Road closures and delays

Only closures of main traffic routes are listed in this summary. For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - LES VIEUX BEAUCAMPS; RUETTE DES EFFARDS to RUE DE LA PERRUQUE ( RUETTE DES EFFARDS to RUE DE LA PERRUQUE )
Description: Work starting 08:00 AM on Mon 06 Mar 23 and finishing 11:59 PM on Wed 29 Mar 23 - Slip line leaking main
Start date: Monday, 06/03/23 End date: Wednesday, 29/03/23 Timing: All Day
Promoter: Guernsey Water Contractor: Guernsey Water
Bus Routes Affected: Cycle Access: Dismount past works

CASTEL - ROUTE DE COBO ( LE DOUIT BOUDIN to RUE DE BOUVERIE )
Description: Work starting 08:00 AM on Mon 20 Mar 23 and finishing 05:00 PM on Wed 29 Mar 23 - Chamber and duct installations
Start date: Monday, 20/03/23 End date: Wednesday, 29/03/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 41 Cycle Access: Yes

FOREST - LES NICOLLES ( to FST-MISC28 )
Description: Work starting 07:00 AM on Mon 27 Mar 23 and finishing 05:00 PM on Tue 11 Apr 23 - service alteration
Start date: Monday, 27/03/23 End date: Tuesday, 11/04/23 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: No: dismount

ST. MARTIN - LES HUBITS
Description: Scaffolding ; Property: Maison des Arbres; Purpose: Roofing Works
Start date: Monday, 13/03/23 End date: Monday, 03/04/23 Timing: Between AM and PM Peaks
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - LONG TRAC ( RUE DES CROUTES to RUE DES MARETTES )
Description: Work starting 08:00 AM on Mon 20 Mar 23 and finishing 05:00 PM on Thu 06 Apr 23 - Network Upgrade
Start date: Monday, 20/03/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - NEW PLACE ( VICTORIA ROAD to VAUVERT )
Description: Loading and Unloading - Garden Excavation
Start date: Friday, 24/03/23 End date: Wednesday, 29/03/23 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - NEW PLACE
Description: Scaffolding No 34 Victoria Road ; Property: No 34 Victoria Road ; Purpose: Other (see Details)
Start date: Wednesday, 01/03/23 End date: Saturday, 01/04/23 Timing: Between AM and PM Peaks
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - RUE DE QUANTERAINE ( RUE DU BORDAGE to ROUTE DES SAGES )
Description: large collapsed wall - blocking road
Start date: Monday, 14/11/22 End date: Friday, 28/04/23 Timing: All Day
Promoter: Jonathan Ogier Contractor: Jonathan Ogier
Bus Routes Affected: Cycle Access: No: Road is blocked by fallen debris - unsafe area

ST. SAVIOUR - ROUTE DES BORDAGES
Description: Work starting 07:00 AM on Mon 20 Mar 23 and finishing 04:00 PM on Thu 06 Apr 23 - Road resurfacing
Start date: Monday, 20/03/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: 71 Cycle Access: Restricted: Walk through site

TORTEVAL - RUE DE LA FOLIE ( RUE DU GAINS to RUE DU HUREL )
Description: Work starting 08:00 AM on Mon 20 Mar 23 and finishing 05:00 PM on Fri 31 Mar 23 - Excavating
Start date: Monday, 20/03/23 End date: Friday, 31/03/23 Timing: All Day
Promoter: Lotus Pools Ltd Contractor: Lotus Pools Ltd
Bus Routes Affected: Cycle Access: No

TORTEVAL - RUE DES CAMBREES ( CHEMIN LE ROI to RUE GENETTE )
Description: Closure to allow main overlay and services
Start date: Monday, 20/02/23 End date: Friday, 31/03/23 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

TORTEVAL - RUE DU ROCHER
Description: Chamber and duct installation
Start date: Monday, 27/03/23 End date: Friday, 12/05/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: No: Road too narrow

