Only closures of main traffic routes are listed in this summary.
For information of closures and other traffic management on minor roads please check the Traffic & Highways Road Information Map
Please note, the timings shown relate to when works are planned to be taking place within the road section.
Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.
|
CASTEL - LES BAISSIERES
|
|
|
Description:
|
Work starting 08:30 AM on Mon 20 Jul 26 and finishing 05:00 PM on Sun 23 Aug 26 - Foul Manhole chamber refurbishments
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Sunday, 23/08/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
LV 1B; LV 2B; SS 1B; 51;52
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - LES BEAUCAMPS
|
( LES VIEUX BEAUCAMPS to MONT D`AVAL )
|
|
Description:
|
Replacement of streetlight
|
|
Start date:
|
Wednesday, 22/07/26
|
End date:
|
Thursday, 23/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
LB 1B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; LMDC 3B / LB 8B; LV 5A / LB 6A; LV 5B / LB 6B; 60;61
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - LES BEAUCAMPS
|
|
|
Description:
|
Work starting 07:30 AM on Mon 20 Jul 26 and finishing 04:00 PM on Fri 21 Aug 26 - Road resurfacing
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Friday, 21/08/26
|
Timing:
All Day
|
|
Promoter:
|
Traffic and Highway Services (Capital Works)
|
Contractor:
|
Ronez (Patching)
|
|
Bus Routes Affected:
|
LB 1B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; LMDC 3B / LB 8B; LV 5A / LB 6A; LV 5B / LB 6B; 60;61
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - RUE DE GALAAD
|
|
|
Description:
|
Work starting 08:30 AM on Mon 20 Jul 26 and finishing 11:59 PM on Fri 24 Jul 26 - Renew water meter chambers and services
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Friday, 24/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
LMDC 4A; LMDC 4B; LMDC 6A / LV 6A; LMDC 6B / LV 6B; LMDC 7A; LMDC 7B; SS 8A; SS 8B; LMDC 1A / LB 7A; LMDC 1B / LB 7B; LMDC 3A / LB 8A; LMDC 3B / LB 8B; 41;N2
|
Cycle Access:
|
Dismount past works
|
|
CASTEL - RUETTE DE TOUILLETS
|
( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
|
|
Description:
|
Work starting 08:00 AM on Sat 19 Aug 23 and finishing 05:00 PM on Mon 31 Aug 26 - Investigation and repairs to roadside wall
|
|
Start date:
|
Saturday, 19/08/23
|
End date:
|
Monday, 31/08/26
|
Timing:
All Day
|
|
Promoter:
|
Private Individual
|
Contractor:
|
Private Individual
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
FOREST - RUE DES AUBERTS
|
( LE BOURG to )
|
|
Description:
|
Primary substation replacement
|
|
Start date:
|
Monday, 22/06/26
|
End date:
|
Friday, 27/11/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. ANDREW - RUE DES ROQUETTES
|
( LES FRIQUETS to ROUTE DES TALBOTS )
|
|
Description:
|
Work starting 08:00 AM on Mon 20 Jul 26 and finishing 05:00 PM on Mon 03 Aug 26 - REBUILDING GRANITE ROADSIDE WALL
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Monday, 03/08/26
|
Timing:
All Day
|
|
Promoter:
|
Private Individual
|
Contractor:
|
Private Individual
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - BELMONT ROAD
|
( QUEENS ROAD to LES CROUTES )
|
|
Description:
|
Work starting 12:00 AM on Mon 20 Jul 26 and finishing 05:00 PM on Fri 31 Jul 26 - Essential maintenance to gas network
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Gas
|
Contractor:
|
Guernsey Gas
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - BERTHELOT STREET
|
|
|
Description:
|
Work starting 07:30 AM on Mon 17 Mar 25 and finishing 11:59 PM on Thu 31 Dec 26 - Scaffolding at La Bigoterie no. 14.; Property: La Bigoterie no. 14; Purpose: External Decoration
|
|
Start date:
|
Monday, 17/03/25
|
End date:
|
Thursday, 31/12/26
|
