Traffic Management (e.g. road closures and one-ways) will often be placed out in advance of the works and, unless otherwise advised, remain in place until early morning the day following the works. This is to ensure the safety of operatives setting out and collecting the signage. It also allows asphalt to cure before the road is trafficked.

Closures
CASTEL - CANDIE ROAD ( RUE A L'EAU to LES VALINGUETS )
Description: Chamber and duct installation
Start date: Monday, 10/06/24 End date: Tuesday, 18/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

CASTEL - RUETTE DE TOUILLETS ( ROUTE DE L'EGLISE to RUETTE DES PONCHEZ )
Description: Work starting 08:00 AM on Sat 19 Aug 23 and finishing 05:00 PM on Mon 30 Sep 24 - Investigation and repairs to roadside wall
Start date: Saturday, 19/08/23 End date: Monday, 30/09/24 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

ST. MARTIN - LA RUE DES ESCALIERS
Description: Chamber and duct installation
Start date: Monday, 10/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LES BLANCHES PIERRES ( LA VEQUESSE to LES TRAUDES )
Description: Repairs to broken duct
Start date: Wednesday, 12/06/24 End date: Friday, 14/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LES HURETTES
Description: Work starting 08:00 AM on Mon 03 Jun 24 and finishing 05:00 PM on Thu 20 Jun 24 - High and low voltage cabling upgrade
Start date: Monday, 03/06/24 End date: Thursday, 20/06/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - BACK STREET
Description: Scaffolding ; Property: No 3; Purpose: Demolition / New Build
Start date: Friday, 08/03/24 End date: Tuesday, 29/10/24 Timing: Between AM and PM Peaks
Promoter: Formula Scaffolding Contractor: Formula Scaffolding
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - BELMONT ROAD ( QUEENS ROAD to LES CROUTES )
Description: replacing two streetlights
Start date: Wednesday, 12/06/24 End date: Friday, 14/06/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - DOYLE ROAD ( BROCK ROAD to GRANGE ROAD )
Description: Work starting 08:00 AM on Wed 15 May 24 and finishing 05:00 PM on Wed 30 Oct 24 - Low voltage network upgrade, pillar installation and high voltage duct lay
Start date: Wednesday, 15/05/24 End date: Wednesday, 30/10/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 32 Cycle Access: Dismount past works

ST. PETER PORT - HIGH STREET
Description: Excavations required to upgrade LV network
Start date: Monday, 20/05/24 End date: Friday, 19/07/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LE BOUET
Description: Demolition ; Property: 10 Le Bouet; Purpose: Demolition / New Build
Start date: Wednesday, 12/06/24 End date: Wednesday, 24/07/24 Timing: All Day
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: 31, 32 Cycle Access: Yes

ST. PETER PORT - LES COTILS
Description: Scaffolding ; Property: La Coniere; Purpose: Carry Structural Load
Start date: Monday, 11/03/24 End date: Thursday, 11/07/24 Timing: All Day
Promoter: Access Scaffolding Contractor: Access Scaffolding
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - MOUNT ROW
Description: Work starting 07:00 AM on Mon 10 Jun 24 and finishing 05:00 PM on Fri 16 Aug 24 - High and low voltage infrastructure upgrade
Start date: Monday, 10/06/24 End date: Friday, 16/08/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: P2, 60, 61, 71 Cycle Access: Dismount past works

ST. PETER PORT - ROHAIS ( LE FOULON to COLLINGS ROAD )
Description: Service alteration
Start date: Wednesday, 12/06/24 End date: Friday, 14/06/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: 41, 42, 51, 52, N2 Cycle Access: Dismount past works

ST. PETER PORT - THE STRAND
Description: Scaffolding ; Property: La Coquere; Purpose: Demolition / New Build
Start date: Monday, 22/04/24 End date: Saturday, 31/08/24 Timing: Between AM and PM Peaks
Promoter: Impact Scaffolding Contractor: Impact Scaffolding
Bus Routes Affected: Cycle Access: Dismount past works

ST. PIERRE DU BOIS - RUE DU BORDAGE
Description: Road resurfacing
Start date: Monday, 10/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Traffic and Highway Services (Capital Works)
Bus Routes Affected: Cycle Access: No: Dismount

ST. SAMPSON - RONDE CHEMINEE
Description: Work starting 07:00 AM on Tue 04 Jun 24 and finishing 05:00 PM on Fri 21 Jun 24 - Upgrade existing water main and services
Start date: Tuesday, 04/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAVIOUR - RUE DE LA HOUGUE BACHELE
Description: Work starting 08:00 AM and finishing 05:00 PM daily between Wed 12 Jun 24 and Fri 19 Jul 24 - Scaffolding ; Property: La Hougue; Purpose: External Decoration
Start date: Wednesday, 12/06/24 End date: Friday, 19/07/24 Timing: Between AM and PM Peaks
Promoter: Scaffolding Services Contractor: Scaffolding Services
Bus Routes Affected: Cycle Access: Yes

