULLERIE ( LES NAFTIAUX ESTATE to RUE DES HOUGUES )
Description: Work starting 08:00 AM and finishing 05:00 PM daily between Thu 29 May 25 and Fri 30 May 25 - Cable splicing 8am - 4pm daily
Start date: Thursday, 29/05/25 End date: Friday, 30/05/25 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Forest 2B; St Martin 1A; LB 4B; LB 4A Overflow Cycle Access: Dismount past works

ST. ANDREW - RUE MARQUAND ( LES MOURANTS to RUE DES LANDES )
Description: Gardening works
Start date: Tuesday, 27/05/25 End date: Tuesday, 27/05/25 Timing: All Day
Promoter: Cutbacks Contractor: Cutbacks
Bus Routes Affected: Cycle Access: No

ST. MARTIN - LA GRANDE RUE
Description: Work starting 09:00 AM on Tue 27 May 25 and finishing 05:00 PM on Fri 30 May 25 - Undertake trial trenches
Start date: Tuesday, 27/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Geomarine Contractor: Geomarine
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 1A; LB 1B; LB 2A; LB 3B; LV 4B; 81;91;92;93;94;95;N3 Cycle Access: Dismount past works

ST. PETER PORT - CROUTES HAVILLAND ( FORT ROAD to DAMOUETTES LANE )
Description: Work starting 09:30 AM and finishing 04:00 PM - Household removal.
Start date: Wednesday, 28/05/25 End date: Wednesday, 28/05/25 Timing: Between AM and PM Peaks
Promoter: R and R Removals Contractor: R and R Removals
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - EDABL Seafront Sunday May 25th 2025
Description: EDABL Seafront Sunday May 25th 2025
Start date: Sunday, 25/05/25 End date: Sunday, 25/05/25 Timing: All Day
Promoter: EDABL Committee Contractor: N/A
Bus Routes Affected: 11;12;13;21;31;32;41;42;51;60;61;71;81;92;N1;N2;N4 Cycle Access: Dismount past works

ST. PETER PORT - Guernsey Kart and Motor Club LBG - Val Des Terres ( Castle Emplacement to Fort Road )
Description: Guernsey Kart and Motor Club LBG - Val Des Terres
Start date: Monday, 26/05/25 End date: Monday, 26/05/25 Timing: All Day
Promoter: GKMC - Guernsey Kart and Motor Club Contractor: N/A
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 2A; LMDC 7B Cycle Access: No

ST. PETER PORT - LES VARDES ( MONTVILLE ROAD to PIED DES VARDES )
Description: Work starting 08:00 AM on Fri 23 May 25 and finishing 05:00 PM on Sun 25 May 25 - Repairing road side wall
Start date: Friday, 23/05/25 End date: Sunday, 25/05/25 Timing: All Day
Promoter: Hillstone GSY Ltd Contractor: Hillstone GSY Ltd
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - SAUSMAREZ STREET ( UNION STREET to NORTH CLIFTON )
Description: New duct installation
Start date: Thursday, 29/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - SIR WILLIAM PLACE ( LA PLAIDERIE to LE TRUCHOT )
Description: Closure of Sir William Place to enable scaffolding to be struck from ETWH
Start date: Saturday, 24/05/25 End date: Saturday, 24/05/25 Timing: All Day
Promoter: States Property Services Contractor: States Property Services
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - UPPER MANSELL STREET ( PARK STREET to TRINITY SQUARE )
Description: Ladder access for cabling works
Start date: Wednesday, 28/05/25 End date: Thursday, 29/05/25 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - OATLANDS LANE ( LES GIGANDS ROAD to LES SAUVAGEES )
Description: Replacing Streetlights
Start date: Tuesday, 27/05/25 End date: Thursday, 29/05/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

VALE - PLEINHEAUME ROAD ( L'ETONNELLERIE to LES BARRAS LANE )
Description: Tree surgery works.
Start date: Wednesday, 28/05/25 End date: Wednesday, 28/05/25 Timing: All Day
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: Capelles 1A; Capelles 1B; LV 1B; LV 8A; SS 1B; SS 4A; SS 4B; 31;32 Cycle Access: Dismount past works

VALE - ROCQUE ES CAS ( VALE-MISC54 to LA RUE DE LA CORDERIE )
Description: Tree works
Start date: Friday, 23/05/25 End date: Friday, 23/05/25 Timing: Between AM and PM Peaks
Promoter: treeworks Contractor: treeworks
Bus Routes Affected: Cycle Access: No

One Ways
ST. PETER PORT - BROCK ROAD
Description: Work starting 09:00 AM and finishing 03:00 PM - Household removal.
Start date: Thursday, 29/05/25 End date: Thursday, 29/05/25 Timing: Between AM and PM Peaks
Promoter: Diamond Group Ltd Contractor: Diamond Group Ltd
Bus Routes Affected: 31;32 Cycle Access: Yes, in direction of one-way

ST. PETER PORT - LES GRAVEES
Description: Chamber installations x 2
Start date: Tuesday, 27/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Vauvert 1B; LMDC 7A; 41;42;N2 Cycle Access: Yes

ST. PETER PORT - VILLE AU ROI ( RUETTES BRAYES to AVENUE DU MANOIR )
Description: Work starting 08:00 AM on Thu 29 May 25 and finishing 04:00 PM on Fri 30 May 25 - Excavate blocked duct
Start date: Thursday, 29/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: St Martin 3A; St Martin 3B; LB 1A; LB 2A; LB 2B; LB 3B; LMDC 6A / LV 6A; LMDC 6B / LV 6B; LV 4A; 60;71 Cycle Access: Yes

Signals
ST. PETER PORT - ST. JAMES STREET; COLLEGE STREET to GRANGE ROAD ( COLLEGE STREET to GRANGE ROAD )
Description: Work starting 09:30 AM on Wed 28 May 25 and finishing 05:00 PM on Fri 30 May 25 - New service line
Start date: Wednesday, 28/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - ROUTE DE PLEINMONT; RUETTE DE L'AITTE to RUE DES POINTES ( RUETTE DE L'AITTE to RUE DES POINTES )
Description: Cable splicing
Start date: Friday, 23/05/25 End date: Friday, 23/05/25 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LA ROUTE DES CAPELLES; LES CANUS to VERTE RUE ( LES CANUS to VERTE RUE )
Description: Essential maintenance to gas services.
Start date: Tuesday, 27/05/25 End date: Friday, 30/05/25 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: Cycle Access: Yes