Timing:
All Day
|
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LA GIBAUDERIE
|
( ROSAIRE AVENUE to DALGAIRNS ROAD )
|
|
Description:
|
Work starting 08:30 AM on Tue 21 Jul 26 and finishing 05:00 PM on Fri 24 Jul 26 - Undertake trial trenches
|
|
Start date:
|
Tuesday, 21/07/26
|
End date:
|
Friday, 24/07/26
|
Timing:
All Day
|
|
Promoter:
|
Geomarine
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
St Martin PS 1A;St Martin PS 1B;LB HS 4A Overflow
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - LES COTILS
|
|
|
Description:
|
Work starting 08:00 AM on Fri 10 Apr 26 and finishing 06:00 PM on Fri 31 Jul 26 - Erecting scaffolding.; Property: Mont Bleu ; Purpose: Roofing Works
|
|
Start date:
|
Friday, 10/04/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
Advanced Scaffolding (Guernsey)
|
Contractor:
|
Advanced Scaffolding (Guernsey)
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LES PETITES FONTAINES
|
( MOUNT HERMON to VALNORD ROAD )
|
|
Description:
|
wall repairs
|
|
Start date:
|
Saturday, 02/05/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
TNT Stonemasons
|
Contractor:
|
TNT Stonemasons
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - PIETTE ROAD
|
|
|
Description:
|
Work starting 08:00 AM and finishing 05:00 PM daily between Wed 22 Apr 26 and Thu 20 Aug 26 - ERECTING SCAFFOLDING; Property: BURNLEY; Purpose: Roofing Works
|
|
Start date:
|
Wednesday, 22/04/26
|
End date:
|
Thursday, 20/08/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Advanced Scaffolding (Guernsey)
|
Contractor:
|
Advanced Scaffolding (Guernsey)
|
|
Bus Routes Affected:
|
Vauvert PS 1B
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - QUEENS ROAD
|
|
|
Description:
|
High and low voltage cable upgrade and streetlight replacements
|
|
Start date:
|
Monday, 06/07/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
Vauvert 1B; LMDC 7A; 60;61;71;81;N4
|
Cycle Access:
|
Dismount past works
|
|
ST. PIERRE DU BOIS - RUE DU BORDAGE
|
( RUE DU CAMP AU PRETRE to RUE DE LA FONTENELLE )
|
|
Description:
|
rebuild roadside wall
|
|
Start date:
|
Monday, 15/06/26
|
End date:
|
Tuesday, 25/08/26
|
Timing:
All Day
|
|
Promoter:
|
Breton Construction
|
Contractor:
|
Breton Construction
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. SAMPSON - LA ROUTE DES CAPELLES
|
|
|
Description:
|
Reset Manhole cover
|
|
Start date:
|
Wednesday, 22/07/26
|
End date:
|
Thursday, 23/07/26
|
Timing:
All Day
|
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
Capelles 1B; 31;32
|
Cycle Access:
|
Yes
|
|
ST. SAMPSON - RONDE CHEMINEE
|
|
|
Description:
|
Low voltage cabling and distribution pillar upgrades
|
|
Start date:
|
Monday, 15/06/26
|
End date:
|
Friday, 21/08/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Guernsey Electricity
|
|
Bus Routes Affected:
|
Vale PS 1A;Vale PS 3B;SS HS 1A;SS HS 3B;SS HS 4A;SS HS 4A NEW;SS HS 5A;SS HS 6A;SS HS 7B;SS HS 8A
|
Cycle Access:
|
Dismount past works
|
|
TORTEVAL - RUE DES BROUARDS
|
|
|
Description:
|
Work starting 07:30 AM on Mon 06 Jul 26 and finishing 04:00 PM on Fri 07 Aug 26 - Erect Scaffolding; Property: Les Buttes Cottage; Purpose: Access
|
|
Start date:
|
Monday, 06/07/26
|
End date:
|
Friday, 07/08/26
|
Timing:
All Day
|
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
VALE - RUE BATEE
|
( LA BUTTE to LES GRIPPIOS )
|
|
Description:
|
Pest control - road closed between 21:00hrs and 22:30hrs
|
|
Start date:
|
Wednesday, 22/07/26
|
End date:
|
Wednesday, 22/07/26
|
Timing:
After PM Peak
|
|
Promoter:
|
ACLMS
|
Contractor:
|
ACLMS
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
VALE - SOUS LES HOUGUES; SUMMERFIELD ROAD to RUE FLERE
|
( SUMMERFIELD ROAD to RUE FLERE )
|
|
Description:
|
To construct road wall that collapsed during works.