ST. SAVIOUR - RUE DU MONT SAINT ( RUE DES HURIAUX to LE MONT SAINT )
Description: Work starting 07:00 AM on Thu 16 May 24 and finishing 05:00 PM on Mon 23 Sep 24 - Site compound
Start date: Thursday, 16/05/24 End date: Monday, 23/09/24 Timing: All Day
Promoter: Geomarine Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

VALE - RUE DES HAUTGARDS
Description: Work starting 07:30 AM on Mon 10 Jun 24 and finishing 04:00 PM on Fri 21 Jun 24 - Road resurfacing
Start date: Monday, 10/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Traffic and Highway Services (Capital Works) Contractor: Ronez (Patching)
Bus Routes Affected: Cycle Access: Dismount past works

One Ways
ST. PETER PORT - LE BOUET
Description: Work starting 08:00 AM on Thu 13 Jun 24 and finishing 05:00 PM on Wed 24 Jul 24 - Demolition and re-build property
Start date: Thursday, 13/06/24 End date: Wednesday, 24/07/24 Timing: All Day
Promoter: Just Build It Ltd Contractor: Just Build It Ltd
Bus Routes Affected: 31, 32 Cycle Access: Yes, in direction of one-way

Signals
CASTEL - RUE DE LA SALINE
Description: Repointing of seawall at La Saline - roadside compound and working area / pedestrian footway - traffic control by temporary traffic signals.
Start date: Monday, 11/03/24 End date: Friday, 19/07/24 Timing: All Day
Promoter: Property Services Contractor: Property Services
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - LA CHARROTERIE; PRINCE ALBERT ROAD to RUE DU PRE ( PRINCE ALBERT ROAD to RUE DU PRE )
Description: Node installations
Start date: Monday, 10/06/24 End date: Friday, 14/06/24 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - ST. GEORGE`S ESPLANADE ( PIETTE ROAD to BOUILLON LANE )
Description: Work starting 07:00 AM on Sun 17 Mar 24 and finishing 05:00 PM on Fri 21 Jun 24 - Excavate and lay ducting across road and through footpath
Start date: Sunday, 17/03/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: 11, 12, 13, 21, 31, 32, 51, 52, 91, 92, N1, Cycle Access: Dismount past works


Starting - next 7 days
Closures
CASTEL - LA NEUVE RUE
Description: Trial trench survey works
Start date: Wednesday, 19/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: P2, 51, 52 Cycle Access: Dismount past works

CASTEL - ROUTE DE COBO
Description: Trial trench investigation works
Start date: Monday, 17/06/24 End date: Tuesday, 18/06/24 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: P2, 41, 42, N2 Cycle Access: Dismount past works

CASTEL - RUE DES CAUVAINS ( LA NEUVE RUE to RUETTE DE LA CROIX )
Description: Chamber installation
Start date: Thursday, 20/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. ANDREW - CANDIE ROAD ( RUE DES CARRIAUX to ROUTE DE ST. ANDRE )
Description: Chamber installations
Start date: Wednesday, 19/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. MARTIN - LES CAMPS DU MOULIN
Description: Clear blocked ducts and install cables
Start date: Wednesday, 19/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - LES CAMPS DU MOULIN; VILLE AMPHREY to RUETTE RABEY ( VILLE AMPHREY to RUETTE RABEY )
Description: Replace 4 nr. manhole cover & frames
Start date: Wednesday, 19/06/24 End date: Monday, 24/06/24 Timing: All Day
Promoter: Guernsey Water (Wastewater) Contractor: Geomarine
Bus Routes Affected: 81 Cycle Access: Dismount past works

ST. MARTIN - LES PAGES ( RUE DES PAGES to LES MARTINS )
Description: Work starting 05:00 PM on Thu 20 Jun 24 and finishing 05:00 PM on Thu 25 Jul 24 - High and low voltage cabling upgrade
Start date: Thursday, 20/06/24 End date: Thursday, 25/07/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Guernsey Electricity
Bus Routes Affected: Cycle Access: No

ST. PETER PORT - COLBORNE ROAD ( RUETTES BRAYES to HAVILLAND ROAD )
Description: Work starting 09:00 AM and finishing 03:00 PM - Tree Surgery Works
Start date: Tuesday, 18/06/24 End date: Tuesday, 18/06/24 Timing: Between AM and PM Peaks
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: 91, 92, 93, 94, 95, N3 Cycle Access: Yes

ST. PETER PORT - COLBORNE ROAD ( RUETTES BRAYES to HAVILLAND ROAD )
Description: making safe rock face.
Start date: Monday, 17/06/24 End date: Tuesday, 18/06/24 Timing: All Day
Promoter: States Property Unit Contractor: States Property Unit
Bus Routes Affected: 91, 92, 93, 94, 95, N3 Cycle Access: Dismount past works