VALE - LES CROUTES ( KING'S ROAD to RUE GODFREY )
Description: Work starting 07:00 AM on Mon 27 Feb 23 and finishing 04:00 PM on Thu 06 Apr 23 - Demolishing and rebuilding roadside wall
Start date: Monday, 27/02/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: East Coast Construction Contractor: East Coast Construction
Bus Routes Affected: Cycle Access: Yes

VALE - PORT SOIF LANE ( LES GRANDES MIELLES LANE to PORT SOIF ROAD )
Description: Work starting 07:30 AM on Mon 20 Feb 23 and finishing 05:00 PM on Fri 07 Apr 23 - Road resurfacing
Start date: Monday, 20/02/23 End date: Friday, 07/04/23 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: 41 Cycle Access: Restricted: Dismount Signage

VALE - RUE DE L`ECOLE
Description: Chamber and duct installation
Start date: Monday, 27/03/23 End date: Friday, 31/03/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

VALE - RUE DES HAIZES ( LA BAILLOTERIE LANE to RUETTE DES HAIZES )
Description: Install chamber and clear blocked duct
Start date: Monday, 27/03/23 End date: Wednesday, 29/03/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

One Ways
ST. MARTIN - LA RUE DES FRENES
Description: Temporary traffic signals for scaffolding in road
Start date: Thursday, 23/03/23 End date: Friday, 14/04/23 Timing: All Day
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BOSQ LANE
Description: Work starting 06:00 AM on Thu 28 Jul 22 and finishing 05:00 PM on Sun 27 Aug 23 - Scaffolding for internal building reconstruction; Property: Royal Terrace; Purpose: Other (see Details)
Start date: Thursday, 28/07/22 End date: Sunday, 27/08/23 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Yes

Signals
CASTEL - RUE COHU ( ROUTE DE SAUMAREZ to RUE DU FRIQUET )
Description: Temporary traffic lights - Repair road side wall
Start date: Monday, 27/03/23 End date: Friday, 14/04/23 Timing: All Day
Promoter: Keystone Masonry Contractor: Keystone Masonry
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - RUE DE LA VALLEE ( LES CAMPS DU MOULIN to LA RUE DES FRENES )
Description: Work starting 09:00 AM on Thu 23 Mar 23 and finishing 03:00 PM on Thu 04 Jan 24 - Scaffolding and Construction Works
Start date: Thursday, 23/03/23 End date: Thursday, 04/01/24 Timing: All Day
Promoter: Ravenscroft Construction Ltd Contractor: Traffic and Highway Services (Roadworks Coordination)
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - ROUTE DES ADAMS
Description: Final works to complete Les Adams substation replacement
Start date: Monday, 27/03/23 End date: Wednesday, 05/04/23 Timing: Between AM and PM Peaks
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 61, 71, 93, 94, N3 Cycle Access: Yes, in direction of one-way

ST. PIERRE DU BOIS - ROUTE DES PAYSANS ( RUE DE LA HOUGUETTE to ROUTE DES ADAMS )
Description: Work starting 08:00 AM on Mon 20 Mar 23 and finishing 04:00 PM on Wed 05 Jul 23 - Rebuild of roadside wall.
Start date: Monday, 20/03/23 End date: Wednesday, 05/07/23 Timing: All Day
Promoter: Granite Le Pelley Contractor: Granite Le Pelley
Bus Routes Affected: Cycle Access: Yes


Starting - next 7 days
Closures
CASTEL - LA BANQUETTE
Description: Duct installation
Start date: Monday, 03/04/23 End date: Tuesday, 11/04/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 42, N2 Cycle Access: Yes

CASTEL - ROUTE DE COBO ( LA HAYE DU PUITS to RUETTE DE LA GENEROTTE )
Description: Work starting 08:00 AM on Thu 30 Mar 23 and finishing 05:00 PM on Fri 31 Mar 23 - Duct installation across road
Start date: Thursday, 30/03/23 End date: Friday, 31/03/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 41 Cycle Access: Dismount past works