|
|
Start date:
|
Friday, 17/07/26
|
End date:
|
Friday, 07/08/26
|
Timing:
All Day
|
|
Promoter:
|
Trant
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
Vale PS 2B;Vale PS 3B;LV HS 2A;LV HS 2B;SS HS 2B;SS HS 5A;SS HS 5B
|
Cycle Access:
|
Dismount past works
|
|
VALE - VALE-MISC54
|
( ROCQUE ES CAS to LA MOYE ROAD )
|
|
Description:
|
Deliveries and Barn renovations
|
|
Start date:
|
Tuesday, 14/07/26
|
End date:
|
Monday, 14/09/26
|
Timing:
All Day
|
|
Promoter:
|
Omega Group
|
Contractor:
|
Omega Group
|
|
Bus Routes Affected:
|
Vale PS 2B;Vale PS 3B
|
Cycle Access:
|
Dismount past works
|
|
ST. SAMPSON - ROUTE CARRE
|
|
|
Description:
|
REBUILDING ROADSIDE WALL
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
M and E Builders
|
Contractor:
|
M and E Builders
|
|
Bus Routes Affected:
|
Capelles 1A; Capelles 1B; LMDC 7A; LMDC 7B; LV 1A; SS 4A; SS 4B; SS 8A; SS 8B; P2;13;21;N1
|
Cycle Access:
|
Yes, in direction of one-way
|
|
CASTEL - RUE COHU
|
( ROUTE DE SAUMAREZ to RUE DU FRIQUET )
|
|
Description:
|
Work starting 08:00 AM on Mon 20 Jul 26 and finishing 05:00 PM on Fri 31 Jul 26 - Repairs to roadside wall
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Friday, 31/07/26
|
Timing:
All Day
|
|
Promoter:
|
Keystone Masonry
|
Contractor:
|
Keystone Masonry
|
|
Bus Routes Affected:
|
LMDC 6A / LV 6A; LMDC 7A; SS 4A; SS 4B; P2;41;42;N2
|
Cycle Access:
|
No
|
|
CASTEL - RUE DU FRIQUET
|
|
|
Description:
|
Upgrade foul manhole
|
|
Start date:
|
Monday, 20/07/26
|
End date:
|
Friday, 24/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. SAMPSON - LES GRANDES MAISONS ROAD; LES BAS COURTILS ROAD to LONGUE HOUGUE LANE
|
( LES BAS COURTILS ROAD to LONGUE HOUGUE LANE )
|
|
Description:
|
Work starting 09:00 AM on Tue 21 Jul 26 and finishing 11:59 PM on Tue 28 Jul 26 - Essential maintenance to gas network
|
|
Start date:
|
Tuesday, 21/07/26
|
End date:
|
Tuesday, 28/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Gas
|
Contractor:
|
Guernsey Gas
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
TORTEVAL - ROUTE DE LA LAGUE
|
( RUE DE LA VILTOLE to RUE DU HUREL )
|
|
Description:
|
Work starting 08:00 AM on Mon 08 Jun 26 and finishing 05:00 PM on Fri 02 Oct 26 - repair roadside wall
|
|
Start date:
|
Monday, 08/06/26
|
End date:
|
Friday, 02/10/26
|
Timing:
All Day
|
|
Promoter:
|
States Committee of the Environment and Infrastructure
|
Contractor:
|
States Committee of the Environment and Infrastructure
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
CASTEL - Grandes Rocques Super Sprint
|
|
|
Description:
|
Guernsey Triathlon LBG
|
|
Start date:
|
Sunday, 26/07/26
|
End date:
|
Sunday, 26/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Triathlon Club
|
Contractor:
|
N/A
|
|
Bus Routes Affected:
|
Capelles PS 1B;Capelles PS 2B
|
Cycle Access:
|
Yes
|
|
CASTEL - ROUTE DE CARTERET
|
|
|
Description:
|
Work starting 08:00 AM on Mon 27 Jul 26 and finishing 08:00 AM on Mon 17 Aug 26 - erect scaffolding on the iconic bridge; Property: Le Genats Bridge; Purpose: External Decoration
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Monday, 17/08/26
|
Timing:
All Day
|
|
Promoter:
|
Advanced Scaffolding (Guernsey)
|
Contractor:
|
Advanced Scaffolding (Guernsey)
|
|
Bus Routes Affected:
|
SS 8A; SS 8B; 42
|
Cycle Access:
|
Dismount past works
|
|
FOREST - LA RUE DES VILLETS
|
( LA RUE DU GOUFFRE to LES VILLETS )
|
|
Description:
|
Supply line upgrade
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Wednesday, 29/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - All Terrain Challenge 2026
|
|
|
Description:
|
Road closed from 6:30pm to 7:30pm
|
|
Start date:
|
Friday, 24/07/26
|
End date:
|
Friday, 24/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Athletics Club
|
Contractor:
|
N/A
|
|
Bus Routes Affected:
|
St Martin 3A; St Martin 3B; LB 2A; LMDC 7B
|
Cycle Access:
|
No
|
|