ST. PETER PORT - COLBORNE ROAD; RUETTES BRAYES to HAVILLAND ROAD ( RUETTES BRAYES to HAVILLAND ROAD )
Description: Excavate (sharing P031638-THS1 + extra day) - Carry out essential works outside Treetops, Colborne Road, St. Peter Port, GY1 1EN.
Start date: Monday, 17/06/24 End date: Wednesday, 19/06/24 Timing: All Day
Promoter: Guernsey Gas Contractor: Guernsey Gas
Bus Routes Affected: 91, 92, 93, 94, 95, N3 Cycle Access: Dismount past works

ST. PETER PORT - EADBL Seafront Sunday
Description: EADBL Seafront Sunday
Start date: Sunday, 16/06/24 End date: Sunday, 16/06/24 Timing: All Day
Promoter: SOG Sport and Culture Contractor: N/A
Bus Routes Affected: 11, 12, 13, 21, 31, 32, 41, 42, 51, 52, 60, 61, 71, 81, 92, N1, N2 Cycle Access: Dismount past works

ST. PETER PORT - LE MARCHANT STREET ( to RUE DU MANOIR )
Description: Install new water service
Start date: Monday, 17/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Guernsey Water Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - LOWER HAUTEVILLE ( CLIFF STREET to PEDVIN STREET )
Description: Chamber and duct installation
Start date: Monday, 17/06/24 End date: Wednesday, 19/06/24 Timing: All Day
Promoter: Sure Guernsey Contractor: Geomarine
Bus Routes Affected: Cycle Access: Dismount past works

ST. PETER PORT - RUE DES FRERES
Description: CCTV Camera Clean
Start date: Friday, 14/06/24 End date: Friday, 14/06/24 Timing: Between AM and PM Peaks
Promoter: Guernsey Water (Wastewater) Contractor: Guernsey Water (Wastewater)
Bus Routes Affected: Cycle Access: Yes

ST. PETER PORT - Val De Terres Hill Climb - GK&MC ( Fort Road to Castle Emplacement )
Description: Work starting 07:00 AM on Sat 15 Jun 24 and finishing 07:00 PM on Sat 15 Jun 24 - Val De Terres Hill Climb - GKandMC
Start date: Saturday, 15/06/24 End date: Saturday, 15/06/24 Timing: All Day
Promoter: GKMC - Guernsey Kart and Motor Club Contractor: N/A
Bus Routes Affected: Cycle Access: No

ST. PIERRE DU BOIS - RUE DES HECHES ( to RUE DES REINES )
Description: Service alteration
Start date: Wednesday, 19/06/24 End date: Friday, 21/06/24 Timing: All Day
Promoter: Guernsey Electricity Contractor: Trant
Bus Routes Affected: Cycle Access: Dismount past works

ST. SAMPSON - LA VIEILLE RUE ( LES GIGANDS ROAD to LE BORDAGE ROAD )
Description: House move. Large vehicle parked in front of house
Start date: Wednesday, 19/06/24 End date: Thursday, 20/06/24 Timing: All Day
Promoter: Private Individual Contractor: Private Individual
Bus Routes Affected: Cycle Access: Yes

ST. SAMPSON - ROUTE MILITAIRE ( SALTPANS ROAD to ROUTE ST. CLAIR )
Description: Tree Surgery Works
Start date: Wednesday, 19/06/24 End date: Thursday, 20/06/24 Timing: Between AM and PM Peaks
Promoter: Arbology Contractor: Arbology
Bus Routes Affected: 21 Cycle Access: Dismount past works

ST. SAMPSON - RUE SAUVAGE; LA ROUTE DES CAPELLES to LES BASSES CAPELLES ROAD ( LA ROUTE DES CAPELLES to LES BASSES CAPELLES ROAD )
Description: Repair works to defective section of tarmac.
Start date: Saturday, 15/06/24 End date: Monday, 17/06/24 Timing: All Day
Promoter: Traffic and Highway Services (Highways Inspector) Contractor: Geomarine
Bus Routes Affected: 31, 32 Cycle Access: Dismount past works

One Ways
CASTEL - CASTEL - Classic Vehicle Show 2024 Saumarez Park
Description: Classic Vehicle Show 2024 Saumarez Park
Start date: Sunday, 16/06/24 End date: Monday, 17/06/24 Timing: All Day
Promoter: Private Individual Contractor: N/A
Bus Routes Affected: P2, 41, 42, N2 Cycle Access: Yes, in direction of one-way

CASTEL - RUE DE BOUVERIE; RUETTE DE LA TOUR to ROUTE DE CARTERET ( RUETTE DE LA TOUR to ROUTE DE CARTERET )
Description: Node and CBT installation
Start date: Thursday, 20/06/24 End date: Friday, 21/06/24 Timing: Between AM and PM Peaks
Promoter: Sure Guernsey Contractor: Sure Guernsey
Bus Routes Affected: Cycle Access: Yes

Signals
No future major delays due to signals