CASTEL - RUE DE LA VIEILLE MARE
Description: Install new water main and services
Start date: Monday, 03/04/23 End date: Friday, 28/04/23 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: 42 Cycle Access: Restricted: Cyclists to dismount

CASTEL - RUE DES EMRAIS ( RUE DES HOUMETS to ROUTE DE LA HOUGUE DU POMMIER )
Description: CCTV Camera Clean
Start date: Monday, 03/04/23 End date: Monday, 03/04/23 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Yes

CASTEL - Vazon Sprint - GKandMC ( RUE DU GELE to LA ROCQUETTE )
Description: Guernsey Kart and Motor Club - Sprint
Start date: Saturday, 01/04/23 End date: Saturday, 01/04/23 Timing: Between AM and PM Peaks
Promoter: Guernsey Kart and Motor Club Contractor: N/A
Bus Routes Affected: 91, 92, N2 Cycle Access: No: Motor Sport Event

ST. MARTIN - ICART ROAD ( RUE DES MARETTES to )
Description: Closure of road section between Saints Bay Hotel and Icart Car Park for felling of pine trees. Car Park closed during works.
Start date: Monday, 03/04/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: Treevolution Contractor: Treevolution
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LA PLANQUE LANE
Description: Install ducting
Start date: Monday, 03/04/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - LE COURTILLET ( ROUTE DE JERBOURG to LE MONT DURAND )
Description: Household removal
Start date: Thursday, 30/03/23 End date: Thursday, 30/03/23 Timing: Between AM and PM Peaks
Promoter: A J Removals Contractor: A J Removals
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - School Street - Route des Coutures
Description: Work starting 08:30 AM and finishing 09:00 AM - Closure of road section for School Street between: 8:30am and 9:00am
Start date: Wednesday, 29/03/23 End date: Wednesday, 29/03/23 Timing: Before AM Peak
Promoter: Traffic and Highway Services (Roadworks and Events) Contractor: N/A
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - ST. MARTIN - ST. MARTIN - School Street - Route des Coutures
Description: Closure of road section for School Street between: 2:45pm and 3:15pm
Start date: Wednesday, 29/03/23 End date: Wednesday, 29/03/23 Timing: All Day
Promoter: Traffic and Highway Services (Roadworks and Events) Contractor: N/A
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - CHURCH SQUARE
Description: Crane Lift
Start date: Sunday, 02/04/23 End date: Sunday, 02/04/23 Timing: Between AM and PM Peaks
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - GRANGE ROAD
Description: Install new water service
Start date: Monday, 03/04/23 End date: Friday, 07/04/23 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: 31, 41, 42, 51, 52, 60, 61, 71, 81, N2 Cycle Access: Restricted: Dismount

ST. PETER PORT - Guernsey Marathon 2023
Description: Work starting 08:00 AM on Sun 02 Apr 23 and finishing 05:00 PM on Sun 02 Apr 23 - Guernsey Marathon 2023
Start date: Sunday, 02/04/23 End date: Sunday, 02/04/23 Timing: All Day
Promoter: 3D Events Contractor: N/A
Bus Routes Affected: 12, 91, 92 Cycle Access: Yes

ST. PETER PORT - HAVILLAND STREET
Description: Concrete pour at property. Pump and; x2 Agi
Start date: Thursday, 30/03/23 End date: Thursday, 30/03/23 Timing: Between AM and PM Peaks
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LA VRANGUE
Description: Work starting 07:30 AM and finishing 04:30 PM daily between Thu 30 Mar 23 and Fri 31 Mar 23 - Tree Surgery Works
Start date: Thursday, 30/03/23 End date: Friday, 31/03/23 Timing: Between AM and PM Peaks
Promoter: Barrett Landscapes Ltd Contractor: Barrett Landscapes Ltd
Bus Routes Affected: 31, 32, 51, 52 Cycle Access: Yes