ST. PETER PORT - DAMOUETTES LANE
|
( HUBITS DE BAS to COURTIL COLIN )
|
|
Description:
|
New service
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Wednesday, 29/07/26
|
Timing:
All Day
|
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - DAMOUETTES LANE
|
|
|
Description:
|
Sewer Renovation Works ( GEO _ ET )
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Tuesday, 08/09/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water (Wastewater)
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - DOYLE STREET; LOWER CANICHERS to LE TRUCHOT
|
( LOWER CANICHERS to LE TRUCHOT )
|
|
Description:
|
Cherry Picker Works for Cabling
|
|
Start date:
|
Thursday, 23/07/26
|
End date:
|
Thursday, 23/07/26
|
Timing:
Between AM and PM Peaks
|
|
Promoter:
|
Sure Guernsey
|
Contractor:
|
Sure Guernsey
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PETER PORT - LA GIBAUDERIE
|
( ROCQUETTES ROAD to ROSAIRE AVENUE )
|
|
Description:
|
CRANE REQUIRED TO LIFT MATERIALS AND MACHINERY OVER HOUSES AT THE ABOVE ADDRESS
|
|
Start date:
|
Thursday, 23/07/26
|
End date:
|
Thursday, 23/07/26
|
Timing:
Before AM Peak
|
|
Promoter:
|
Stan Brouard
|
Contractor:
|
Stan Brouard
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
No
|
|
ST. PETER PORT - ROUTE DES COUTANCHEZ
|
|
|
Description:
|
Tree Surgery
|
|
Start date:
|
Tuesday, 28/07/26
|
End date:
|
Tuesday, 28/07/26
|
Timing:
All Day
|
|
Promoter:
|
CVTS
|
Contractor:
|
CVTS
|
|
Bus Routes Affected:
|
31;32
|
Cycle Access:
|
Dismount past works
|
|
ST. PETER PORT - ROUTE DES COUTANCHEZ; RUE THOMAS to LA ROUTE DES CAPELLES
|
( RUE THOMAS to LA ROUTE DES CAPELLES )
|
|
Description:
|
Work starting 08:00 AM on Wed 29 Jul 26 and finishing 05:00 PM on Wed 29 Jul 26 - Cut Off
|
|
Start date:
|
Wednesday, 29/07/26
|
End date:
|
Wednesday, 29/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Electricity
|
Contractor:
|
Trant
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes
|
|
ST. PIERRE DU BOIS - Torteval Scarecrow Festival 2026
|
|
|
Description:
|
Roads closed from 9:30am to 6:00pm
|
|
Start date:
|
Saturday, 25/07/26
|
End date:
|
Sunday, 26/07/26
|
Timing:
All Day
|
|
Promoter:
|
Torteval Scarecrow Festival
|
Contractor:
|
N/A
|
|
Bus Routes Affected:
|
Forest PS 1A;Forest PS 1B;Houguette PS 1A;LB HS 6A;LB HS 6B;LMDC HS 1A 2A;LMDC HS 1B 2B;LV HS 5A;LV HS 5A Overflow;LV HS 5B;LMDC HS LB HS 1A;LMDC HS LB HS 1B;LV HS LB HS 5A;LV HS LB HS 5B
|
Cycle Access:
|
No
|
|
ST. SAMPSON - ROUTE DU CAMP DU ROI; RUE DES ANNEVILLES to LA ROUTE DES CAPELLES
|
( RUE DES ANNEVILLES to LA ROUTE DES CAPELLES )
|
|
Description:
|
Repair water leak
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Tuesday, 28/07/26
|
Timing:
All Day
|
|
Promoter:
|
Guernsey Water
|
Contractor:
|
Geomarine
|
|
Bus Routes Affected:
|
LMDC 7A; LMDC 7B; LV 1A; LV 2B; P2
|
Cycle Access:
|
Dismount past works
|
|
ST. SAVIOUR - LA RUE DU HAMEL
|
( RUE DU DOS D`ANE to RUE DES HURIAUX )
|
|
Description:
|
Build a roadside wall
|
|
Start date:
|
Sunday, 26/07/26
|
End date:
|
Tuesday, 04/08/26
|
Timing:
All Day
|
|
Promoter:
|
Hillstone Guernsey Ltd
|
Contractor:
|
Hillstone Guernsey Ltd
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
VALE - LA MAZOTTE
|
( LA HOUGUE RICART to HOUMTEL LANE )
|
|
Description:
|
Resurfacing of roadside driveway
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Wednesday, 05/08/26
|
Timing:
All Day
|
|
Promoter:
|
Tarmac Services
|
Contractor:
|
Tarmac Services
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Dismount past works
|
|
VALE - TRAFALGAR ROAD
|
|
|
Description:
|
Erect Scaffolding ; Property: New Home Base store Project; Purpose: Access
|
|
Start date:
|
Monday, 27/07/26
|
End date:
|
Thursday, 27/08/26
|
Timing:
All Day
|
|
Promoter:
|
Access Scaffolding
|
Contractor:
|
Access Scaffolding
|
|
Bus Routes Affected:
|
|
Cycle Access:
|
Yes, in direction of one-way
|