ST. PETER PORT - LES VARDES
Description: Tree Surgery Works
Start date: Thursday, 30/03/23 End date: Thursday, 30/03/23 Timing: Between AM and PM Peaks
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - ST STEPHEN`S HILL
Description: service alteration
Start date: Tuesday, 04/04/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - VAUVERT ( GRANGE ROAD to LA COUPERDERIE )
Description: Crane Lifts and Deliveries
Start date: Saturday, 01/04/23 End date: Saturday, 01/04/23 Timing: Between AM and PM Peaks
Promoter: F Watson and Son Contractor: F Watson and Son
Bus Routes Affected: Cycle Access: Yes

ST. PIERRE DU BOIS - RUE DE L`ECLET ( RUE DES CARRIAUX to ROUTE DES PAYSANS )
Description: CCTV Camera Clean
Start date: Tuesday, 04/04/23 End date: Tuesday, 04/04/23 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Yes

ST. SAVIOUR - RUE DES ANNEVILLES; RUE DE LA TERRE NORGIOT to RUE DE LA HOUGUE MABAN ( RUE DE LA TERRE NORGIOT to RUE DE LA HOUGUE MABAN )
Description: service alteration
Start date: Monday, 03/04/23 End date: Wednesday, 05/04/23 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

TORTEVAL - RUE DE LA BELLEE ( RUE GENETTE to RUE DE LA PLANQUE )
Description: Closure to allow for a mains overlay and services
Start date: Monday, 03/04/23 End date: Tuesday, 23/05/23 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Yes

TORTEVAL - RUE DE LA CROUTE ( RUE DES CLERCS to RUE COLLAS SIMON )
Description: Tree Surgery Works
Start date: Monday, 03/04/23 End date: Tuesday, 04/04/23 Timing: All Day
Promoter: Spruce Up Contractor: Spruce Up
Bus Routes Affected: Cycle Access: Yes

TORTEVAL - RUE DES CAMBREES
Description: LV fault in junction Les Sages and Cambrees
Start date: Wednesday, 29/03/23 End date: Wednesday, 05/04/23 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

VALE - ROUTE DES LANDES ( LA GRANDE RUE to LA RUE DU PASSEUR )
Description: Chamber and ducting in road for new service install
Start date: Monday, 03/04/23 End date: Wednesday, 05/04/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 11, 12, N1 Cycle Access: Yes

VALE - RUE D`AVAL ( LES HAUTS COURTILS LANE to RUE COLIN )
Description: Tree Surgery Works
Start date: Wednesday, 29/03/23 End date: Wednesday, 29/03/23 Timing: Between AM and PM Peaks
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: Cycle Access: Yes

VALE - RUE DE LA GREVE ( LA VILLE BAUDU to LES HOUGUES PERES )
Description: Chamber installation
Start date: Wednesday, 29/03/23 End date: Friday, 31/03/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

One Ways
ST. PETER PORT - Guernsey Marathon - Friday
Description: Guernsey Marathon - Friday Set up day
Start date: Friday, 31/03/23 End date: Friday, 31/03/23 Timing: All Day
Promoter: 3D Events Contractor: N/A
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - Guernsey Marathon - Saturday
Description: Guernsey Marathon - Saturday - Set up day
Start date: Saturday, 01/04/23 End date: Saturday, 01/04/23 Timing: All Day
Promoter: 3D Events Contractor: N/A
Bus Routes Affected: Cycle Access: Yes

Signals
ST. PIERRE DU BOIS - ROUTE DU COUDRE; RUE DE LA LICHOTERIE to RUE DU COUTEUR ( RUE DE LA LICHOTERIE to RUE DU COUTEUR )
Description: Cable splicing
Start date: Monday, 03/04/23 End date: Monday, 03/04/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - LA ROUTE DE L'ISLET
Description: Road crossing trench from chamber to pole to lay new duct
Start date: Monday, 03/04/23 End date: Thursday, 06/04/23 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Yes

VALE - LES JUQUEURS ROAD
Description: Cable splicing in chamber
Start date: Tuesday, 04/04/23 End date: Tuesday, 04/04/23 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

VALE - SOHIER ROAD
Description: Cable jointing in chamber
Start date: Thursday, 30/03/23 End date: Thursday, 30/03/23 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes